Project Manager Engineer

Location:
Pompano Beach, FL, 33076
Posted:
March 17, 2011

Contact this candidate

Resume:

FRED LESTER

**** ** **** ***

CORAL SPRINGS, FL *3067

EMPLOYMENT HISTORY

FOSTER MARINE CONTRACTORS, INC. WEST PALM BEACH, FL

**/**** - *******

SENIOR PROJECT MANAGER/BRANCH MANAGER - POMPANO BEACH OFFICE

RESPONSIBLE FOR THE COMPLETE EXECUTION AND CONSTRUCTION OF EACH PROJECT

FROM POST BID THROUGH TO FINAL COMPLETION. RECENT PROJECTS INCLUDE: $30

MILLION CITY OF FT.LAUDERDALE WATER & WASTEWATER 2011 PROGRAM. OPEN CUT

INSTALLATIONS IN HEAVY TRAVELED ROADWAYS AT 22' DEPTH AND DEWATERING IN

ENVIRONMENTALLY SENSITIVE AREAS. $12 & $8 MILLION WATER, SANITARY SEWER,

STORM DRAINAGE AND MILES OF ROADWAY CONSTRUCTION FOR BROWARD COUNTY WATER &

WASTEWATER SERVICES NEIGHBORHOOD IMPROVEMENT PROJECTS. $3.7 MILLION

BROWARD COUNTY SHORT WATER & SEWER WORK ORDER ANNUAL CONTRACT.

LANZO CONSTRUCTION, POMPANO BEACH, FL

6/1995 - 11/1996

PROJECT ENGINEER

RESPONSIBLE FOR MATERIAL PROCUREMENT, SHOP DRAWING REVIEW, SCHEDULING,

OWNER-ENGINEER CORRESPONDENCE, CHANGE ORDERS AND TROUBLESHOOT FIELD

PROBLEMS FOR MUNICIPAL WATER AND SEWER PROJECTS RANGING FROM $1 MILLION TO

$6 MILLION IN CONTRACT VALUE.

RONNY TURNER CONSTRUCTION, CONOVER, NC

9/1994 - 5/1995

ESTIMATOR FOR VARIOUS PIPELINE PROJECTS IN THE CAROLINAS AND VIRGINIA.

SUPERINTENDENT ON 24" WATER LINE IN UNION CO., NORTH CAROLINA.

BRYANT ELECTRIC INC., HIGH POINT, NC

9/1993 - 9/1994

PROJECT MANAGER

RESPONSIBLE FOR CONSTRUCTION FOR 4.5 MILES OF 48" PCCP RAW WATER LINE FOR

THE CITY OF NORFOLK, VA. THE LINE INSTALLED IN A HEAVY TRAVELED STREET AT

DEPTHS OF UP TO 20' WITH NUMEROUS EXISTING UTILITY CROSSINGS. RESPONSIBLE

FOR OWNER-ENGINEER CORRESPONDENCE, PAY REQUESTS, CHANGE ORDERS, SCHEDULING

OF MATERIALS AND SUB-CONTRACTORS.

WESTERN WELTEK, SALT LAKE CITY, UT

2/1992 - 9/1993

PROJECT MANAGER

RESPONSIBLE FOR CONSTRUCTION OF 32 MILES OF 10" AND 16" GAS LINE FOR

ENTERPRISE PRODUCTS COMPANY, HOUSTON, TX. RESPONSIBLE FOR INSTALLATION AND

WELDING OF 9,000 LF OF 102" DIAMETER STEEL LINER INSIDE AN EXISTING 108"

PRE-STRESSED RAW WATERLINE FOR COASTAL WATER AUTHORITY, HOUSTON, TX.

GARNEY COMPANIES, INC., KANSAS CITY, MO.

8/1990 - 2/1992

CONSTRUCTION MANAGER

RESPONSIBLE FOR ESTIMATING VARIOUS HEAVY CIVIL PROJECTS AND MANAGING FIELD

OPERATIONS ON MUNICIPAL PIPELINE AND ENVIRONMENTAL PROJECTS IN VIRGINIA AND

MARYLAND

JOHN D. STEPHENS, INC., STONE MOUNTAIN, GA

1985 - 8/1990

PROJECT MANAGER

$6 MILLION WATER PIPELINE FOR FAIRFAX COUNTY, VA. WATER AUTHORITY. PROJECT

CONSISTED OF 6 MILES OF 54" BUTT WELDED STEEL AND DUCTILE IRON PIPE.

ESTIMATOR FOR INITIAL PROJECT BID AND MANAGEMENT OF ALL FIELD OPERATIONS.

(8/1988 - 8/1990) PROJECT MANAGER: $37 MILLION RAW WATER PIPELINE FOR

TARRANT COUNTY, TX. WATER CONTROL BOARD. PROJECT CONSISTED OF 36 MILES OF

90" DIAMETER PRE-STRESSED CONCRETE PIPE. RESPONSIBLE FOR ALL FIELD

OPERATIONS. (8/1985 - 8/1988)

PAUL N. HOWARD COMPANY, GREENSBORO, NC

1979 - 1985

PROJECT MANAGER

RESPONSIBLE FOR ENTIRE FIELD OPERATIONS, PROJECT BUDGET AND COST CONTROL,

OWNER-ENGINEER CORRESPONDENCE, PREPARATION OF CHANGE ORDERS, COORDINATED

SUB-CONTRACTORS AND FIELD PURCHASING ON THE FOLLOWING PROJECTS:

$14 MILLION SEWER INTERCEPTOR FOR THE CITY OF WINSTON-SALEM, NC.

$2 MILLION CO2 GAS GATHERING PIPE SYSTEM FOR AMERADE-HESS OIL COMPANY,

SEMINOLE, TX.

$14 MILLION SITE FACILITIES AND TRACK-WORK PROJECT FOR METRO-RAIL, DADE

COUNTY, FL.

$18 MILLION JOINT VENTURE PROJECT FOR LITTLE BLUE SEWER AUTHORITY, KANSAS

CITY, MO.

$3 MILLION SEWER INTERCEPTOR FOR THE CITY OF HIGH POINT, NC.

BREECE AND BURGESS, INC. GREENSBORO, NC

1974 - 1979

PROJECT MANAGER

RESPONSIBLE DUTIES INCLUDING CONSTRUCTION LAYOUT, MATERIAL COORDINATOR AND

SUPERVISION OF TWO PIPE INSTALLATION CREWS ON VARIOUS PROJECTS LOCATED

THROUGHOUT THE CAROLINAS AND VIRGINIA. PROJECTS CONSISTED OF MID TO LARGE

DIAMETER SHEETING, CONCRETE PIERS AND ENCASEMENTS.

LAMBETH CONSTRUCTION CO., GREENSBORO, NC

1972 - 1974

JUNIOR ESTIMATOR FOR UTILITY AND HIGHWAY CONTRACTOR. DUTIES INCLUDED PRE-

BID TAKE-OFF, SUB-SURFACE INVESTIGATIONS WITH SEISMOGRAPH AND DRILL RIG AND

PREPARATION OF MONTHLY PAY ESTIMATES.

HUGH CREED AND ASSOCIATES, GREENSBORO, NC

1969 - 1972

SURVEY PARTY CHIEF AND INSTRUMENT MAN FOR THIS ENGINEERING FIRM. DUTIES

INCLUDED PROPERTY AND CONSTRUCTION LAYOUT FOR WATER AND SEWER PIPELINES AND

ROAD.

EDUCATION

GULFORD TECHNICAL COMMUNITY COLLEGE, JAMESTOWN, NC

MAJORED IN CIVIL ENGINEERING, CONSTRUCTION TECHNOLOGY

GRADUATED BEN L. SMITH HIGH SCHOOL, GREENSBORO, NC

TRAINING

OSHA EXCAVATION, COMPETENT PERSON, CONFINED SPACE & HAZARDOUS ATMOSPHERE

PETROCHEMICAL PLANT SAFETY

EXCAVATION & DISPOSAL OF ASBESTOS

COMPUTER EXPERIENCE

MICROSOFT OFFICE, PRIMAVERA SURE TRAK

ACTIVITIES

BOARD MEMBER - BROWARD COUNTY CENTRAL EXAMINING BOARD OF ENGINEERED

CONSTRUCTION TRADES

MEMBER BROTHERHOOD OF ST. ANDREW



Contact this candidate