LYUDMILA KONNOVA

*** **** ******, #.**

BROOKLYN, NY 11220

Tel.: 718-***-**** (Home)

718-***-**** (Cell)

Email: ********.*******@*****.***

Objective:

Seeking position mechanical estimator in the fields of civil and

industrial construction

cost estimating.

Summary:

Extensive experience in the construction and engineering industry.

Specializing in mechanical, fire protection, power plants, and

plumbing systems.

Capital, budgetary and conceptual cost estimates and proposal pricing

project design, cost estimating of mechanical systems for New York

City

commercial projects at all levels of design, and construction covering

wide spectrum

of building types - residential, commercial, and transportation

facilities.

Proficient in:

- All levels of cost estimating for construction projects (mechanical

portion).

- AutoCAD, Microsoft Word & Excel, MCACES, and Timberline.

Experience:

ACCU-COST Construction Consultant, Inc. New York, NY

2004-2010 Mechanical Estimator

- Was responsible for providing all levels of budgeting for various

construction projects.

- Performed conceptual estimating with minimal information and have the

ability to visualize.

- Projects range in size from under $100,000 to over $300 M,

manufacturing, schools

and colleges, parks, zoos, and governmental facilities.

- Estimated services predominately for fixed price bidding and design

reviews.

Take-Offs and Cost Estimating of:

- Plumbing, including pumps, heaters, non-pressure vessels, fixtures,

and piping.

- Power plants & HVAC systems, including air handling units, chillers,

fans, humidifiers, boilers,

turbines, heaters, cooling towers, ducts, etc,

- Fire Protection, such as sprinkler systems, and equipment.

- List of the cost estimating for Companies see sh.3.

Fronek Company Inc, New Jersey

1998-2004

Mechanical Designer

Performed for the power plants:

- Pipe support design related to seismic and non-seismic categories of

piping.

- Mechanical design and stress analyses of the pipe shields

- Stress analyses of the piping systems (Calculations were performed by

CEASAR program).

- Hunger location and load calculation.

- Estimate of piping systems and hangers.

-1-

State Design Energy Company, Ukraine.

1978-1997

Lead Design Mechanical Engineer

Project Estimator

- Provided schematic, design development and detailed estimates of

equipment, construction, and maintenance costs for various projects

such as wastewater treatment facilities, machine shops, power plants

and other industrial buildings.

Made material and labor take-offs from drawings, coordinated

availability of equipment with suppliers, and evaluated alternatives

for different plumbing and water supply systems.

Mechanical engineer

-Designed and drafted plumbing and water supply systems, steam

distribution systems

and HVAC system for power plants, commercial and residential areas.

- Coordinated all work with architects and engineering trades.

- Assured compliance with building codes and safety regulations.

- Made site inspections to ensure compliance with drawings.

- Provided preliminary and detailed estimates of equipment and

construction costs for

various projects such as power plants, (all mechanical parts)

Education: State Polytechnic University Kiev, Ukraine

B.S. / M.S. Mechanical Engineering

American Training Center, INC., Forest Hills, NY

Advanced Courses in Computer Aided Design and Drafting using AutoCAD.

New York University, Manhattan, NY

Advanced Courses in Construction and Mechanical Estimating

-2-

LYUDMILA KONNOVA

350 65th STREET, #.5A

BROOKLYN, NY 11220

Tel.: 347-***-**** (Home)

347-***-**** (Cell)

Email: ********.*******@*****.***

LIST OF COMPANIES (ESTIMATING PERFORMED ON MECHANICAL PORTION IN ACCU COST)

US Army Medical Research

(Performed on "MCACES, 2nd Generation (MII))

. Institute of Chemical Defense (USAMRCID) Edgewood, MD - $

354.29M

. Institute of Infection Diseases (USAMRIID) Fort Detrick, MD -

$ 677.08M

Hospitals/ Medical Centers

. Jacoby Medical Hospital, Bronx - $ 4.8M

. Kings County Hospital, Brooklyn - $ 3.2M

. Sagamore Children's Psychiatric Center, NJ - $ 4.4M

Transportation (MTA, TBTA, Port Authority)

(Performed on "MCACES, 2nd Generation (MII))

. USACE TBTA - NYCDOT Hazard Mitigation for East River Bridges

Manhattan Bridge - $ 160.2M

. Brooklyn Bridge - $ 103.9M

. Queensboro Bridge - $ 153.8M

. Williamsburg Bridge - $ 102.5M

. MTA - Cross Bay Bridge, NY - $ 41.8M

Universities

. Jay John College of Criminal Justice, 899 10th Ave., NYC - $

214.2M

. CUNY - Fitterman Hall, NYC - $ 160.8M

. Housatonic Community College, CT - $ 39.2M

. The Leadership Institute at Fordham Library, Bronx - $ 16.7M

. University of Virginia - Radiology Lab's Renovation - $ 9.2M

. Tuffts University - Bio-Containment Lab's Renovation - $ 22.5M

. Montclair University, Finley Hall, NJ - $ 8.4M

Residential/ Condos/ Hotels

. Banana Townhouses and Condos, Weehawken, NJ - $ 133.5M

. Epstein Redevelopment (3 buildings), Morristown, NJ - $ 120.4M

. Covenant House, NYC - $ 31.0M

. Courtyard of Marriott, Farmingdale, NY - $ 25.2M

Others

. Xanadu Meadowlands, NJ - $ 681.6M

. Ocean County Jail Expansion, NJ - $ 53.3M

. Federal Building US Land Port of Entry, Calais, Maine - $ 51.7M

. Home Depot, Bellport, NY - $ 19.9M

. SCA and NJ EDA Schools

-3-