Objective
Project Engineer
Summary
> Over 12 years of EPC experience in fields of heavy oil and power as
a result oriented project engineer
> Extensive background in prioritizing, coordinating and leading
execution activities
> Knowledge of project management principles, and project life cycle
consistent with PMI standards
> Skillful at estimating, planning, progressing and completing
projects accurately on time and within budget
> Expert in preparing scope of work, managing changes and their
effects and probable risks
> Able to work with technical software such as Auto-CAD, Caesar and
Tank
Professional Experience
Project Engineer - IWPC Company (2003
- 2013)
> Generated 12% per year more revenue by completing two new plants
> Prepared project time schedules, cost break down and QC plan and
assessed projects by these benchmarks
> Well-developed Critical Path of the project and focused on that area
> Conducted executive procedures and enforced project team in order to
reach projects targets
> Managed design and field changes and removed conflicts before
project cope with problems
> Investigated and decreased 83% of vendors claim
> Documented project by general and technical reports
> Participated and coordinated site visits and project meetings with
Client and Consultant
Project Engineer - Sabir Company (2010
- 2013)
> Coordinated and reviewed more than 70 construction work package
(CWPs)
> Managed all changes in different stages of project engineering,
procurement and construction
> Prepared master and detail plans for all phases of project in order
to meet project deadlines
> Pre-evaluated vendors and reviewed technical bid evaluation,
deviation and clarification list and selected more efficient
suppliers
> Integrated and expedited manufacturing procedures in order to ensure
that all equipment delivered on time
> Navigated factory acceptant test based on the ITP and released
trustable equipment
Mechanical Lead Engineer - Pishgaman Fanandish Tehran Company
(2007 - 2010)
> Managed tender offers for five bids and earned two new projects for
my company during those 3 years
> Outsourced design activities and reduced the cost of design stage
> Conducted project core team to compromise technical specification
within contract
> Prepared new technical offers in order to construct more cutting
edge projects
> Rearranged site general arrangement and gained considerable benefits
> Updated and shared knowledge and procedures on all relevant
mechanical engineering aspects
> Contributed to preparing WBS, CBS, CPM and Time Schedule in order to
framed and controlled project
Mechanical site supervisor - Moshanir Consultant Engineer
(2001 - 2003)
> Controlled equipment delivery by project plan, repacked equipment
with packing list
> Reported equipment delivery and installation situation to the site
manager in order to ensure activities followed by project time
schedule
> Supervised pipelines construction and welding procedures in order to
reach minimum probable defects
> Tested fix and rotary equipment after installation and during pre-
commissioning procedures
> Approved needed work permit, field change notices, As built
drawings, test sheets and final books
> Managed interfaces among different contractors and prepared suitable
condition Part time job
EDUCATION & CREDENTIALS
> M.Sc. Degree in Mechanical Engineering (2005)
Sharif University of Technology - Tehran, Iran - 2 years study
> B.Sc. Degree in Mechanical Engineering (2000)
Kerman University, Kerman, Iran - 4 years study
Training & Skills
Skill Organization Date Grade
Principles of Negotiations Course TETYS International 2013 -
An Introduction to FIDIC course TETYS International 2013 -
Principles of Communications Course TETYS International 2013 -
Intermediated in CEASAR II Novin Parsian 2013 92/100
Principles of Team Working Course TETYS International 2012 -
NDT Procedures Kavosh Company 2002 -
Prime project management professional PrimeLearning.com 2011 46PDU
Prime Manager PrimeLearning.com 2011 36PDU
Advanced in 2D Auto-CAD and intermediated in 3D Tehran Institute of 2009 95/100
Auto-CAD Technology
PFD & PID Faragostaran 2007 -
Project Management based on PMBOK Industrial Management 2007 92.5/10
Institute 0
Advanced in windows (XP&7) Self-developed - -
Advanced in Microsoft Office (Word, Excel, Power Self-developed - -
Point & Visio)
Intermediated in Tanks Self-developed - -
MEMBERSHIPS & ASSOCIATIONS
> Iranian Society of Mechanical Engineers (ISME), 2001- Present
> Approved by Engineers Australia as Professional Mechanical Engineer,
2010
> Nominated members for American Society of Chemistry (ASC), 2013
REFRENCES
> Will be provided upon your request
Full Time Student in LINC Program - Maple Leaf Academy, Calgary, Canada,