Snamprogetti Engineering & Contracting

C U R R I C U L U M V I T A E

Application for QC Supervisor ( Piping & RTR )

SAUDI ARAMCO SAP # 70008575 SINCE 2008

NAME: MUHAMMED SIRAJUDDIN

DATE OF BIRTH : APRIL 4, 1971

NATIONALITY: INDIAN

QUALIFICATION : DIPLOMA IN MECHANICAL ENGINEERING PASSED IN 1992 ISO 9001-2008 QMS Auditor / Lead Auditor IRCA training attended from Bureau Veritas India pvt ltd.

ASNT NDT LEVEL II in PT,MPT,UT, and RT. INDIA KALVA ENGINEERS.

TRAINING / SEMINAR

Training on ISO 9001-2008 Awareness. Quality Management System requirements.

Training on closed awareness & understanding of Saudi Aramco Engineering Standards, Procedure, & Drawings such as SAES, SAMSS, SAEP, SASD, SATIP, SAIC .

International Standards such as ASME, ASTM, ANSI, ASNT, API, AWWA, MSS,BSI. •

Awareness and understanding of Schedule “Q” Saudi Aramco.

SEMINAR ATTENDED FOR ASSEMBLY INSTRUCTION & INSTALLATION OF RTR, GRE, PIPES & FITTINGS AT BONDSTRAND LTD, AMIANTIT GROUP KSA..

AUGUST 2018 TILL PRESENT

SM BROTHERS CONTRACTING.

PROJECT : SHUTDOWN JOBS AT ACC CEMENT LTD, WADI INDIA. QC MECHANICAL ENGINEER

RESPOSIBILITIES :

Checked all kinds of inspection procedure for the heavy structure pipe, all Instrument & equipment calibration and inspection of materials, silo, vessel, Hoper, Gas holder, fuel tanks etc inspect and installation of valves and checking flow direction of check valves/glove valves and ensure that all pertinent Inspection QC Records & documentation are in order for final handed-over to the client.

Snamprogetti Engineering & Contracting

Reveiw of document for Material receiving inspection of structural/mechanical material etc. DEC 2016 T0 MAY 2018

SAUDI ARABIAN SAIPEM LTD.

.

PROJECT : SAUDI ARAMCO OIL COMPANY

JAZAN IGCC PACKAGE # 2.

QA/QC Inspector ( Piping & RTR )

Responsiblities :-

Responsible for QC Inspection in accordance to approved PQP Procedure for the mechanical piping of metallic & non-metallic RTR inspection installation of pipes fittings & spools, gasket installation,bolt tightening. Installation of all types of valves & check valves, other related mechanical activities. Visual inspection of spools marked up & identification.

Check the instrument equipment use for hydro testing such as manifold, pressure gauge, relief valves ensure that properly calibrated with tag label sticker for valid date of expiry. Conduct line checking on all pipeline to ready for hydro test.

Conduct inspection activities in project through the implementation of PQP, QCP, ITP, as per approved issue for construction drawing &applicable standards.

Witnessing hydrostatic test of new pipe line &spools, valves, cleaning & flushing pipes verification, identification of pipes spools, valves equipment’s. Ensure that all pertinent inspection QC records & documentation in order to final handover to clients.

Verify line modification prior to proceed & make sure all procedure as per standards & verify approved construction drawing base to the latest revision review as build drawing and finally coordinate to client for all hold point inspection required.

All above items are approved as per P.O.& NMR 601&602 together with compliance certificate and material test certificate prior to release to project site and provide technical assistance to QA/QC Manager for the preparation of project quality plan, Quality control procedure,& ITP, work instruction pre— commissioning & test package material level of inspection, Purchase requisition submittals, Vendor source, Inspection assignment package, Final inspection disposition report, Assist the QA Manager in training & indoctrination of QA/QC Personnel especially on wielding piping & structural inspection.

Coordinate for the third party testing agency technician for the proper execution of a particular jobs. Maintain QA/QC statistic for the project responsible for the supervision & organization of QA/QC activities for implementation of all standards, specification, testing, precommissioning of project. Report directly to the QA/QC Manager regarding the status of activities Snamprogetti Engineering & Contracting

include preparation & filing documents and two week ahead report for weekly meeting

MARCH 2014 –MARCH 2015

Project: GS E & C South Korea.

PETRORABIGH PHASE II, ( SAUDI ARAMCO & SUMITOMO

CHEMICAL )

UO1 Interconnecting Petrorabigh phase II, RABIGH SAUDI ARABIA QA/QC PIPING SUPERVISOR

Responsibilities

Review the documents according to project specifications

(procedures, method of statement, Inspection test plan and etc..)

Participate in subcontractor kick-off, pre inspection meetings and project quality meetings. Review of the subcontractor documents and monitor Sub-contractor performance for compliance with quality requirements.

Ensure and review of material test certificates and witnessing of material inspection as per project requirement and /or client specification for procurement of materials.

Review of welding procedure specification and witnessing welding procedure qualification test and welder performance qualifications to ensure compliance to the able code, approved drawings, procedure & specifications.

Co-ordinate a team of Piping Inspectors.

At all times adopting the one team approach for the full execution of the fabrication works.

As a representative of Company leading by example on all issues

Ensure that the design intent is preserved in accordance with technical engineering requirements and within Company and Project quality expectations.

Ensure compliance with the Project Quality Plan and Quality Strategy.

Support the Construction team and ensure that all Quality requirements and procedures are understood.

Attend appropriate quality audits and Inspections covering Contractor, Suppliers and sub-contractors.

Report deviations and Non-conformances.

Ensure Contractor quality management plans are followed.

Participate in weekly quality meetings.

Generate weekly QC Inspection report and track and expedite closure of quality related issues.

Ensure all Quality related documentation deliverables are identified collated, reviewed and stored.

Carry out any additional activities as assigned by the Quality Manager.

Interpretation of P& IDs, Plan drawings & Isometric drawings

During surveillance randomly checking of the Fit-up, Pre-heat, Snamprogetti Engineering & Contracting

Inter pass temperature etc. as per applicable WPS & final Visual Inspection of completed welds for the occurrence of Porosity, Cracks, Undercut, and Spatters prior to Non Destructive Testing

Inspection of pipe supports, Guides, anchors on the lines installed. Inspection for flexibility, support and anchoring of piping. Punch listing of piping system after completion of fabrication before blowing/flushing and commissioning of the system.

Witnessing Hydro test, Pneumatic test, Visual test on completed lines, Flushing and Sign off

Provide technical support in the areas of non-destructive examination for welded joints and leading NDT Technicians to perform Radiography, DP, MPI & PMI

Preparation of test packages and compilation of QA/QC Dossiers

Review of Radiographic films, PWHT reports, PMI reports, Hardness reports, and Line History sheet requirement

Issuing NCR’s when Non-conformity activities noted.

.

.

DEC 2011 - Aug 2013

SAMSUNG ENGINEERING, South Korea.

PROJECT : SAUDI ARAMCO OIL COMPANY

SHAYBAH NGL Inlet and Gas treatment plant, SAUDI ARABIA QA/QC Piping Inspector

Responsibilities Witnessing mechanical tests (Destructive testing).

Verifying and reviewing welding consumable test certificates and monitoring the preservation, storage & handling of electrodes and calibration status of electrode backing and holding ovens

Monitoring/ witnessing and surveillance inspection of ongoing welding, fabrication and painting activities at the field and work shop

Witnessing and surveillance inspection activities during construction of new pipelines, hook-up lines, re-routing lines and modification on piping’s for well manifolds, gas dehydration units, and piping’s from oil and gas wells.

Witnessing hook up and tie-in, shout-down activities like new well to well manifold pipe lines/ existing line tie-in, replacement of tie-in spools and etc..

Witnessing the cold bend inspection activities such as visual inspections of production bends, verification of dimensions for completed bends, gauging, surface preparations, coating and markings & tagging as per project requirement and /or client specification.

Inspection of subassemblies like road crossing spools, tie-in spools finished items for appearance, workmanship, dimensions, surface conditions, testing, coating inspections Snamprogetti Engineering & Contracting

and monitoring all QA/QC Inspection activities in related works

Monitoring valve testing preparation activities and witnessing valve testing.

Verifying equipment conditions, calibrations status, checking the suitability of protections and precautionary measures adopted for the Inspection tools, Welding and other equipments and storage quivers. Witnessing various NDT activities, PMI and hardness test and reviewing reports

Witnessing/ surveillance inspection of heat treatment activities and review of heat treatment method of statements and PWHT Charts and Reports.

Interpretation of Radiographic films and reviewing the reports.

Raise Non-Conformance (NCR), where warranted, on process / product non-conformances.

Attending line walk/check for confirmation of the punch items

(pre and post pressure tests) and preparing additional punch items if necessary.

Reviewing the hydro test packages and ensures all inspection/test completed and all reports/ documents in place before approval of the packages prior to the pressure tests.

Line checking and verifying and clearing the punch items before the pressure test.

Witnessing of cleaning and gauge pigging activities in pipe lines and review the reports.

Witnessing the Pressure Tests (Hydro, Pneumatic and Service Tests) activities and reviewing the test reports

Witnessing of cleaning, drying, flushing and pigging activities in pipe lines prior to the tie-in and reviews the reports.

Verify and close out punch list items and inspection of reinstatement activities.

Witnessing the final painting inspection and review the reports.

Attending Mechanical completion walk through and preparation of punch listing for newly installed beam pumps for wells

Physical verification of vendor’s program like documentation, fabrication schedules, inspection intervention, confirmation of delivery date & outstanding action points to be completed

Attending Mechanical completion walkthrough/ meeting and/or Pre start-up safety review meetings/ walk down.

Final Inspection prior to dispatch the product which is included Cleaning, Coating, Packing and Marking and review of final documentation dossier

MAY 2007 -OCT 2011

GULF CONSOLIDATED CONSTRUCTION CO, KSA

PROJECT : SAUDI ARAMCO CO, LTD.

PROJECT EXECUTED. SAP # 70008575

Pipeline upgrade for area classification compliance phase II ABQIAQ to UTMANIYAH area HOTTAPPING sites Contract # 660******* Snamprogetti Engineering & Contracting

B.I. # 10-03096 (501) QA/QC Mechanical Inspector ( Piping )

Construction of Qassim crude oil pipeline project of QCPP Qassim area Contract # 10821103/00 : B.I.# 21-02025 (502) QA/QC Piping Inspector

Increased RTDB-1 Pipeline capacity of RAS TANUARAH REFINERY plant area. Contract # 660******* : B.I.10-00613 (278) QA/QC Piping Inspector

Increased DHAHRAN-1 Pipeline capacity Dhahran area, Contract # 660******* ; B.I. # 10-00035 (503) QA/QC RTR Inspector QA/QC Piping Engineer.

Responsibilities

Responsible for QC Inspection in accordance to approved PQP Procedure for the mechanical piping of metallic & non-metallic RTR inspection installation of pipes fittings & spools, gasket installation,bolt tightening. Installation of all types of valves & check valves, other related mechanical activities. Visual inspection of spools marked up & identification.

Check the instrument equipment use for hydro testing such as manifold, pressure gauge, relief valves ensure that properly calibrated with tag label sticker for valid date of expiry. Conduct line checking on all pipeline to ready for hydro test.

Conduct inspection activities in project through the implementation of PQP, QCP, ITP, as per approved issue for construction drawing &applicable standards.

Witnessing hydrostatic test of new pipe line &spools, valves, cleaning & flushing pipes verification, identification of pipes spools, valves equipment’s. Ensure that all pertinent inspection QC records & documentation in order to final handover to clients.

Verify line modification prior to proceed & make sure all procedure as per standards & verify approved construction drawing base to the latest revision review as build drawing and finally coordinate to client for all hold point inspection required.

All above items are approved as per P.O.& NMR 601&602 together with compliance certificate and material test certificate prior to release to project site and provide technical assistance to QA/QC Manager for the preparation of project quality plan, Quality control procedure,& ITP, work instruction pre— commissioning & test package material level of inspection, Purchase requisition submittals, Vendor source, Inspection assignment package, Final inspection disposition report, Assist the QA Manager in training & indoctrination of QA/QC Personnel especially on wielding piping & structural inspection.

Coordinate for the third party testing agency technician for the proper execution of a particular jobs. Maintain QA/QC statistic for the project responsible for the supervision & organization of QA/QC activities for implementation of all standards, specification, testing, precommissioning of project. Report directly to the QA/QC Manager regarding the status of activities include preparation & filing documents and two week ahead Snamprogetti Engineering & Contracting

report for weekly meeting

SEPT 2004 –AUG 2006

BONDSTRAND LTD, AMIANTIT GROUP DAMMAM, KSA.

MANUFACTURER OF REINFORCED THERMOSETTING RESIN, GRE, FBE PIPES and FITTINGS

QA/QC PIPING INSPECTOR ( RTR )

Responsibilities

Review Method of Statement and ITP for RTR pipe.

Review BPS (Bonding Procedure Specification).

Inspection of RTR pipes fabrications and installations.

Inspection of curing time of adhesive depends on diameter of the RTR pipe.

Conducting each pipes and fittings 100% checking of various RTR joints such as Taper-taper joint, Mechanical Quick lock joint and Butt and wrap joints.

Inspection of RTR repairs depends on the approved repair procedure.

Inspection of wrinkles, crack, inside surface of RTR Pipes.

Strict inspection of compaction and sand bagging and check compaction test report.

Prepare hydro test packages and punch list.

Witness hydro testing and water flushing.

Nov 2002 –MAY 2004

SOULOJAN METAL FABRICATION, DAMMAM KSA.

QA/QC Mechanical Inspector

Responsibilities

Review material certificate and delivery notes, inspect delivered material as per before

acceptance and approval.

Interpret fabrication & Erection drawings.

Inspect fit-up tolerance of Fabrication of Steel Structure according to plans and specs

Checked dimensional and visual inspection in accordance with inspection and te specs

Inspection of final weld visual

Witnessed NDT (Non Destructive Testing) with the use of MT and DPT

Submit inspection reports to the QC Manager.

Coordinate and supervise technicians and other testing requirements as per project requirements

Monitor and ensure that all works are in accordance with contract standards and specifications

Preparation of Inspection Test Plan & various types of Quality Control Procedu

Preparation of various types of Quality Control Reports and Manufactures Rec

PMI (Positive Material Identification) check of Pipes, Flanges, Fittings etc.,

other NDE activities like DPT, MPT, Hardness test & Thickness survey Snamprogetti Engineering & Contracting

Prepare inspection request prior to accept the construction piping / welding wo

pressure testing and releasing of fabricated pipe lines in order to prepare certif completed

FEB 1996 – JULY 1998

SAUDI OGER LTD, SAUDI ARABIA.

PROJECT : ROYAL COMMISSION WWTP JUBAIL &

KKIA PROJECT RIYADH.

QC Field Inspector

Responsibilities Installation of firefighting and chilled water system and all the accessories related to the system.

Supervisory the daily work activities.

Modified shop drawing as built as per site condition.

To prepared daily and weekly planning activities.

To submit visual and installation inspection prior to hydro test.

To perform hydro test and submit for inspection. To submit precommissioning and commissioning

OCT 1992 –FEB 1996

ABB ABL LTD, SHAHABAD, KARNATAKA INDIA.

Manufacturer of Power plant equipements and Cement machineries.

Assistance QA/QC Mechanical Inspector.

Responsibilities

Checked all kinds of inspection procedure for the heavy structure pipe, all Instrument & equipment calibration and inspection of materials, silo, vessel, Hoper, Gas holder, fuel tanks etc inspect and installation of valves and checking flow direction of check valves/glove valves and ensure that all pertinent Inspection QC Records & documentation are in order for final handed-over to the client.

Material receiving inspection of structural/mechanical material etc. With best regards...

YOUR SINCERELY

MUHAMMED SIRAJUDDIN AW

QC PIPING ENGINEER