Resume

Sign in

Manager Engineer

Location:
Cairo, Cairo Governorate, Egypt
Salary:
40000+car
Posted:
September 25, 2018

Contact this candidate

Resume:

CURRICULAM VITAE

Personal Data

Name : Salah Nos'hey Abdalla

Position : Project Manager

Date of birth : 09/04/1967

Main profession : Civil Engineer

Nationality : Egyptian

Language : English, Arabic

Marital status : Married (w/3 children)

Mobile :

+201********* - Egypt

Passport No. : A17527010 / Egypt

Date of Issue : 02/02/2016

Expire Date : 01/02/2023

E-mail : ac658i@r.postjobfree.com

EDUCATION AND PROFESSTIONAL STATUS

Education : B.Sc. 1991-Cairo University Faculty of Engineering

Major: Civil Engineering, Good

PROFESSIONAL EXPERIENCE:

Experiences : twenty seven years’ experience in construction & management field.

Recent Position : Project Manager

Company : NOVUS STANZA

From .May 2018 up to Date.

Company Name : NOVUS STANZA

Position : Project Manager

Project Name : LIBERTY VILLAGE

: New Capital

Client : NOVUS STANZA

Designer : YBA

From Feb.2018 up to May 018

Company Name : Hassan Allam Constriction (HAC)

Position : Construction Manager

Project Name : AL Mansoura -2

: New Capital

Client : IC

Designer : UG-5

From Apr.2016 to Apr.2017.

Company Name : Alghanim International (AGI)

Position : Snr Construction Manager

Project Name : AL ZOR NRP

: New Refinery Project -Kuwait

FDH -JV Flour - Daewoo- Hyundai

Al Zor - KUWAIT

Client : KNPC -Kuwait National Petroleum Company

Designer : SSH International Consultant

From Mar.2014 up to Date.

Company Name : Alghanim International (AGI)

Position : Construction Manager

Project Name : SheikhAbdullah Al Salem

: Cultural Center

Al siekh Abd Ullah Alsalem Cultural Center

KUWAIT

Client : Al Diwan Al Amiri

Consultant : SSH International Consultant

From Jul.2012 up to Feb.2014

Company Name : Civil Home

Position : Project Manager

Project Name : Landscape &External works. (Finishing)

: Hyde Park

: New Cairo -Egypt

Client : Damac

Management : Damac

Consultant : Site International

From Oct. 2010 up to Jul 2012

Company Name : Orascom Construction Industries (OCI)

Position : Construction Manager

Project Name : Abu Qir thermal Station

: 2*650 MW

: Abu Qir -Alex

Client : Ministry of electricity (Egypt)

Management : Pegesco

Consultant : Pegesco

From Jan.2010 up to Oct. 2010

Company Name : Square engineering firm

Position : Project Manager

Project Name : 85 residential villas

: Allegria project

: Zayed city

Client : SODIC

Management : Turner

Consultant : ECH

From Jul. 2004 up to Dec. 2009

Working for: Al Shafar Transport &Contracting Co. U.A.E (ASTCC)

From Jun... 2008 up to Dec. 2009

Company Name : Al Shafar Transport &Contracting Co. U.A.E - (ASTCC)

Position : project Manager

Project Name : Jadaf Pearl &10 mock up villas (jabl Ali Palm)

Client : 1-Al shafar development co (Jadaf project)

: 2- Nakheel (jabel Ali palm)

Scope of work:

aConstruction and finishing of residential building at Jadaf area-Dubai

bConstruction and finishing 10Mock up for luxury villas at jabel Ali palm

From Oct. 2006 up to Jun 2008

Company Name : Al Shafar Transport &Contracting Co. U.A.E (ASTCC)

Position : Deputy Project Manager

Project Name : Discovery Gardens Project

Contract value : 500 Million Dhs.

Client : Nakheel

Management : Turner

Consultant : Engineering Consultant Group (ECG)

Scope of work

Construction and finishing of 12 residential buildings

At Discovery Gardens Consisting of

12 nos Multi-storey (Ground plus 8 Floors) Residential Buildings

Basement under Ground common parking

Handing over the project (test &commissioning)

Maintenance the project through the warrantee period

From Aug. 2005 up to Sep. 2006

Company Name : Al Shafar Transport &Contracting Co. U.A.E (ASTCC)

Position : Construction Manager

Project Name : INTERNATIONAL CITY –JAP 015/4-3

RESIDENTIAL /COMMERCIAL BUILDINGS) PACKAGE 3

Contract value : 250 Million Dhs.

Client : Nakheel

Management : Dress and Sommer

Consultant : Associated consultant engineers int'l (ACE)

Scope of work

Construction and finishing of 27 residential &commercial buildings

5 nos stories (Ground plus 4 Floors) Residential Buildings

From Jul. 2004 up to Jul. 2005

Company Name : Al Shafar Transport &Contracting Co. U.A.E (ASTCC

Position : Senior Engineer

Project Name : INTERNATIONAL CITY –JAP 015/3

(CHINAMEX MART-DRAGON MART

Contract value : 250 Million Dhs.

Client : Nakheel

Management : Drees and Sommer

Scope of Work

Completing the Finishing the china Mexmart (Dragon Mart)

Handing over for the China Mexmart to client and end users

Completing the finishing for ware houses of China Mexmart)

Handing over the project (test &commissioning)

Maintenance the project through the warrantee period

From Jul. 1998 up to Jun. 2004

Working for SONID GROUP

From Jul. 2003 up to Jun. 2004

Company Name : Master line for tourist projects

Position : Finishing Manager (Responsible for finishing package)

Project Name : Fanadir resort & hotel (5 stars hotel) Hurgada, Egypt

Contract value : 400 Million Egyptian pounds for construction & finishing

Works

Client : Master line for tourist projects

Management : Costain – Samcrete project Management S.A.E.

Scope of work

Finishing of 5 star hotel consisting of 400 rooms at Hurgada – Egypt

Coordinate finishing at public areas

Construction of swimming pools, lake and utility building

From Jun. 2001 up to Jun. 2004

Company Name : Encorp International Inc. (USA)

Position : Site Manager

Projects Name : F-16 Depot Facilities, Egypt

Contract value : 15 Million Dollars

Client : Egyptian Air Force

Management : U.S.A Corp. of Engineers

Scope of work

Bead Blast Building

1Erection & Finishing Bead Blast Building

2Steel structure building

3Complete system of media blast

4High grade finishing of flooring

5High finishing material by using Kemply cladding system

6Erection of swing plenum door

Steel Bolted Tanks

1Erection of 2 steel bolted tanks with capacity of 1500 m2 for firefighting system

Fire Fighting System

1Erection of FFL to many building in F-16 project with length of 1.5 km - 20 inches

2Erection of complete system for FFS at fire pump house for all airport

3Handing over the project (test &commissioning)

4Maintenance the project through the warrantee period

From Aug. 2000 up to May, 2001

Company Name : Costain – Samcrete project Management (UK)

Position : Coordinator &Supervisor Engineer

Project Name : Sainsbury's Project Going Home

Budget : 60 Million Egyptian pounds

Client : Sainsbury's

Management : Ove Arup (UK)

Scope of Work

a- Finishing & modifying of existing multi stories building to be a head administration for Sainsbury's group

From Jul. 1999 up to Jul. 2000

Company Name : COSTAIN – Samcrete Project Management (UK)

Position : Coordinator &Supervisor Snr. Engineer

Project Name : Verdi Hotel – Hugged

Contract value : 40 Million Egyptian pounds

Client : Master line for tourist projects

Management : Contain – Secrete Project Management (UK)

Scope of work

Construction and finishing 4 stars hotel consisting of 150 rooms

Furniture of 150 rooms

Construction and finishing the new Reception building & restaurant

From Jun. 1998 up to Jun. 1999

Company Name : Master line for tourist projects

Position : Client Represented& Supervisor Engineer

Project Name : Aida Hotel – Hurgada

Contract value : 52 Million Egyptian pounds

Client : Master line for tourist projects

Scope of work

Construction and finishing 4 stars hotel consisting of 100 rooms.

Furniture of 100 rooms

Construction and erection of the equipment's for the Kitchen

Construction and finishing of swimming pool for the hotel.

From May. 1997 up to Jul. 1998

Company Name : Archilab for consultancy services

Position : Supervisor Engineer & Q.S. Engineer

Project Name : Dar El Markabat & ophthalmic Hospital Renovation

Contract value : 6 Million Egyptian pounds

Client : Armed forces & Ministry of Health

Scope of work

Construction & finishing works of the Pharanoiac hall

Renovation of Dar Al Markabat hotel

Repair the concrete works for the hotel building

Construction, finishing works & Renovation of the ophthalmic hospital

From Jun, 1995 up to Apr. 1997

Company Name : Consultant Group for Reconstruction

Position : Coordinator, Supervisor Engineer & Q.S. Engineer

Project Name : Egyptian Central Hospital (VFI)

Contract value : 5.5 Million Egyptian pounds

Client : Egyptian Central Hospital (VFI)

Scope of work

Construction & finishing of multi stories building in Maddi

Finishing of 2 surgery rooms

Finishing of lab for the (VFI) procedures.

From Apr. 1994 up to May. 1995

Company Name : Consultant Group for Reconstruction

Position : Supervisor Engineer & QS Engineer

Project Name : Al – Akkad Shopping Mall

Contract value : 48 Million Egyptian pounds

Client : Al-Akkad Group

Scope of work Construction of the Al-Akkad Mall, Naser City

Construction of multi stories 6 buildings

Coordinate between MEP works and construction activities

Computer skills : Good practice of software programs.

Testimonials will be furnished upon request



Contact this candidate