Post Job Free
Sign in

Project Manager Construction

Location:
Stockton, CA, 95219
Posted:
August 21, 2013

Contact this candidate

Resume:

*

Randal Bruno

project manager

Education Years of Experience

BS, Engineering Physics, Colorado School Total – 37 years

of M ines, 1976 With ITSI Gilbane – 4 years

Active Registrations Certifications Clearances

Contractor, Arizona, ROC186838, 07/07; 0062992

Contractor, California, 815620, 10/06

Contractor, Nevada, 05/07

Contractor, U tah, 630****-****, 11/07

Engineer in Training, 7944, Virginia, 12/06

USACE Construction Quality Control for Contractors, 6/25/2010; expires 6/25/2015

Training Expertise

40-Hour HAZWOPER and Emergency Response Refresher Training

8-Hour HAZWOPER and Emergency Response Refresher Training

40-Hour HAZWOPER and Emergency Response Training

Employment History

2009– Present: ITSI Gilbane Company

2008 – 2009: Sierra Mountain Construction, Inc.

2002 – 2008: Shaw Environmental & Infrastructure, Inc.

1999 – 2002: IT Corporation

1990 – 1999: EMCON

1987 – 1990: Oakland Scavenger Co./Waste Management

1987: EMCON Associates

1986 – 1987: Pacific Asphalt Company

1985 – 1986: Kiewit Pacific

1981 – 1985: K iewit Industrial Company

1976 – 1981: U.S. Army Corps of Engineers

E xperience Summary

Mr. Bruno has 37 years of experience directing multimillion-dollar construction projects at

2

R andal Bruno continued

U.S. Air Force, other DoD installations, and other government facilities. His expertise includes

comprehensive experience in project and subcontractor management; H &S; quality control,

cost, and schedule; procurement; and logistics. He is highly skilled in preparing work plans,

safety and quality plans, SOWs, subcontractor quote requests, construction specifications, as-

built drawings, and project reports, and in implementing project plans, assigning and

managing field and supervisory personnel, enforcing safety and quality requirements,

i nterfacing with customers and regulators; ensuring that regulatory requirements are met,

performing technical quality reviews; managing contract modifications, and resolving issues

and non-conformances. Mr. Bruno has experience in all phases of the design-build

construction process, from survey to completion. He has managed multiple design-build

p rojects valued at approximately $50 million and is highly skilled in selecting design-build

teams and coordinating and reviewing the design effort, from award through the 100% design

submittal. Mr. Bruno has a proven record of managing projects to meet safety, quality,

schedule, and cost objectives.

P roject Experience

Project Manager – Building 209 Construct Fire Training, Clear Air Force Station, Alaska,

A FCEE WERC 09, FA8903-09-D-8567, 0019 (07196.0019), September 2011 to July 2013,

$2.3M. P roject Manager for project to demolish an existing two-story Fire Training Structure

(Building 52) and install a new prefabricated /modular, four-story, 1,376-square foot Fire

T raining Structure complete with excavation and fill, concrete slab and foundation, site work

and electrical service at Clear AFS. Construction of the new structure included installation of

a subfloor radon evacuation system. As Project Manager, Mr. Bruno managed subcontractors,

i nterfaced with the client, maintained quality and safety on the jobsite, and ensured all cost

and schedule milestones were achieved.

Project Manager – Design-Build to Convert Launch Pad 1840, Vandenberg AFB, California,

A FCEC SATOC 08, FA3002-08-D-0008, QW04 (07144.6606), August 2012 to April 2013,

$498K. P roject Manager/QC Manager for conversion of the existing Peacekeeper Test Pad-01

(TP-01) to a M inotaur IV Conventional Strike M issile (CSM) Test Launch Pad. The scope

i ncluded patching and smoothing the existing concrete pad and designing, installing, and

testing the foot plates and anchor points to be f lush with the surface of the concrete pad and to

be used for the integration of launch Ground Support Equipment. As Project Manager, Mr.

B runo managed subcontractors, interfaced with the client, maintained quality and safety on

t he jobsite, and ensured all cost and schedule milestones were achieved.

ITSI Gilbane Company

3

R andal Bruno continued

Project Manager – Repair HVAC Building 8250, Vandenberg AFB, California, AFCEC SATOC

08, FA3002-08-D-0008, QW05 (07144.6607), September 2011 to September 2012, $491K. Site

Superintendent/H &S Manager for the design and construction for the HVAC system repair in

B uilding 8250. ITSI Gilbane removed the existing unit and replaced it with a new 55-ton unit.

We installed an 11,500-CFM indoor AHU to include a new chilled water cooling coil, heating

coil, air side economizer and 95% efficiency fil ters. We also installed new VAV boxes (with

i ndividual electronic thermostats), supply and return registers in each room, CO2 sensors for

Demand-Controlled Ventilation in each classroom, and new Direct Digital Control standards

(BACnet or LanWorks). As Project Manager, Mr. Bruno managed subcontractors, interfaced

w ith the client, maintained quality and safety on the jobsite, and ensured all cost and schedule

m ilestones were achieved.

Project Manager and QC Manager – Marine Corps Reserve Training Center Facility Repair

and Modernization, US Marine Corps, USACE FRR; W912DY-08-D-0032, 0009 (07166.0008),

E lmendorf AFB, Alaska, December 2009 to September 2011, $5.4M. M anaged work on this

repair and renewal of the interior and exterior components, systems, and site under the

USACE Huntsville District Facility Repair and Renewal (FRR) ID IQ contract. Oversaw the

renovation work done to improve the working environment, provide energy savings, and

p rovide ADA compliance to meet life/safety requirements. In addition to the responsibilities as

p roject manager, provided QC management during the project.

P roject Manager – Repair U tilit ies in Permanent Party Dorms, Buildings 2202 and 2204, US

A ir Force, AFCEC SATOC; FA3002-08-D-0008, 0043 (07144.4504), Eielson AFB, Alaska, June

2010 to August 2012, $11.4M. M anaged work on this design-build renovation and repair of

u tili ties and infrastructure in two permanent party dorm buildings under the AFCESA

Sustainment/Restoration and Modernization Acquisition Task Order Contract (SATOC).

D irected subcontractors in replacing HVAC, electrical, fire and life safety, and communications

systems and repairing architectural features, such as walls and ceilings. Wrote SOWs for

subcontractors, conducted weekly meetings with client, managed the on-site superintendent,

and prepared submittals, including the Work Plan and material and equipment specifications.

Project Manager – Repair U tilit ies in Permanent Party Dorms, Buildings 2260 and 2266, US

A ir Force, AFCEC SATOC; FA3002-08-D-0008, 0026 (07144.4502), Eielson AFB, Alaska,

December 2009 to June 2011, $7.6M. M anaged work on this design-build renovation and repair

of utili ties and infrastructure in two permanent party dorm buildings under the AFCESA

Sustainment/Restoration and Modernization Acquisition Task Order Contract (SATOC).

I TSI Gilbane Company

4

R andal Bruno continued

Directed nine subcontractors in replacing HVAC, electrical, fi re and life safety, and

communications systems and repairing architectural features, such as walls and ceilings.

Oversaw the renovation of each building separately to allow residents to occupy at least one

building during renovation, and allocated 30 days in the schedule to t ransfer residents

between the two dorms. Wrote SOWs for subcontractors, conducted weekly meetings with

client, managed the on-site superintendent, and prepared submittals, including the Work Plan

and material and equipment specifications. This project was completed on schedule and within

budget.

P roject Manager – Repair Nosedock 2 Mechanical/Hangar Door Systems, US Air Force,

A FCEC SATOC; FA3002-08-D-0008, 0031 (07144.4503), Eielson AFB, Alaska, December 2009

to September 2010, $3.4M. D irected this project to design, reconfigure, and repair the HVAC

and hangar door system in Building 1121 under the AFCESA SATOC. The scope included

p roviding a new HVAC system, hangar door operating system, and hangar door t racks, and

reinstalling the repaired hangar doors and associated equipment. Work also covered

i nstallation of the hangar door t rack/apron ice melt system, electrical work, and seismic

supports, as well as hazardous material abatement. In addition, ITSI Gilbane repaired the

exterior hangar door skin, fur r ing, and fasteners. Wrote SOWs for three subcontractors,

conducted weekly meetings with client, managed the on-site superintendent, and prepared

submittals, including the Work Plan and material and equipment specifications. This project

was completed on schedule and within budget.

P roject Manager, Tuolumne City Sanitary District, Wastewater Treatment Plant

I mprovements, Tuolumne, California, July 2008 to December 2009, $5.7M. D irected

wastewater t reatment plant improvement project, which required construction of a concrete

headworks structure with a mechanical screen and screening washer, an aeration basin with

an integral clarifier, a masonry block blower building, and six manholes. Managed three

subcontractors in completing modifications to the existing aerated lagoons; installation of

u nderground piping and valves, a sewer lift station, and aeration equipment, including

b lowers and all electrical and controls; site grading and paving; and integration of the new

facilities with the existing operations. Prepared the project’s cost estimate, and oversaw the

completion of this project on schedule and approximately $250,000 under budget.

P roject Manager – Oakdale I r r igation District, South Main Canal Rehabili tation, Oakdale,

California, October 2008 to February 2009, $890K. M anaged removal and replacement of two

concrete control structures and appurtenances and the shotcrete lining of a portion of the

I TSI Gilbane Company

5

R andal Bruno continued

South Main Canal. Directed the team in self-performing 95% of the work, and managed one

subcontractor. Work included demolishing the two existing concrete control structures,

removing the existing shotcrete lining, reshaping 1,760 feet of the existing canal, exporting

over 8,000 cubic yards of unsuitable soil, placing 88,000 square feet of shotcrete, replacing five

l andowner tu rnouts, and installing 20 tons of r ip rap, 1,630 lineal feet of barbed wire fence

and entrance gates, 38 feet of 84-inch-diameter reinforced concrete pipe, and two control

structures complete with slide gates, catwalks, and concrete headwall. Prepared the project’s

cost estimate, and directed the completion of this project on schedule and within budget.

P roject Manager – Jamestown Mine Closure, Shaw Environmental L iability Solutions, L LC,

Jamestown, California, July 2006 to July 2008, $6.3M. Oversaw design-build project, which

required closure of the mine’s tailings management facility (TMF). Work included dewatering

approximately 200 acre feet of existing surface water pond on the TMF; excavating and placing

180,000 cubic yards of soil; fine grading the TMF to a minimum of 1% slope; screening,

s tockpiling, and placing 250,000 low-permeability cubic yards of protective layer soils;

i nstalling drainage structures; and hydroseeding disturbed areas. Led the project team in

completing work on schedule and $1 million under budget.

CQA Manager – San Joaquin County, North County Landfill Expansion, Lodi, California,

J une 2006 to October 2006. Provided CQA services for the installation of a geosynthetic liner

system for the landfill expansion. Managed the field staff and had overall responsibility for

construction testing and observation. Reviewed the staff’s daily activity reports, and prepared

weekly summaries to document site activities for the client. Established an excellent working

relationship with the California Regional Water Quality Control Board (RWQCB), the lead

regulatory agency on the project. Prepared the construction quality control report, which was

accepted by the RWQCB.

P roject Manager – Trust for Public Land Tank Removal, San Diego County, California,

September 2005 to February 2006, $100K. D irected improvements to the access road and

removal of an existing 10,000-gallon fuel tank. Prepared the Closure Report and received

acceptance for clean closure of the site from San Diego County.

P roject Manager – City of Fresno, 14-Month Landscape Establishment Program, Landfill

C losure, Fresno, California, March 2004 to May 2005, $119K. Established and maintained a

135-acre grass ecosystem on the closed City of Fresno Sanitary Landfill.

P roject Manager – City of Fresno, Fresno Landfill Closure and Construction of Regional

I TSI Gilbane Company

6

R andal Bruno continued

Park/Sports Complex, Fresno, California, July 2000 to June 2003, $24M. M anaged

construction of a 135-acre landfill cap, subdrain system, landfill gas f lare complex, and

g roundwater t reatment facility and control building, and installation of 105 landfill gas wells

and over 6 miles of landfill gas, condensate, and air pipes. Also oversaw construction of six

softball fields (four lighted); nine soccer fields; two concession/restroom buildings; 1-1/2 miles

of paved road; nine parking lots; underground electric, domestic water, sewer, and storm drain

p iping; and a sewer lift station, 3-acre lined lake, i r r igation pump station, i r r igation system for

t he landfill and park, and 35 acres of tu rf. Directed creation of a California native grass

environment on top of the landfill. Directed nine subcontractors, and coordinated the work of

t he City’s three engineering companies to construct a completely integrated and working

facility.

CQA – Western Regional Landfill Module X, Lincoln, California, March 2000 to May 2000,

$100K. P rovided CQA services for the $100,000 construction of a new 10-acre landfill module,

i ncluding excavation and installation of a geosynthetic clay liner (GCL) and a high-density

polyethylene (HDPE) liner. Provided construction observation and inspection services and

p repared daily and weekly summary reports to document site activities for the client.

Project Manager – Placer County, Western Regional Sanitary Landfill Closure, California,

J une 1998 to October 1998, $45K. D irected construction and CQA services for the closure of a

10-acre portion of a landfill. Oversaw construction testing and observation. Reviewed the

staff’s daily activity reports and prepared weekly project summaries for the client. Prepared

t he project’s construction quality control report. Site closure was accepted by the RWQCB.

Project Manager – Placer County, Eastern Regional Landfill Closure, Truckee, California,

M arch 1996 to December 1998, $250K. M anaged the design and acted as the owner's

representative for the construction of a 40-acre landfill closure. The scope included placement

of the soil cover and landfill gas collection pipes and f lare. Managed the field staff and

construction testing and observation. Reviewed the staff’s daily activity reports and prepared

weekly project summaries for the client. Prepared the project’s construction quality control

report. Site closure was accepted by the RWQCB.

CQA Manager/Resident Engineer – Tulare County, Woodville Landfill Expansion, Woodville,

California, June 1996 to November 1996, $100K. Oversaw construction management and

i nspection services for construction of a new landfill cell. Managed the field staff and

construction testing and observation. Reviewed the staff’s daily activity reports and prepared

I TSI Gilbane Company

7

R andal Bruno continued

weekly project summaries for the client. Prepared the project’s construction quality control

report. The liner was accepted by the RWQCB.

P roject Manager – Placer County, Loomis Landfill Closure, Loomis, California, March 1995 to

September 1996, $100K. D irected CQQ and resident engineer services for closure of the 30-

acre Loomis Landfill. The closure included importing and placing low-permeability and

vegetative soils and installing 16 landfill gas wells, a condensate collection and pumping

system, and a landfill gas f lare. Managed the field inspection staff, and reviewed daily project

reports and field and laboratory test data. Performed the constructability review.

CQA Manager – BFI Waste Systems, Ox Mountain Project, Half Moon Bay, California, August

1992 to November 1994. P rovided CQA services for the construction of a new landfill,

i ncluding a 1-million-cubic-yard toe berm, roads, drainage, ditches, a groundwater collection

system, and a 4-acre detention basin. Work also included screening and placement of 35 acres

of clay liner and geosynthetic liner. Managed the field staff and construction testing and

observation. Reviewed the staff’s daily activity reports, and prepared weekly summaries for

t he client. Prepared the project’s construction quality control report. This project was

completed on schedule and within budget and was accepted by the RWQCB.

Project Manager – Landfill Construction, EMCON, Sacramento, California, 1990 to 1992.

Responsible for providing project/construction management services to clients for the

construction of landfills, landfill closures, landfill gas collection and f lare systems, recycling

centers, t ransfer stations, maintenance facilities, and entrance facilities. Also provided

resident engineer and inspection services for clients.

Capital Projects Manager – Oakland Scavenger Company/Waste Management, Northern

California, Oakland, California, 1987 to 1989. M anaged design and construction and

modifications of landfills and t ransfer stations in Northern California. Also responsible for

p reparing design and construction budgets for projects and selecting and managing engineers

and architectural fi rms.

Project Manager – Pacific Asphalt Company, Stockton, California, 1986 to 1987.

Responsibilities included preparing cost estimates and managing the construction of grading,

paving and underground utility construction projects.

Superintendent – Kiewit Pacific, Northern California, Concord, California, 1985 to 1986.

P repared cost estimates for grading and underground utility construction. Supervised and

I TSI Gilbane Company

8

R andal Bruno continued

managed the construction of civil engineering projects.

Field Engineer – K iewit Industrial Company, Process Division, Alameda, California, 1981 to

1985. Responsibili ties included assisting in preparation of bids for the construction of oil

t reatment facilities for the Prudhoe Bay, Alaska, oil fields. Assisted the superintendents in the

construction of modules for Alaska and the installation of oil modules in Alaska.

Assistant Operations Officer (Captain) – United States Army, U. S. Army Corps of Engineers

( USACE), Fort Lewis, Washington, 1976 to 1981. Responsibili ties included managing and

leading a 30-man combat engineer platoon in Germany, and design and construction of roads,

a irfields, and bridges.

Publications Technical Presentations

Awards Commendations

Commendation for outstanding work on the Loomis Landfill and Eastern Regional Landfill

closure projects for Placer County, California, 1996 – “I have found your work to be

p rofessional, timely, and thorough. In addition, your outlook and perspective are assets that

have helped me greatly in the administration of these projects.” – Will Zimmerman, Civil

E ngineer, Placer County

ITSI Gilbane Company



Contact this candidate