K RAMESH
Mobile: 91-944**-*****
Email: ***************@*****.**.**
Job Objective:
Seeking senior level assignments in project Execution & Coordination,
Estimation & Costing, Billing Quantity Surveying, Erection and
Commissioning, Resource management, operation and maintenance with a high
growth oriented organization of repute.
Professional Synopsis:
> Over 23 yrs of Cross cultural Experience in the areas of Planning and
Execution of Projects, QA/QC and Formwork Co-ordination, Quantity
surveying and billing, Resource Management and System implementation.
> A Strategic Planner with multi-discipline expatriation in execution of
high raised, heavy and critical concrete structures for Paper Mill,
Steel & Power Plant, Housing Apartments, Irrigation and Water supply
projects,canal projects, and various industrial projects.
> Experience of 23 Yrs with clients like DuPont, ITC, TATA, Sterilities,
M.N.Dastur & Co., Sri Sathya Sai Central Trust in India, Coromandel
International,NTPL & TOYO Engineering..
> Expertise in fulfilling client's requirement and working on their
suggestion and feedback with proven track records in Safety and
Quality.
> A keen planner and strategist with skills in troubleshooting, Team
building capability, excellent interpersonal relationship, proven
abilities in planning & managing resources and Public Relations.
Educational Qualification:
> D C E State Board of Technical Education -
Tamil Nadu. 1988
> D C Tech Annamalai University, Chidambaram
1989
> B.E., Civil ANNA UNIVERSITY, Guindy, Chennai.
2004
> Primavera P6 CADD Centre, Chennai
2011
Organization Experience:
> Tecton Engg. & Constn. (I) Pvt. Ltd., Sr.Manager
Sep'10 to Oct'11
> Hindustan Dorr-Oliver Ltd., Sr.Manager
Apr'09 to Jul'10
> Zuari Cement Limited, Italcementi Group Sr.Manager
Aug.08 to Mar' 09
> Larsen & Toubro Ltd. ECC Division Asst.Const.Manager
Sep' 95 to Aug' 08
> UNITECH Limited Jr. Constn.
Engineer May' 94 to Aug' 95
> Overseas Water Proofing Corporation. Site Engineer.
Apr' 93 to May' 94.
> Private Concerns & Building Work Site Engineer.
Aug'88 to Apr' 93.
PROFESSIONAL EXPERIENCE: 23 years in the field of Civil Engineering
> Presently working with M/s. Doshion Veolia Water Solutions Pvt.Ltd.,
Ahmadabad, as a AGM - Projects for Construction of RWTP, UF, RO Plant
at OMPL, Mangalore.
Tecton Engg & Constn. (I) Pvt. Ltd., - Chennai.
Designation: Senior Manager- Project Coordination Period: September,
2010 - October, 2011
Job Responsibilities:
> Planning and Monitoring of Monthly, Weekly and Daily Program in line
with Master Schedule to complete the task in time.
> Finalization of Required Resources for the project, Optimum
utilization of assigned Resources and demobilizing the same at right
time.
> Allocation of Sub - ordinates, Frontline supervisor and skilled
workmen in Right location according to their experience and caliber to
achieve maximum productivity.
> Overall Planning, Scheduling and management of civil projects,
ensuring completion of assignments within time.
> Monitoring project with respect to cost, resource deployment, time
overruns, Quality compliance and manpower planning to ensure timely
execution of projects.
> Expertise in Detailed Estimation and finalizing of quantities for EPC
projects with relevant to available drawings, specifications and
contract.
> Experienced in working-out quantities, measurement certification for
billing from clients Rate analysis, certification of sub contractor
measurements etc according to Project.
Hindustan Dorr-Oliver Limited - Vizag
Project: Construction of Horizontal Belt Filter Building for Coromandel
International Ltd., Vizag.
Designation: Senior Manager- Projects Period:
April, 2009 - June, 2010
Job Responsibilities:
Project Execution & Coordination for over all civil activities with Electro-
mechanical & Instrumentation works, Scope of works Planning & Monitoring
the daily activity and complete the project.
. Approval & Finalization of Vendor & Specialized agencies.
. Preparation of Detailed Estimation and finalizing the BOQ. Estimating
and Costing, Rate analysis for each Item of works to finalization of
contracts and payment.
. Coordination with Internal departments and given civil front to
electromechanical work. Technical Assistance/guidance to contractor to
complete the work in scheduled time.
. Good rapport with Client's and completes the work & Payment in time.
. Re-bar & Structural detailing, Checking and Estimating the
quantity, Reconciliation of steel.
Zuari Cement Limited, Italcementi Group - Bangalore.
Project: Construction of New Burning Line II (5500 MTPA), Yerraguntala.
Designation: Senior Manager Period: Aug,
2008 - March, 2009
Job Responsibilities:
Project Execution & Coordination for over all civil activities with
Electro-mechanical & Instrumentation works, Scope of works Planning &
Monitoring daily activity.
. Planning and Monitoring of Monthly, Weekly and Daily Program in line
with Master Schedule to complete the task in time & Inspection of
Civil Structures as per approved drawing.
. Preparation of Detailed Estimation and finalizing the BOQ. Estimating
and Costing, Rate analysis for each Item of works to finalization of
contracts and payment.
. Continuous follow-up with vendor and Technical Assistance/guidance to
complete the work in scheduled time. Vendor bill checking and
reconciliation of materials structure wise.
. Re-bar & Structural detailing, Checking and Estimating the
quantity, Reconciliation of steel.
A LARSEN & TOUBRO LTD., ECC DIVISION - 13 YEARS EXPERIENCE
1. Project: L&T ECCD., - NSRDWS, Anantapur.
Designation: Asst. Construction Manager Period Aug
2007 - Aug 2008
Job Responsibilities:
. Site In charge for the Construction of Heavy duty pump house,
OHWST, UG Sump & OHSR over hill in various interior village
locations as per Client' requirement.
. Preparation of BOQ, Schedule of Quantities and Rate analysis
for finalization of Scope of work. Planning, Execution &
Monitoring of OHSR in Various Capacity of Tanks & Sumps, Heavy
Duty Pump House building work.
. Preparation of client bill & certification, according to that
Contractor bill payment
2. Project: L&T ECCD., - Alisagar Lift Irrigation
Project, Nizamabad.
Designation: Asst. Construction Manager Period:
May 2006 - July 2007
Job Responsibilities:
. Site In charge for Construction of Alisagar Lift Irrigation
Scheme - Stage III.
. Planning, Estimating, Procurement, Monitoring & Execution Heavy
Duty Pump House, Road Bridge & Railway Bridge, Canal excavation
& Lining, Pipe line Thrust Block, Air Valve Chamber construction
work.
. Railway Bridge (Pre-cast) was constructed by Box pushing method
without disturbing of the existing railway line & traffic.
. Preparation of client bill, certification & Technical Assistance
to contractor.
Preparation of BOQ, Schedule of Quantities and Rate
analysis
3. Project: L&T ECCD., - Construction of 22.5ML
Capacity MB Reservoir for HMWSSB.
Designation: Senior Engineer Period Jan 2005
- May 2006
Job Responsibilities:
. Preparation of scope of work & Schedule of quantity for Master
Balancing Reservoir for HMWSSB at Gungal, Hyderabad.
. Planning, Estimating, Procurement, Monitoring & Execution of
Reservoir.
. Reservoir Cover Slab 70 mtr. Dia & 6mtr High was casted with
Structural Steel Bracket system without vertical support &
staging.
. Preparation of client bill, certification & Technical
Assistance to contractor for the above shuttering system to
complete the work ahead the schedule.
. Preparation BBS of steel quantity and estimation.
4. Project: L&T ECCD., - Cogent. Power Plant for EID Parry
(I) Ltd, Pudukkottai.
Designation: Senior Engineer Period: May
2005 - Jan 2006 .
Job Responsibilities:
. Preparation of scope of work and construction of LT Panel, MCC
Room, and Raw water Tank cum Pump House & TG Building
construction work.
. Planning, Estimating, Execution & monitoring of all civil &
Structural work and preparation of bar bending schedule for the
above structure.
. Preparation of Clients & Subcontractor billings, Certification.
. Technical Assistance to contractor and complete the work in
time.
5. Project: L&T ECCD., - TATA Steel Project, Jamshedpur
Designation: Senior Engineer Period: March 2004 -
April 2005
Job Responsibilities:
. Construction of ECR Building 100m x 30m for New Rebar mill.
Planning, Estimating, Monitoring & Execution of ECR Building.
. Each Floor Slab was casted in a month by providing Structural
Steel Shuttering method without vertical support, Staging and
save the Cost & Time.
. Finalization of specialized agencies for various finishing item
of work, execution & supervision in time to and complete the
work in time.
. Construction of 33 KV Transformers - 2 Nos in the ECR Building.
. Preparation of structural steel & Rebar detailing, estimation
for the work
. Preparation of sub contractor & Client Billing and follow up the
payment.
6. Project: L&T ECCD., - CMWSSB Water Treatment Plant, Chennai
Designation: Senior Engineer Period: Jan
2003 to Feb 2004
Job Responsibilities:
. Preparation of scope of work for Kilpauk Water Treatment Plant,
Detailed Estimation for each building, clarifier, Chemical
House, Gravity sand filter building, Pump house. Preparation of
Bill of qualities, Finalization of Contract value.
. Preparation of cost estimation & client's bill certification.
Rebar detailing, Checking & bar bending schedule, Reconciliation
of Cement & Steel.
. Specialized agency finalization for chemical treatment and
waterproofing work.
7. Project: L&T ECCD., - Testing & commissioning of pipe line for
Chennai Metro Water.
Designation: Senior Engineer Period: June 1999 to
Dec 2002
Job Responsibilities:
. Doing Main condition survey for existing pipe line in area wise
and preparation of Estimate & finalization of Scope of work.
. Laying of New CI Pipe and replacing of old pipe.
Testing & commissioning
pipe line without any leakage.
. Client's bill certification and follow-up & Consumer
satisfaction.
. Good rapport with publics and complete the job successfully.
8. Project: L&T ECCD., - Construction of surge pond for Sterlite
project, Tutucorin.
Designation: Assistant Engineer Period: Dec1998 to May 1999
Job Responsibilities:
. Planning, Estimating, Surveying, Monitoring and Execution of
Surge Pond work.
. Preparation of subcontractors billing and reconciliation of
Cement & Steel.
. Preparation of Rebar detailing and bar bending schedule.
9. Project: L&T ECCD., - Bellary Steel & Alloys Ltd., Bellary
Designation: Assistant Engineer Period: August 1997
to Nov 1998
Job Responsibilities:
. Planning and Execution of Blast Furnace Foundation HRC
(2500 cum) concrete work done by manually.
. Preparing and Monitoring of Monthly, Weekly and Daily Program in
line with Master Schedule to complete the task in time.
. Finalization of Required Resources for the project, Optimum
utilization of assigned Resources and demobilizing the same at
right time.
. As a Planning/ Billing Engineer Preparation of Client's bill
for each building/Structure wise & getting certification from
consultant /Client. Sub-contractor bill preparation &
reconciliation of materials.
. Preparation of cost estimate and rate analysis, reconciliation
of Cement & Steel.
. Preparation of bar bending schedule, Structural steel detailing
and estimation for Steel Plant.
10. Project: L&T ECCD., - ITC Bhadrachalam Paper Ltd. Bhadrachalam
Designation: Jr. Engineer Period: Oct 1996 to
August 1997
Job Responsibilities:
. Surveying & Marking of Foundation Layout and
Construction of Bulk Tower,
Broke Tower, Final tower & Dump Tower of 20mt.dia &
30mtr Height.
. Construction of Tower by conventional doka method shuttering and
Mixing, placing of concrete by manually.
. Preparation of sub-contractor billing and reconciliation of
materials.
. Preparation of bar bending schedule and estimation.
11. Project: L&T ECCD., - Tapar DuPont Ltd. Gummudipoondi
Designation: Jr. Engineer Period: Sept 1995 to Oct 1996
Job Responsibilities:
. Re bar & structural Steel detailing, checking & preparation of
bar bending schedules as per drawing to entire project work and
reconciliation of Steel.
. Planning Execution & Monitoring of factory buildings, Cable
Trenches, Specialized Flooring work. Allocation of Excavators,
Roller, Trucks for site requirement.
. Supervision of Compound wall construction and grading of area
for sand Blast area.
B UNITECH LTD, Chennai.
Project: NOVA Projects & Indoor Stadium, Chennai
Designation: Jr. Construction Engineer Period: May
1994 to August 1995
Job responsibilities:
. As Planning Engineer preparation of detail Estimate, cost
estimation and finalize the BOQ. Preparation of client bill and
certification of payments.
. Preparing and Monitoring of Monthly, Weekly and Daily Program in
line with Master Schedule to complete the task in time.
. Rebar detailing, Estimation of steel & reconciliation of the
materials.
C OVERSEAS WATER PROOFING CORPORATION, New Delhi.
Project: Jindal corporate office, Delhi ITO Sub way, underground
car parking
Designation: Engineer Period:
April 1993 to May 1994
Job Responsibilities:
. Preparation of schedule and bill of quantities, updating of daily
progress report.
. Planning, Supervision, Monitoring & Execution of Water proofing
work like Terrace water proofing (BrickCoba) method, Box type
method for wall and Flooring .
. Preparation vendor & Client's Billing and certification.
D Private Builders & Building Works, Chennai.
I have worked as a Site Engineer for the Construction of Residential,
Commercial & Apartments Buildings including Surveying, Marking,
Supervising, & monitoring the daily activities.
Period : June 1988 to Nov 1989
& Feb 1990 to March 1993
Key Result Areas:
Project Execution:
> Finalization of construction Methodology with respect to contracts,
specifications, environment, within accepted cost limits and Ultimate
safety conscious to complete in time.
> Preparing and Monitoring of Monthly, Weekly and Daily Program in line
with Master Schedule to complete the task in time.
> Finalization of Required Resources for the project, Optimum
utilization of assigned Resources and demobilizing the same at right
time.
> Allocation of Sub - ordinates, Frontline supervisor and skilled
workmen in Right location according to their experience and caliber to
achieve maximum productivity.
Project Co-ordination:
> Overall Planning, Scheduling and management of civil projects,
ensuring completion of assignments within time.
> Monitoring project with respect to cost, resource deployment, time
overruns, Quality compliance and manpower planning to ensure timely
execution of projects.
Formwork Competency:
> Expertised in different type of formwork and shuttering system like
Doka, Acrow units and convention methods including mockups and
training to workman.
> Handled in finalizing methods of shuttering materials and manpower
required for the projects within the cost and approval from client.
Construction Equipment:
> Coordinated with Plant and Machinery Department for finalizing
required Man and Machineries for the project, Plant cost and
Maintenance Schedule to run the Plant within the Accepted cost.
> Worked with different types of Contract like Item Rate, EPC, Lumpsum
Package and Cost Plus with different clients.
> Spearheaded in finalizing Sub Contractor and vendors, Rate Analysis,
Negotiation and Placing of work order to the agencies.
Safety
> Co-Ordination with Safety Engineering Department in Implementing HSE
Policies at site level
> Maintaining a high level of safety and safe working plan and ensuring
all workmen are familiar with the employer safety guide confirm to
safe working practice at all time.
Quality
> Worked as Management Representative for implementing ISO- 9001 quality
Management system at site level.
> Implementing and finalizing PQP for the project, approving the client
and implementing the same at site.
Training Program Attended:
> Construction Management
> Supervisory Development Program
> User Awareness on construction equipment
Personal Details:
Father's Name : R. Krishnaiyan
Date of Birth : 15.04.1967
Sex : Male
Marital Status : Married
Nationality : Indian
Languages known : English, Hindi, Tamil, Telugu, Sourastra.
Communication Address : Plot No.2, Flat No.7 VARUN
TERRACE,
Venkateswara Cross Street,
Radha
Nagar,
Chrompet,
Chennai -
600 044.
Remuneration Package:
Present Salary : Rs.15.11 Lakh PA
Expected Salary: Negotiable
K. RAMESH