WORK EXPERIENCES:
Company : DAELIM-PETROFAC JOINT VENTURES
Project : SOHAR REFINERY IMPROVEMENT PROJECT
Address : Falaj Al-Qabail P.O. Box 537, 322 Sohar Sultamate Of Oman
Position : Piping Supervisor
Date : May 14,2016 – March 30, 2017
Proponent : Oman Oil Refineries & Petroleum Industries Company (ORPIC)
Reason for leaving : Project Completion
SCOPE OF WORK
Prepare daily reports of work progress and manpower utilization.
Prepare weekly reports of the total spool erection, isometric weight installed, welded dia inches of supports and joints and the remaining work front with the material available.
Co-coordinate with the sub contractors to achieve the targets and schedule set by the planning.
Conduct the safety walk through in the site in co-ordination with the safety department on weekly basis.
Supervision of all piping works and ensures safety and quality standards of all client.
Inspection and approval of all the QA/QC submittals of the subcontractor.
To study the isometric drawing received from the clients and to identify the pipe lines and carry out the inspection work.
Check flow direction arrows on valves: verify that they are properly identified and valves are installed in accordance with the piping drawings and the pipe support details.
Monitoring the QA/QC Documentation of the subcontractors and ensure that all activities are incorporated to their system on daily basis and can be traced according to our requirements.
Line check to verify the use of correct material fittings, punch list for incomplete works, check and closing after the work is done.
Issue the work permits ensuring SHE requirements.
Company : DAELIM SAUDI ARABIA CO. LTD.
Project : Saudi Elastomer Project
Address : AL Jubail Kingdom of Saudi Arabia
Position : Piping Supervisor
Date : May 19,2014 – May 19,2015
Proponent : AL Jubail Petrochemical Co.(KEMYA)
Reason for leaving : Project Completion
SCOPE OF WORK
Prepare all necessary documents needed in construction works
Praparation of underground piping
Praparing test packages for gravity test and hyro test
Line checking completed under ground piping
Supervise of sub constructors
Company : DAELIM SAUDI ARABIA CO. LTD.
Project : (YASREF ) Yanbu Aramco Sinopec Refining Co.
Address : Yanbu City, Kingdom Of Saudi Arabia
Position : Piping Supervisor
Date : May 31,2013 – March 31,2014
Proponent : Aramco
Reason for leaving : Project Completion
SCOPE OF WORK :
Prepare all necessary documents needed in construction works
Supervise all the installation of all types of piping works
Inspection of all pipe line completion
Company : DAELIM SAUDI ARABIA CO. LTD.
Project : (JERP) Jubail Export Refinery Project 2B
Address : Jubail, Industrial City
Position : Piping Supervisor
Date : February 19, 2011 –May 31,2013
Proponent (SATORP) Saudi Aramco Total Refinery &
Petrochemical Company
Reason for leaving : Project Completion
SCOPE OF WORK :
Prepare all necessary documents needed in construction works
Prepare test package for line checking
Coordination with sub constractors
Inspection of pipe line completion
Company : CHIYODA TECHNIP JOINT VENTURE
Project : Qatar gas 3 & 4 LNG Onshore Projects
Address : Doha, Qatar
Position : Piping Supervisor
Date : April 26, 2009 - March 30, 2010
Proponent : Qatar Gas / ConocoPhillips / Shell (QCS)
Reason for leaving : Project Completion
SCOPE OF WORK :
Prepare all necessary documents needed in construction works.
Line checking and punch clearing test packages.
Check test pack piping system equipped with vent at highest point and
drain at lowest points.
Confirm flange alignment, parallelism bolt torquing and tensioning.
Confirm all lines installed are vertical / level / slope as per iso
Installation of correct permanent gaskets confirmed.
Fabricate & install 90 tones of pipe supports.
NDT Inspection
Hydrotesting
Understanding P&ID
Company : TOYO ENGINEERING CORP.
Project : Yanbu National Petrochemical Company (YANSAB)
Ethylene Oxide / Ethylene Glycol project.
Address : Yanbu, Saudi Arabia
Position : Piping Supervisor
Date : July 04,2007 – January 31, 2009
Proponent : Foster wheler
Reason for leaving : Project Completion
SCOPE OF WORK:
Prepare all necessary documents needed in supervising construction works.
These includes isometric drawings, piping plot plan.
Supervise the installation of all types of piping works.
Prepare test package for line checking.
Monitor daily activities on site and coordinate with design engineer any changes needed in the working drawing due to actual on site. prepare FRI if required.
Company : TOYO ENGINEERING CORP.
Project : South Pars Gas Field Development Phase 6, 7 & 8
Address : P.O. Box 75391-193, Assluyeh, Busher Province, Iran
Position : Piping Supervisor
Date : December 17, 2005 – June 02,2007
Reason for leaving : Project Completion
SCOPE OF WORK:
Supervises the Hydrostatic and Pneumatic test of various pipes
Line checking and Punch clearing test packages
Coordinates with the construction, QA/QC and pre-commissioning groups
Company : EXTENDED STEEL FE INC.
Project : Bulacan Paper Mill
Address : Bo. Osorio, Trece Martires City
Position : Piping Supervisor
Date : March 18, 2005 – November 20, 2005
Reason for leaving : Project Completion
SCOPE OF WORK:
Supervises the fit-ups and completion of various sizes of pipes for steam line
Inspection during erection and transporting of pipe from finish mill to SILO
Company : EEI CORPORATION
Project : Kalayaan Pump Storage Power Plant II
Address : CBK, Kalayaan, Laguna
Position : Piping Inspector
Proponent : IMPSA
Date : October 1, 2003 to August 29, 2004
Reason for Leaving : Project Completion
SCOPE OF WORK:
Inspection of all various sizes of pipes for dewatering system, oil and air lines.
Inspection during Alignment of pumps drive motors at waste water treatment
Inspection during Erection of 4 unit pressurized tank for lube oil supply.
Company : TOYO ENGINEERING CORP.
Project : Petrokemya Polyethylene Project
Address : Kingdom of Saudi Arabia
Position : Piping Supervisor
Proponent : PKPE
Date : November 15, 2002 to September 14, 2003
Reason for Leaving : Project Completion
SCOPE OF WORK:
Supervise Inspection of Piping Line Completion
Checking of Latest Isometric, Supports and P& ID
QC Coordination during Piping Pressurizing
Coordination with Construction Team.
Company : EEI CORPORATION
Project : San Roque Multipurpose Project
Address : San Roque San Manuel, Pangasinan
Position : Mechanical Foreman
Proponent : ABB-ALSTOM
Date : February 5, 2001 to August 30, 2002
Reason for Leaving : Project Completion
SCOPE OF WORK:
Erection /Assembly 6 units radial gate
Erection of trunion base arm 12 units
Coordination of pipes for tellus oil, for cervomotors 12 units.
Company : EEI CORPORATION
Project : CME-PEG Cement Plant Project
Address : Bo. Bigte, Norzagaray, Bulacan
Position : Mechanical Foreman
Date : July 25, 2000 to December 22, 2000
Reason for leaving : Project Completion
SCOPE OF WORK:
Lay-out, cutting and fit-up all cement plant accessories.
Erection / installation of conveyor briges.
Company : EEI CORPORATION
Project : RCBC Plaza
Address : Ayala Ave., Makati City
Position : Mechanical Fitter
Proponent : Mitsubishi Heavy Industries (MHI)
Date : November 4, 1999 to July 21, 2000
Reason for Leaving : Project Completion
SCOPE OF WORK:
Alignment of 7 units 2000 kW diesel generator
Alignment/ installation of mufflers or genset
Erection/ installation of expansion join for mufflers of diesel generator
Run testing, commissioning
Fet-up various size of pipe for steam, chemical and air lines.
Start-up commissioning work
Company : EEI CORPORATION
Address : Sta. Maria Bauan, Batangas City
Position : Mechanical Fitter
Project : Fabrication Shop
Date : February 22, 1997 to March 12, 1999
Reason for leaving : Project Completion
SCOPE OF WORK:
Assembly of fit-up of any kind of pressurized tank or non pressured tank.
HIGHEST EDUCATIONAL ATTAINMENT
College : Cagayan Capitol College
Course : Bachelor of Science in Mechanical Engineer
Date Graduated : March 1985 / Under board
SEMINARS ATTENDED
Total Quality Management March 1999
(EEI Corporation)
PTW Training course August 2009
PMC Training course September 2009