A summary of more than 20 years of continuous extensive experience in the field of mechanical and structural engineering practices. Majority of the role held is in Quality Control and Monitoring inspection for various industries to name the few; refineries, petrochemical ,power generating plants ( such as Hydro power plant,coal fired, diesel powerplant )with more focus in the Oil & Gas sector manufacturing, construction,fabrication & installation facilities . With broad experiences in the fabrication,installation and hook-up/tie-in for offshore platform facilities, jackets(4,6 and 8 legged assembly) topsides modular platforms, decks and sub – sea pipelines.

Good knowledge in using international codes and standards, company procedures and specifications.

The enclosed CV will show that in addition to these broad experiences I mentioned above, I have possessing necessary qualifications which I’m sure could be used to advantage and benefit for working in your company.

Very Truly Yours,

Elvis M. Fajutagana

Registered Mechanical Engineer

PMP- Certified

AWS- Certified Welding Inspector

CSWIP – 3.2

NACE- CIP LEVEL 2 Certified

ELVIS MORES FAJUTAGANA

Address : Balimbing,San Pascual, Batangas

Philippines

Mobile No. +971-050-237-8661 (U.A.E.)

+63-919-***-**** (Phils.)

e-mail : isxrzm@r.postjobfree.com

PERSONAL DETAILS:

Full Name : ELVIS MORES FAJUTAGANA

Date of Birth : December 09, 1966

Place of Birth : Labnig, Corcuera, Romblon, Phils.

Nationality : Filipino

Marital Status : Married

Sex : Male

Health : Excellent

Passport No. : EB3312632

PROFESSIONAL QUALIFICATIONS:

• Registered Mechanical Engineer - RME

Phil. license No.….....042855

• Project Management Professional - PMP ( Certified )

PMP No…………….. 0448328

• Certified Senior Welding Inspector – CSWIP 3.2

Certificate No………14499

Certified Welding Inspector _ CSWIP 3.1

Certificate No……… 5078

• Certified Welding Inspector _ AWS-CWI ( former )

Certificate No….......96041551

• NACE Coating Inspector Level 1 – NACE CIP 1 Certified

Certificate No….. 38087

• NACE Coating Inspector Level 2 – NACE CIP 2 Certified

Certificate No……38087

• Certified NDT level II…………… ( RT, MT, PT )

• Qualified SAUDI ARAMCO QC Supervisor ( Offshore and Onshore )

SAP no. …………….70007630

Resume of Elvis M. Fajut…( Cont’d..2 )

DATE

EDUCATION:

Trainings & Courses attended :

March 17 - 29, 2012

Oct.02 - Dec. 11, 2009

Oct. 2 - Oct. 21, 2007

April 2006 - May 2006

Feb. 2007 - May 2007

Jan. 2007 - March 2007

June 2006 - Aug. 2006

Nov. 2003 - Dec. 2003

July 2001 - Aug. 2001

March 1996 - April 1996

June 1993 – July 1993

NATIONAL ASSOCIATION OF CORROSION ENGINEERS-ABU DHABI- U.A.E.

NACE - COATING INSPECTION PROGRAM – LEVEL 1 & 2

CHICAGO MANAGEMENT TRAINING INSTITUTE

COST ENGINEERING – SKILLS and KNOWLEDGE OF COST ENGINEERING FIFTH EDITION.

Cambridge Educational Institute – Abu Dhabi, U.A.E.

Primavera Project Planner P3 - V3.1

Cambridge Educational Institute – Abu Dhabi, U.A.E.

A Registered Education Provider of PMI

Earned a title of Project Management Professional – PMP

FILIPINO ASSOCIATION for COMPUTER EXCELLENCE

Philippine Overseas Labor Office – Abu Dhabi, U.A.E.

• International Computer Driving License ( I.C.D.L. )

• PC ASSEMBLY

OVERSEAS FILIPINO CIVIL ENGINEER ASSOCIATION

Philippine Overseas Labor Office – Abu Dhabi, U.A.E.

• BASIC AUTOCAD

FILIPINO ASSOCIATION for COMPUTER EXCELLENCE

Philippine Overseas Labor Office – Abu Dhabi, U.A.E.

• GRAPHIC DESIGN – Adobe Photoshop & Illustrator

The Welding Institute - Abu Dhabi , U.A.E

• Senior Welding Inspection Course – CSWIP 3.2

The Welding Institute - Manila , Philippines

• Welding Inspection Course – CSWIP 3.1

Nondestructive Testing & Training Center – Al-Kbobar, K.S.A.

• AWS – Certified Welding Inspector

Oilfield Industrial Services (O.I.S.)- Masila, Rep. Of Yemen

• Industrial Radiography

June 1984 - April 1989

Resume of Elvis M. Fajut…( Cont’d..3)

EXPERIENCES :

Technological Institute of the Philippines –(T.I.P)

20th Avenue, Cubao, Quezon City, Philippines

Earned a degree in Bachelor of Science in Mechanical Engineering.

April 2003 - to date

Role

On the job responsibilities National Petroleum Construction Company - NPCC

Musaffah, Abu Dhabi, U.A.E.

Quality Control Supervisor

As Quality Control Supervisor, I ensure that the implementation and overseeing of applicable standards and quality procedures, the product requirements, and its compliance are being followed. (see attached synopsis )

March 1999 – March 2003

Role

On the job responsibilities

Whessoe, Philippines Construction Inc. – WPCI

Makati City , Philippines

Held a various positions namely; Project Engineer, Welding Engineer and Head of Quality Control in which varies from project to project requirements. (see attached synopsis)

Oct. 1997 – June 1998

Role

On the job responsibilities

PT. Transalindo Eka Persada

Batu Ampar, Batam , Indonesia

Head of Quality Control

As Head of Quality Control, I am in-charge of Quality Section with a team of 30 QC inspectors and engineers working hand in hand to ensure that the implementation of the applicable Quality procedures, codes, standards, project specifications and requirements has been adhered to.

Apr. 1995 – June 1996

Role

On the job responsibilities

Belleli Saudi Heavy Industries

Kingdom of Saudi Arabia

Welding Inspector & Laboratory Technician

A Welding Inspector and laboratory technician who assisted the laboratory supervisor in the preparation of all laboratory activities. ( see attached synopsis.)

Apr 1994 – Nov. 1994

Role

On the job responsibilities Engineering Equipment Inc. (Phils.) - EEI

Batangas city, Philippines

Welding Inspector

Worked as a QC Welding Inspector for the fabrication and installation of structural components and power piping for Pilipinas Shell Petroleum Refinery Company.

Consolidated Construction Intl. Company ( C.C.I.C.)

(Masila – Republic of Yemen )

Structural and Pipe Fabricator

Primary job responsibilities was the fabrication and installation of structural components, power piping above and underground pipelines for Central Processing Facility project.

Resume of Elvis M. Fajut…( Cont’d..4)

May 1989- March 1993

Role

On the job responsibilities PH Engineering Works & Machine Shop

San Pascual Batangas , Philippines

Charge hand Fabricator

Involved in various shut down modifications and fabrication of piping and structural services for Caltex Refinery – Batangas

SYNOPSIS OF WORK EXPERIENCES

Role

On the Job responsibilities

Resume of Elvis M. Fajut…Cont’d…5 )

As Quality Control Supervisor

• Direct, supervise and participate in Quality Control

activities to determine product conformity to customer

specification through independent inspection and tests

in accordance with the Project Quality Plan.

• Liaise with QC/NDT/Certification/Welding Engineering and customer to ensure that Quality problems are addressed and technically resolved.

• Identify non conformity for rectification and assure final

resolution.

• Conduct QA audits to verify practice is compliance to project specific procedures.

• Initiate Quality Planning for the project to assure compliance first time through proactive and preventive measures and consult with the Project Quality Manager concerning prevention and appraisal resources and the effectiveness of project Quality Plan/Procedures necessary to achieve the product quality.

• Initiate evaluation for non conforming items.

• Develop Project Quality Plans, Inspection and test Plans in

consultation with Project Quality Manager.

• Appraise product quality in accordance with the Project Quality Plan, Inspection & Test Plan and determine conformity and non-conformity.

• Assess the manpower requirements during the project execution as per the schedule and the progress.

• Co-ordinate interface with Operations, Certifying Authority,Client, and subcontractor assuring conformity to project specifications.

• Verify QC welding Inspectors effectiveness through random audits.

• Exercise proactive approach in prevention of a problem by

interface with production, engineers and management

personnel.

• Conduct internal audits to assess the effectiveness of QualitySystem outlined in Project Quality Plan and Inspection Test Plan onboard the barge and in preparation prior to mobilisation.

• Liaise with customer representatives for ensuring product

conformity and stage release for each activity denoted

within the Project Quality Plan/I.T.P.

• Ensure that inspection stages are carried out in line with approved inspection plans and/or procedures.

• Maintain records for inspection and test status and for stage and final inspections and tests.

• Review periodic reports covering the relevant inspection activities and the resultant observations.

• Experienced in offshore works activities such as pipelaying,hook-up, tie-in and installation of top sides modular platforms and jackets.

• Performed punchlisting and walkdown of outstanding items prior to Hydro testing.

Role

On the Job responsibilities

As Project Engineer

• Reporting directly to project operation manager for the execution and implementation of the projects deliverables.

• Ensure that works has been carried out safely and efficiently in a competent manner.

• Conduct orientation and toolbox meeting to ensure safely and security of all construction activities and workers.

• Direct and manage project team, tracking team member’s performance, resolving issues to enhance project performance.

• Coaching project team members the importance of complying with the applicable Quality standards and project requirements to ensure the project deliverables are completed to the satisfaction of stakeholders.

• Monitor daily work progress against planned schedule.

• Preparation of Work packages for Hydrotesting.

Role

On the Job responsibilities

As QC Head

• Develop Project Quality Plans, Inspection and test Plans in

consultation with Project Quality Manager.

• Appraise product quality in accordance with the Project Quality Plan, Inspection & Test Plan and determine conformity and non-conformity.

• Assess the manpower requirements during the project execution as per the schedule and the progress. Develop and retain understanding of project quality requirements as defined in the project specifications and applicable codes and standards.

• Working hand in hand with a team of QC inspectors and engineers for the implementation of quality procedures and standards.

• Monitor work in progress and the consistency of

procedures application

• Reviewed NDE procedures submitted by sub-contractors

• Evaluate weld radiographic films submitted by NDE – Sub-contractors.

• Ensure that manufacturer data reports are filed progressively and in timely manner.

• Reviewed final documents prior to submission to client/customers.

Role

On the Job responsibilities

Resume of Elvis M. Fajut…Cont’d…6

As Welding Engineer

• Coordinate with the Project manager for the relevant materials to be used for the project and what product requirements needed to be delivered to the customer.

• Prepare welding procedure and specifications

• Performed weld procedure qualification testing.

• Performed and witnessed welder performance and qualification testing.

• Witnessed mechanical and destructive testing for PQR and welders qualification.

• Conduct welding inspection crash course for the enhancement of QC inspectors and welders regarding the importance of producing a quality sound welds.

• Monitor with the QC inspectors that the relevant welding procedure requirements has been implemented in the worksite.

Role

On the Job responsibilities

As Laboratory Technician

Prepared mechanical testing plans such as:

• Welders qualification test

• Welding qualification procedure

• Material testing.

Performed mechanical testing that includes :

• Tensile test – using Dartec Universal Testing Machine

• Compression testing

• Impact Testing

• Macro and Micro Hardness Test

• Portable hardness test

Other test and calibration performed

• Pressure gauge and charts calibration

• Periodical instrument calibration

• Ferrite checking

• Surface roughness checking

• Conduct PMI -Positive material identification.

• Chemical etching.

• Prepare relevant documents and mechanical test reports

Role

On the Job responsibilities As a Structural Fabricator & Pipe Fitter

• Involves in the fabrication of pipe spool and installation of power piping and pipelines

• Fabricate pipe spools according to the relevant isometric drawings

• Fit-up,install pipes,erect pipe racks and other pipe supports.

• Cutting and beveling of pipes as per the required drawings.

OFFSHORE PROJECT INVOLVES:

MAY-NOV.2004 QC- INSPECTOR - SAUDI ARAMCO- KSA (ABU SAFAH FIELD )

Onboard DEEMA,AHMED rigs for the Tie-In and Hook-Up of Risers

and various pipe sizes for platforms ABSF TP-2, ABSF 10/15,

ABSF 17/22, ABSF 90 and ABSF 100.

FEB-MAY 2005 QC- INSPECTOR -TOTAL-ABK–ABU DHABI U.A.E.(ABK FIELD )

Onboard rig KAMIKAZI and SEP-350 barge for the installation &

Hook-Up of NKKP jacket, top sides modules, NKKP-KPP bridge

And HP flare.

JULY- SEPT 2005 QC- INSPECTOR - OFFSHORE KHUFF GAS. DEV.– ABU DHABI

U.A.E -UMM SHAIF & ABK COMPLEX ( OKGD PROJECT )

Onboard rig LEEN & SEP-350, barge for the installation and &

Hook- Up of TA jacket, top side module.

NOV 07 - MARCH 08 QC- SUPERVISOR -QATAR PETROLEUM/SIME DARBY –

STATE OF QATAR NORTH FIELD BRAVO -QATAR

Onboard HLS-2000 barge for the installation and & Hook-Up

of BH-D05A jacket & top side platform.

Resume of Elvis M. Fajut…Cont’d…7

APRIL - AUGUST 08 QC- SUPERVISOR - QATAR GAS LIQUIFIED LTD.

STATE OF QATAR NORTH FIELD BRAVO -QATAR

Onboard HLS-2000 & PLB -648 barges for the installation &

and & Hook-Up of WH4 & WH5 top side platform and Heli-deck.

NOV 08- AUG.2009 QC- SUPERVISOR -SAUDI ARAMCO- KSA

( MARJAN & ZULUF FIELD )

Onboard HLS-2000 barge for the installation of Jackets & Top side

Platforms for MRJN TP-5 & 6, ZULUF TP-5,6,7,& 8.

Onboard DEEMA barge for the Tie-In and Hook-Up of Risers,

various pipe sizes for platforms MRJN TP-5,6, ZULUF TP-5,6,7,& 8.

AUG- SEPT.2010 QC- SUPERVISOR - OCCIDENTAL PETROLEUM

(OXY-PETROLEUM) ISSD & ISND FIELD- STATE OF QATAR

Onboard PLB-648 barge for pipe laying of 12” & 20” pipeline.

SEPT- OCT.2010 QC-SUPERVISOR - QATAR PETROLEUM DEV.( QPD )

ISSD & ISND FIELD- STATE OF QATAR

Onboard PLB-648 barge for pipe laying of 6” pipeline.

NOV 2010- MAY.2011 QC-SUPERVISOR - ONGC - MUMBAI ( B-22 & RS-12 FIELD )

Onboard HLS-2000 barge for the installation of Jackets & Top side

Platforms for B-22 & RS-12 field development project BS-13A,

B-149A,B-22A & RS-12, N14,N18 & N20.

Onboard PLB-648 barge for the Tie-In and Hook-Up of Risers,

various pipe sizes for platforms BS-13A, B-149A,B-22A & RS-1.

JULY 2011- PRESENT QC-SUPERVISOR/INSPECTOR – ADMA-OPCO, ABU DHABI U.A.E.

PROJECT : UMMSHAIF WELL HEAD TOWER US 40/24 – INTEGRATED GAS

DEVELOPMENT PROJECT.

ZAKUM CENTRAL SUPER COMPLEX (ZCSC)CSP-PP PLATFORM

DEMOTHBALLING PROJECT-EPC

Onboard SEP-350 barge for the De-mothballing and Re-commissioning

Of Oil production facilities which includes demolition of existing

Facilities ,equipment & piping , Installation of structural extentions

new equipment & piping & refurbishment of existing vessels(

Separators & Gas Scrubbers.)

Isolation/Sectionalizing valves on 16” ring main line by Hot Tapping/

Stoppling and modification & piping Tie-ins on the existing pipelines.

Professional Memberships & International Affiliations :

• Project Management Institute

• American Welding Society (former)

• Philippine Society of Mechanical Engineers ( UAE Chapter )