Post Job Free
Sign in

Project Quality Control

Location:
Troutdale, OR, 97060
Posted:
August 25, 2011

Contact this candidate

Resume:

RESUME

Cameron Buck

***** *.*. ********** ****

Troutdale, OR

97060

********@*****.***

503-***-****

Objective/Skills: My objective is to use my exemplary self-motivation

and management skills developed in the construction industry to help you

complete projects within desired results. I'm a self- starter that can

accomplish tasks as directed on my own or as an integral part of a

successful team. I've worked my way up through the field to General

Superintendent and then the Director of Land Development for a top 100 in

the nation multi-family contractor. I have 10 years experience using

Microsoft Project to schedule and track all aspects of a successful

project. I have excellent verbal and writing skills. I value my

communication skills and attention to detail as one of my greatest assets.

I am an experienced public speaker and have demonstrated my ability to

communicate well with jurisdictional personnel, project managers,

engineers, subcontractors and suppliers. I am very experienced in RFI

generation and response, Change Order Requests and Change Orders, and

contract administration. I believe honesty and integrity are key elements

of success. I speak both English and Spanish fluently.

WORK HISTORY

Self-employed Consultant October 2008 to present

Duties

Estimate and Project Manage ARRA Public Works Projects in the greater

Portland metro area.

I coordinate and submit all supplier materials submittals, sub-contractor

agreements, and quality control documentation.

I attend weekly project meetings and provide schedule updates to the

baseline schedule using Microsoft Project.

I supervise the daily activity of the construction crews to assure

compliance to contract documents, quality control, and budget coherence.

Develop and enforce job specific safety plans and policies per government

regulations.

I hold current CPR/First Aid, Competent Person, Trench Safety

certifications.

I own my own hydraulic excavator and skid steer loader as well as small

hand operated compactors, cut of saws, generators, pumps, etc. and do all

my own repairs and maintenance.

Polygon Northwest Inc. February 2004 thru October

2008

109 East 13th Street

Vancouver, WA

98660

Contact:

Dave Gutschmidt

President

360-***-****

Title: Director of Land Development

Duties

Establish, maintain, and manage land development budgets from the initial

stages of proforma through completion of land development and issuance of

building permits. My accomplishments included negotiating and contracting

with engineers, consultants, and contractors. I worked closely with the

jurisdictions through the permitting process and provided and managed the

development schedules to assure compliance with the Polygon business model.

I supported vertical construction in all aspects of construction and

contracted with subcontractors for all site concrete flatwork, structural

and non-structural retaining walls, and all site landscaping.

I monitored all site development contractors for adherence to OSHA

standards.

Projects

Teufel Nursery Property (Developed as Willamette Ridge)

50 Acres 1300 Units

This project included public infrastructure improvements to Barnes Road on

the south and Cornell Road to the north. Included also was an extensive

THPRD parks development. I also managed the removal of underground diesel

storage tanks and removal of contaminated soils along with several deep

well abandonments. I worked closely with Craig Ware of GeoDesign to satisfy

all DEQ

remediation requirements. The project bordered sensitive wetlands, which

required substantial wetland mitigation work and governmental

documentation. I worked hand in hand with Mirth Walker from SWCA

Environmental Consultants to complete the mitigation work.

Project Development Budget $29,800,000.00

Progress Quarry (Developed as Progress Ridge)

24 Acres 750 Units

This project required the relocation of a portion of a State Highway. The

new alignment included the crossing of a sensitive creek in two locations

with extensive wetland monitoring and mitigation. Public infrastructure

improvements included over two miles of new public streets, sanitary,

storm, and water improvements, and development of a 12 Acre lake and parks

facilities. The site was built over an abandoned rock quarry site.

Project Development Budget $21,000,000.00

Sexton Crest

14 Acres 40 Single Family Homes & Approx. 175 M/F Units

This site was built over a refuse dump site with DEQ approval. I managed in

conjunction with the geotechnical firm I contracted with, the remediation

plan, which included monitor wells for methane gas and foundation membrane

installations. The site required the building of surcharge fills and

settling plate survey to assure proper building load soil support. Public

improvements included streets, sanitary, storm, water, and water treatment

facilities.

Project Development Budget $11,000,000.00

Bones Construction Inc. March 1997 to February 2004

3508 SW 209th

Aloha, OR

97008

Contact:

Scott Bernhardt (owner)

Office 503-***-****

Title: General Superintendent

Duties

Bones Construction is a site development contractor who during my

employment completed site development work within the 14M to 22M dollar

range annually.

As the General Superintendent my duties included the hiring and scheduling

of all field personnel on a daily basis. I coordinated the mobilization and

use of over 70 field employees and 50 pieces of heavy equipment. I managed

all of the project completion schedules, communications with owners,

engineers, consultants, inspectors, and subcontractors/suppliers.

It was my responsibility to make sure the projects were completed within

the budget and to the satisfaction of the client and owner of the company.

I organized and supervised all mass dirt moving operations on a daily

basis. Excavation and embankment was the bread and butter for Bones

Construction. I scheduled all compaction testing, surveying, settlement

plate monitoring and all subcontractors involved in trucking, rock

crushing, and soil amendments.

I also organized and supervised up to four complete pipe crews and

equipment for the installation of all underground utilities including

Sanitary Sewer, Storm Sewer, Water, PGE, Street Lighting, Signalization,

Verizon, NNG, and Comcast.

I scheduled all the safety courses for Competent Person, Trench Safety, and

First Aid, and managed the compliance of the company safety and drug

policy.

I operated all equipment including graders, dozers, hydraulic excavators,

compactors, loaders, etc.

Miscellaneous

I graduated from Oakmont High School in Roseville, California.

I successfully completed the Erosion Control and BMP class taught by Fred

Wright of USA at Rock Creek Community College in Aloha, Oregon.

I completed a course at Seattle University on teaching the Spanish

language.

I served a two year mission to Mexico when I was 19 years old and speak

fluent Spanish.

I have served as a leader in the Boy Scouts for 10 years.



Contact this candidate