ROMARICO B. PEÑAFLOR
Takrrer Ruwais Refinery Expansion #3, Samsung Camp, Jabel dhana, Al Ruwais, Abu Dhabi, UAE
Mobile # in UAE. +971********* Email: r8anki@r.postjobfree.com
EMPLOYMENT OBJECTIVE:
To obtain a position as a Design Engineer
SUMMARY OF ACHIEVEMENTS AND QUALIFICATIONS:
Holds a degree in Bachelor of Science in Mechanical Engineering
Piping Engineer at Samsung Engineering Company Limited.
Has experience in Piping Design and Construction
Piping Inspector /Pre Commissioning Supervisor RGX 6/7 LNG PROJECT QATAR
Piping Engineer at QGX 4/5 LNG PROJECT QATAR
Designer at TNH and HSF PROJECT
Area Leader at QCS PROJECT
Piping Design Engineer at CHIYODA PHILIPPINES
Has two (2) years experience in maintenance of Robotics and Mold & Die.
Has thorough knowledge in 3d/2d Micro Station and Auto CAD; Pelican forge for 3D support modeling; and Smart plant Review and PDS 3D Modeling
Can communicate in English fluently and can speak & understand Nihongo.
RELEVANT EMPLOYMENT HISTORY:
July 04, 2011 up to present - PIPING ENGINEER
SAMSUNG ENGINEERING COMPANY LIMITED.
Takrrer Ruwais Refinery Expansion #3 Jabel dhana
Ruwais, United Arab of Emirates
• Responsible for Review and checking of Isometric and P&ID’s.
• Checking of RFI submitted by sub Contractor.
• Coordinating with subcontractor and other disciplines as regards executions and engineering problems.
• Checking of test package requirements and test limit.
• Responsible in drawing modification using AutoCAD and Micro station.
• Verify isometric as per standard.
June 04, 2006 to March 14, 2011 - PIPING DESIGN ENGINEER
Chiyoda Philippines Co.
17th floor Sun plaza Building
1507 Shaw Boulevard cor. Princeton St., Brgy. Wac-wac, Mandaluyong City, Philippines
• Preparation and Checking of Piping layout / Routing, Isometric and General Arrangement drawing.
• Reviewing of P&ID’s / UHD’S & consistency checks between IFC Iso and Flex Iso drawings.
• Execution of clash check, review of piping models for accessibility, opera ability, using SPR (Smart Plant Review)
• Update piping activities’ weekly production and schedules, & control isometric issuance for IFC
• Review the Detail Equipment Vendor drawing,
• Preparation and checking of Orientation, Rating, Size and Operability of Equipment Nozzle.
• Preparation and checking of Loading Data.
• Area lead on QCS project (Process Area)
• 2D Modeling using Micro Station and Auto CAD.
UNDER CHIYODA OVERSEAS ASSIGNMENT
March 09, 2009 – December 2, 2009 -
PIPING INSPECTOR/ PRE-COMMISSIONING SUPERVISOR
Chiyoda Technip Joint Venture (CTJV) (PROCESS AREA)
Ras Gas Exxon (RGX 6/7) LNG Project
Ras Laffan Industrial City, State of Qatar
• Responsible for Piping Quality, physical check of flange surface, alignment, parallelism.
• Inspection of welding.
• Line checking/ Inspection of Piping component, alignment; plumb ness and Valve handle orientation as per Iso drawing.
• Revise Isometric Drawing as per Field Design Change Condition.
• Responsible for Punch clearing before final acceptance.
• Responsible for System checking as per P and ID and its general notes if applied.
• Coordinate and supervise the sub - contractor for the modification of line as per Project specification and Standard.
• Line checking as per standard and Iso drawing.
January 23, 2008 –September 19, 2008 -
PIPING ENGINEER
Chiyoda Technip Joint Venture (CTJV) (PROCESS AREA)
Ras Gas Exxon (QGX) LNG Project
Ras Laffan Industrial City, State of Qatar.
• Checking of the actual status of design change, clashing and other obstruction on site and preparation of Field Design Change (FDC) Drawing.
• Preparation of Site Instruction (SI) for the additional Design Change.
• Monitoring and Updating of Control list for FDC and Technical Query.
• Assisting Line Checker and Testing Group Regarding Design and Engineering matters.
• Line checking as per Isometric Drawing and Standard Specification of Piping line.
• Responsible for Checking and monitoring of test limit on line.
August 10, 2007 – December 15, 2007 –
FELICAN FORGE TRAINEE
Chiyoda Yokohama Japan
Tsurumi, Yokohama, Japan.
• Felican Forge System Operation and Modeling of 3d support.
• Drafting of User Manual for modeling of 3D modeling as per Chiyoda Support Standard & Specification.
• Checking the applicable application of Felican Forge against the Chiyoda standard.
OTHER RELAVANT EMPLOYMENT HISTORY
January 08, 2003- January 07, 2006 - FABRICATION ENGINEER
HYODOU FABRICATION CO.
Ichinomiya, Nagoya, Japan
• Preparation of materials and Equipment needed in fabrication
• Checking of drawing and modification using Auto Cad.
• Responsible with material take-off.
• Supervising fabrication assembly.
• Does welding using semi- automatic welding and Arc Welding.
December 8, 2000 to October 15, 2002 - JR. TECHNICAL ASSISTANT under Parts Manufacturing
MITSUMI PHILIPPINES
BEZ, Mariveles, Bataan, Philippines
• Maintenance, Troubleshooting and Repair of Robotics
• Checking of data input on Robotics panel board to ensure that the sequence is correct.
• Perform Preventive Maintenance.
• Responsible on Machine shop Operation and Repair of Mold and Die.
IN HOUSE TRAINING SEMINAR @ Chiyoda Philippines
June 3-11, 2010 Pipe Welding and Inspection Control
April 2010 – June 2010 Flex Calculation, Equipment Nozzle Orientation, Pipe Routing & Support
May 4-27, 2010 QC Isometric Preparation
February 18, 2010 ISO 27001:2005 ISMS AWARENES
July 11, 2006 ISO 9001:2000 QMS AWARENESS
EDUCATIONAL DEGREE OBTAINED: Bachelor of Science in Mechanical Engineering (Graduate: 2000)
Bataan Memorial College
Balanga City, Bataan Philippines.
REFERENCES: (To be submitted upon request)
_______________
(Romarico Penaflor)