Post Job Free
Sign in

Electrical Engineer Project

Location:
Grayslake, IL, 60030
Posted:
November 29, 2010

Contact this candidate

Resume:

MARIANO MARINKOVIC P.ENG

*** *** ******** ? Sarnia ON N7S 3G5 ? 519-***-**** ?

*******.**********@*********.**

Electrical Engineer with 10 years of Petro-Chemical Industry experience.

Mr. Marinkovic is a Lean Six Sigma Black Belt and Functional Safety Expert.

Mr. Marinkovic has a proven track record leading on major projects and is

results oriented with comprehensive design and plant support experience.

Mr. Marinkovic is efficient with an exceptional work ethic and has the

ability to work well with others in a team or as a leader.

Core competencies and professional strengths include:

Elect/Inst/Controls Design Personnel Oversight Project

Management

Business Case Development Process Improvements Documentation

Personnel/Role Development Safety/Code Compliance

Report/Proposal Preparation

Cross Functional Collaborations Planning/Scheduling

Scoping/Estimation

Outsourcing/Contracting Services Systems Commissioning

Reliability/Plant Support

SELECT ACCOMPLISMENTS

. Lead project engineer coordinating the electrical, instrumentation and

controls engineering disciplines during a 3 year $115M plant expansion

project. Through proactive steering efforts, the project had tracked and

was completed on budget.

. Developed site guidelines for safety instrumented systems to ensure all

aspects, cradle to grave, are optimally implemented and managed.

Successfully secured guideline buy in and captured improvements from

operations, reliability, management and 2 other plants within NOVA. At

the Moore plant, over 70 safety instrumented functions where successfully

implemented across 6 different projects using these guidelines.

. Design Lead on a $2M dollar project to upgrade 108 obsolete gas detectors

and a shutdown/monitoring system for an entire plant. Devised a plan to

do field work with the plant running, thereby completing all gas

detectors a year ahead of schedule and under budget.

. Key team member developing capital solutions to improve power supply

reliability to 3 plants. Team efforts resulted in a large 230KV

reliability project being implemented in partnership with Hydro One that

greatly improved power reliability to 2 plants.

. Design lead on 3 major PLC upgrade projects ($1.7M) for a LDPE unit. All

3 projects where successfully installed during a shutdown on budget and

under a tight timeline. A major achievement was developing logic

narratives and drawings for an entire LDPE unit. These documentation

practices are being applied to the entire site.

. Won support for an $835K project (completed on budget) to replace high

"arc flash" risk switchgear. Completed short circuit, coordination and

arc flash studies for 3 plants with recommendations for equipment, PPE

and procedural changes to improve safety and reliability. Avoided the

construction of 3 remote switch projects (?$250K) at 3 plants by

promoting a portable switch that allows operators to switch any

switchgear from a safe distance.

. Lead a major troubleshooting effort for a 2500HP VFD. Power savings with

the unit online are ? $329K/year. The drive was idle for 3 years due to

unstable operation.

. Created protection and control operational diagrams to train technical

staff on protection and control systems for a 230KV/15KV substation.

Leveraged this training with a design team to upgrade several protection

relays and to implement a site wide SCADA.

. Avoided ? $550K of electrical upgrades deemed necessary by the ESA by

changing the electrical area classification in a reactor cell from C1D1

to C1D2. It was proved with actuarial fugitive emission data that a C1D2

classification was safe and meets regulatory requirements.

. Managed all electrical capital and plant support design work for a plant

turnaround. Lead a reliability team in developing a procedure and

implementation plan to overhaul a 200 ton 1100HP motor for the

turnaround. All electrical projects completed within time and budget.

. Designed and installed 2 UPS systems with diesel backup to improve site

power reliability and wrote a corporate wide design standard capturing

project insight.

PROFESSIONAL EXPERIENCE

Plant Electrical Engineer

2001 to Present

NOVA Chemicals, Moore Polyethylene Plant, Sarnia, ON

Currently a project lead involved in a plant wide automation upgrade from a

Honeywell TDC3000 to an ABB 800xA system.

. Leads on major projects overseeing junior and intermediate engineers.

. Develops capital project strategies and plans for electrical and

automation infrastructure improvements. Promotes infrastructure needs

across 4 NOVA plants.

. Prepares technical proposals and studies. Defines scope, budget and

schedule and reviews proposals and designs giving feed-forward and

feedback to move ahead. Identifies knowledge and personnel gaps and

devises plans to close them.

. Develops bid quality design and commissioning packages and leads

commissioning teams in the field during startup.

. Ensures corporate policy, regulatory compliance and work flow process

adherence and improves upon existing and creates new processes where

value added.

. Develop corporate engineering standards.

Engineering Assistant Co-op

2000

Langtree Controls LTD, Sarnia, ON

. Assisted with the design of front-end phase of major DCS upgrade for a

polyethylene plant.

Research and Development Co-op

1999

Devries Electronics, London, ON

. Assisted with the development of a wireless modem for an ISP application.

EDUCATION AND TRAINING

Electrical Engineering Degree

Lakehead University, Thunder Bay, ON

Electronics Engineering Technology Diploma

Lambton College, Sarnia, ON

Lean Six Sigma Black Belt

Air Academy Associates, Sarnia, ON

Certified Functional Safety Expert Training

Exida, Sarnia, ON

Professional Engineer - Province of Ontario # 100086845

TECHNICAL SKILLS

Computer Skills: MS Office/Project/Access, SAP, MicroStation, SmartPlant,

AutoCAD, Exida SILver, PHA-Pro, SPC XL, Flowel, SKM Power Tools, Familiar

with ETAP.

Automation: Honeywell TDC3000, Allen Bradley, Modicon, Triconex, Triplex,

RMC Motion Controllers

Electrical:

. NETA, IEEE, ISA, NEC, API, NFPA Standards, Considerable upgrade

experience with 230/27.6KV and 230/13.8KV double ended substations.

. LV and MV motor and VFD implementations. (DC motors and drives up to

1200HP, AC synchronous up to 25000HP, Induction motors up to 3500HP,

VFD's up to 1200HP)

. Plant distribution system design and reliability assessments.

(Distribution system upgrades, motor rewind studies, cable pull studies,

switchgear replacement and protection and control upgrades).

. Numerous designs with controllers, marshalling rack rooms, electric heat

tracing, lighting systems, instrumentation and valves.

COMMITTIEES

. Moore Plant Decision Board

. Regional Power System Analysis Group with NOVA

. NOVA Corporate Engineering Standards



Contact this candidate