CURRICULUM VITAE

WORK EXPERIENCE: ** + years

NAME : SRINIVAS. MANGALAGIRI

DATE OF BIRTH : 04-08-1974

PRESENT POSITION : Coordinator QA/QC

BHEL-Hyderabad.

EDUCATIONAL QUALIFICATION : KUVEMPU UNIVERSITY

B.E, Mech. MBA, HR

PROFESSIONAL QUALIFICATION

Core areas of exposure: : ASNT Level II in RT, UT, PT & MPI

Inspection of equipments, Inspection of Piping & Pipelines, QA/QC & Project monitoring for EPC Projects, Weld Inspection, NDT, Shop floor Inspections.

WORK EXPERIENCE:

• Familiar with ASME, IS, API, B31.3, D1.1 codes.

• Familiar in inspection of Pressure vessels, Boilers, Reactors, Colums & Heat Exchangers.

• Approval of WPS &PQR, ITP,

• Witnessing Welder Qualification,

• Witnessing Hydro Test.

• Witnessing of Mechanical tests like UTS, Vickers, Rockwell hardness tests, Micro and Macro examinations.

• Witnessing all NDT activities like RT, UT, DTP, and MPI.

• Final Dimensional Inspection of all machined items

• Review of Radiography-testing Interpretation of welded joints.

• Review for Quality Documents & Manuals.

• Inspections for Anode manufacturing for RIL project KG-D6 at Kandla.

• Receipt of raw material Inspection, such as plates, pipes, and forgings &weld consumables.

• Inspection of structural components in various stages like marking fit up; weld visual and final dimensional checks etc. as per drawing.

• Witnessing CTE Coating and CWC.

• Witnessing of hydraulic pressure test for pipe spools, oil tanks and pressure vessels.

• Surface inspection after shot/sand blasting and DFT checking conducting spark test.

• Preparation of inspection reports & review of final test pack.

• Review of heat treatment charts.

• Inspection of rock wool thermal insulation material.

• Inspection of refractory was carried out for Rotary Kiln in cement plant. The refractory used in Kiln is High Alumina Bricks (Al2O3). During the inspection the erosion bricks / damaged bricks were identified and recommended for replacement. Cutting of Refractory specimens and witnessing the tests like Bulk Density, Cold Crushing Strength, Bulk Density Of Wax Emersion, Permanent Linear Change & Abrasion Resistance Test as per ASTM standards.

• To carry out routine Safety Audit at site.

• Inspection, Testing & Commissioning of Spur Pipe lines.

• Radiographic and Automatic Ultrasonic testing Interpretation of welded joints.

• Surveying of site to check for the feasibility of carrying out the construction work as per planning & drawings.

• Checking of As-built & As-laid drawings prepared for material re-conciliation.

• Maintaining detailed record of all the activities carried out on site.

EMPLOYMENT HISTORY

: • Working with Intertek Moody International (I) Pvt.Ltd since As Coordinator QA/QC (Feb 2011 till date)

• Working with FLASH FORGE Pvt.Ltd as QA&QC Manager (July 10 Dec 10)

• Worked with BUREAU VERITAS INDIA Pvt.Ltd

As Surveyor (Feb08 to June10 )

• Worked with VELOSI Certifications (India) ltd.

As Surveyor (May 07 to Feb08)

• Worked with GLIS (India) Pvt.

As Surveyor (Nov0’6 to April’07)

• Worked with Contractor: Sree Durga Constructions

Inspection Engineer(Jan’00 to Dec’04)

MAJOR PROJECTS HANDLED

:

• Inspection for BHEL brought out items at vendor place. And coordinating for BHEL –Hyderabad Region.

• Fabrication of PRESSURE VESSEL and HEAT EXCHANGERS for KANORIA CHEMICAL Ltd.

• Jindal Power & Steel Raw Water pipe laying for 56 km (Dual Line)

• KSK-Wardhapower Company Raw Water Pipe laying at Warora.

• Bharat Petroleum corporation LPG pipeline Above and Underground.

• CTE and CWC Coating, Anode Installation and Resistance test for L&T MHSRP-II at Jindal, Mundra.

• Anode manufacturing for KGD-6 project at Kandla PSL Ltd.

• Pipe laying for Dahej to UranPipeLine for GAIL.

• Mora to Vapi Pipeline for GSPL.

Scope of Work:

Fabrication of PRESSURE VESSEL and HEAT EXCHANGERS

• Client : KANORIA CHEMICAL&INDUSTRIES Ltd.

• BHEL : Piping for Thermal Power Projects.

• NAVAL DOCKYARD (Vizag): Manufacturing Titanium Water Collecting Tanks and Exhaust Trucking for INDIAN SUBMARIENS.

• Manufacturer: FLASH FORGE Pvt.Ltd.

• Drawing review, QAP approval, Liaoning with Third-party (LLOYD’S REGISTER ASIA), Document Preparation, and Carrey out daily report Radiographic Interpretation of welded joints.

• Preparing WPS/PQR, Welder Qualification

Project: LPG GANTRY for Above and Underground

Client: BPCL

Contractor: Lloyds Insulations Ltd.

• Third Party Inspection of the pipeline project for transmission gas pipeline for 900 Mts with BVIS inspection services. Approval of WPS &PQR, ITP, Welder Qualification, Radiography-testing Interpretation of welded joints. Hydro Test Witness.

Project: IOCL Kondapalli.

• Inspection at IOCL Kondapalli for servicing the 3x150MT LPG storage Bullets.

• Carried out all NDT & Hydro Pressure Test

Client: All seas.

Owner: RIL

Project: KG-D6 field development.

• Third Party Inspection for Anode manufacturing for RIL (KG-D6) project, at PSL Ghandhidam.

• Witness of Manufactured Anode as per ITP.

Dahej Uran Pipeline Project (DUPL)

Client: M/s. GAIL

Consultant: M/s. Tracteble Engineers India.

Contractor: ESSAR CONRUCTIONS/KPTL.

Pipe Size: 30”Length: Approx. 500 Kms.

• Third Party Inspection of the pipeline project for transmission gas pipeline from Dahej to Uran. With Germischen Llyod inspection services. Radiographic and Automatic Ultrasonic testing Interpretation of welded joints.

Client: M/s. Gujarat Gas Company Limited.

Consultant: M/s. Tractebel

Contractor: L&T.

Pipe Size: 30”

Length: Approx. 128 Kms.

• Third Party Inspection of the pipeline project for transmission gas pipeline from Mora to Vapi. Velosi Certifications Services (I) Pvt Ltd. To carry out routine Safety Audit at site. Inspection, Testing & Commissioning of Spur Pipelines. Radiographic Interpretation of welded joints. Surveying of site to check for the feasibility of carrying out the construction work as per planning drawing. Checking of As-built & As-laid drawings prepared for material re-conciliation. Maintaining detailed record of all the activities carried out on site.

JOB PROFILE:

• Inspection of equipments, Inspection of Piping & Pipelines, QA/QC & Project monitoring for EPIC Projects, Weld Inspection, NDT.

• Radiographic Interpretation of welded joints.

• Preparing WPS/PQR, Welder Qualification.

• To carry out routine Safety Audit at site.

• Inspection, Testing & Commissioning of Spur Pipe lines.

• Surveying of site to check for the feasibility of carrying out the construction work as per planning drawing and ITP/QAP.

• Checking of As-built & As-laid drawings prepared for material re-conciliation.

• Maintaining detailed record of all the activities carried out on site.

Knowledge of Computers:

Operating System: DOS, Windows 95/98, Windows 2000, Windows XP, MS-Office.

E-Mail:m2jshl@r.postjobfree.com

Mobile: +91-970*******



Contact this candidate