Profile:

A Graduate Process Engineer with 61/2 years of engineering multidiscipline experience in Simulation, Basic & Detailed Engineering, Project Management, Pre-Commissioning & Commissioning activities related to Oil & Gas Project and Operational activities related to onshore upstream / downstream facilities. Specific Work Experience

Participate in site visitto define scope of work, data collection and preparation of Technical and Commercial Proposal. Preparation of Pre-Commissioning & Commissioning Manuel's.

Practical experience in Engineering of Crude Pumping Stations, Crude Gathering Facilities, Oil & Gas transfer lines and various Utility Systems.

Familiarity with Process Design Safety Requirements, Including safety related to defining of hazardous area classification, risk assessment recommendation, assist in evaluation of critical equipment’s, perform detailed engineering design of active & passive firefighting system and fire and gas detection system based on NFPA Standard. Participated in process hazard analysis such as HAZOP.

Assist/development of Process Block Diagrams, PFD’s and Process & Utility P&ID’s, line list, line schedules.

Familiar with preparation of Equipment and Instrument Process Data Sheets.

Sizing calculations for vessels, pressure safety & control valves for different condition and preparation of specifications.

Prepare process simulations for the process facilities using ProMax simulation software. Perform hydraulic calculations for piping and pipelines, hydraulic horsepower and total dynamic head required for pumps.

Process equipment design & selection based on industry standards.

Monitor performance of wells / processing facilities. Preparing daily production report. Follow up collection of oil and water samples during operating facility. Monitor the induced current readings regularly and take corrective measures. Coordinates with control room &production supervisor to ensure production operation changes are carried out according to company rules, regulations, efficiently and safely.

Good team player, hardworking and trustworthy person.Completed my work tasks on time and producing excellent work. Worked on my own with very little guidance required. Strength involved anything to do with most of process engineering activities and Capable of interacting effectively with other discipline Engineers.

Experience in the review processes and in using design tools, guides, project codes and specification and most of work related to process calculations and documentation development.

Knowledgeable with Industry International Standards such as API, NFPA, GPSA, ASTM, ASME. ISO, Shell Design Engineering Practices, Total General Specifications, OMV Design Philosophies and International Engineering Standards & Codes.

Have experience in use of ProMax Simulation Software. Strong computer skills for data tabulation analysis, statistical and email communications applicationsand report preparation (Excel, word, and power point) Page 2

Details of Professional Experience:

1) Organization : Professional Engineering "PE"

Location : Sana'a, Yemen.

Position : Process / Project Engineer

Working Period : Jan, 2019 – Up to Now

Type of Contract : Permanent" Monthly Rate"

Responsibilities:

Development of technical and commercial proposal documents. Sizing, selection and preparation of Process datasheet.

Performing Technical Specification requirements for procurement process, work with equipment vendor in the development of quote review and technical clarifications, reported the assessment of all procured equipment, instruments and material in order to confirm suitability for the project and all the operation parameters meet the requirements.Carryout the final cost of EPC Project. The following is the Kay Project Undertaken

Engineering Service, Supply, Installation, Testing, and Commissioning of solar pumping system with UNOPS, for seven (7) water wells in Sana’a, Amran, Al-Mahwit, Hajjah. -"EPCC".The project consists of submersible motors and pumps, wellhead facility, Flow lines and all necessary related to safety, electrical and Instrumentation along Utility Water Management system. The project scope includes design, Procurement, Installation, Testing and Commissioning of the entire facility as per international Standards and UNOPS requirements. Advice of the quality and quantities of each well required for the packaged unit and highlight the utilities not available.

Engineering Service, Supply, Installation, Testing, and Commissioning of Utility Water Distribution Network with UNOPS, various area in Mukalla, Hadramout.-"EPCC". The project consists of distribution system pipework, trunk lines and all necessary related to fitting, safety, electrical and Instrumentation along Utility Water Management system.

2) Organization : Ba-Fidel Int. Trading Group (PTG) Location : Sana'a, Yemen.

Position : Process/ Project Engineer

Working Period : Feb, 2018 – Dec, 2018

Type of Contract : Part Time "Hourly Rate"

Responsibilities;

Development of Process Design Basis and Process Description. Hydraulic Study Options and Calculation.

Preparation of Process Block Diagrams, UFD’s and P&ID’s drawings, Line List, Fluid List, Utility Schedule.

Procurement support by Technical Bid Evaluation and Vendor data review.

Performing various process calculations such as firewater hydraulic analysis, firewater and foam demand calculation, piping distribution network pressure drops calculation in various options, deluge system calculation. Sizing and selection of pressure safety and control valves, firewater and jockey Pumps. Performed various equipment specifications such as Deluge, Hydrant Monitor, Subsurface Injection Foam, Water Curtain Nozzle, Foam Branch Pipe, Mobile Foam Unit, Water Foam Monitor and Foam Distribution Package. Instrument / Technical datasheets preparation for fire flame detectors and fire heat detector, Smoke detector and hydrocarbon gas detector.

Performed the technical specification requirements for procurement process. Prepared requests for quotation and work with vendor in the development of quote review, response to queries and finalize the cost estimation.

Page 3

The following are the Kay Projects Undertaken:

Engineering Services, Development, procurement support and review of material requisitions, specifications, data sheets for the up-gradation of Fuel Loading/Unloading ADEN Airport Facility, Yemen. The scope was to check the suitability of extension of existing facility to be loaded/unloaded at a rate of 30000 bbl/day, design a new facility based on the extended capacity, and optimize of drain system and all necessary Safety & Control devices and Instrumentation along Loading/Unloading Management System.

Engineering Services, Development, procurement support for installation oftwo 2 No. of Diesel Fuel Storage Tanks with capacity of 20,000 BBL for each one and active Firefighting Protection system. Scope includes the basic design and procurement support of 2# NO. of Storage Tanks and Active Firefighting system.

3) Organization : OMV Exploration & Production Company Location : Kharwah Field, Block S2, shabu, Yemen.

Position : Well Testing Operator

Working Period : Oct, 2016 – Nov 2017

Type of Contract : Permanent" Monthly Rate"

Responsibilities;

Worked under Production Supervisor in developing of oil & gas production plan, Wellhead operation, well testing, early production facility, oil gathering / processing / pump stations. Check, verify and calibrate sensor/instrumentation as per relevant technical documents and quality control procedures.

Prepare daily production report. Well test data entry, oil & gas calculation for GOR, filter and strainer cleaning. Injection & operation of Christmas tree. Operation of water and gas injection wells.

Flow and pressure recording. Water, oil draining, and operation of all operating valves at crude oil pumping station. Check all alarms and trip switched with the instrument technicians. Familiar with different types of valves such as PCV, PSV, LCV and PRV controller and transmitters. Operating of crude transfer pumps, booster pumps, firewater pumps startup / shutdown operation. 4) Organization : YemCan Engineering, Procurement and Construction. Location : Sana’a, Yemen.

Position : Process Design Engineer/Technical Project Engineer Working Period : Jul, 2012 – May, 2016

Type of Contract : Permanent" Monthly Rate"

Responsibilities:

Participate in site visit to define scope of work, data collection and prepared scope reports. Prepared technical

/ commercial proposal, preparation of process engineering deliverable files.

Hydraulic Piping and Pipeline sizing for different flow phases.

Assist / Development of PFD's, UFD's and P&ID's Drawings, Line Lists, Fluid List, Utility Schedule etc.

Sizing of Process Equipment and preparation of Calculation notes & Process / InstrumentationData Sheetsand selection based on industry.

Performing Technical Specification requirements for procurement. Prepare vendor list, RFQ Process, work with equipment vendor in the development of quote review, technical clarifications, carryout the cost estimation of equipment and material mostly for process, mechanical and Instrumentation equipment.

Track all documents vendor/internal document cycle, coordinate with other discipline Engineers concerning Material Request (MR).

Preparation of Operating, Control and Shut Down Philosophies.

Process Equipment Modeling by using ProMax software and generating Heat and Material Balance. Page 4

Review and prepared checklist report of previous process detailed design deliverables such as PFD's and PID's drawings, safety and control valves, piping class/spec, pipe size checks, fittings information, sample points and process & instrument datasheetsand update the recommended corrective action as per International Standard and accordance with the client process engineering guidelines.

Perform process calculation for Crude Oil Storage tanks Venting/Breathing system requirement as per API2000 Code.

Sizing of Pressure vacuum relief valves, Pressure Safety and Control Valves, Selection and preparation of data sheets as per API521 Code.

Preparation checklists and marking up the P&ID's.Participate in ZAZOP Studies. The following are the Projects where I involved as Process Design Engineer/Technical Project Engineer;

Engineering Service and Procurement Support with OMV E&P for the up-gradation of their Oil & Gas facilities in Yemen.

1. Basic and Detailed Engineering Service of Extended Well Test Facility Phase #1 and Fresh Water Injection System of Kharwah Field Habban-23 for OMV, Yemen. Project Scope includes Design, Procurement, Erection and Commissioning of Extended Well Test Facility as a part of Kharwah Field Habban-23 up-gradation. I involved in the Project as Process / Project Engineer and was responsible to check the suitability of the existing process equipment, production piping/pipeline. Generate As-Built P&ID for the entire facility. Perform detail engineering for the upgrade of the facility. Carryout engineering study for installation of new fresh water injection system to the facility in order to treat the salinity of oil. 2. Basic and Detailed engineering design of the up gradation of Crude Offloading Facility at Safer for OMV, Yemen. The scope was to review and upgrade of the existing offloading and exporting facilities and design a new facility to offloaded and exported transfer 30000 BPD of crude oil, and optimize of drain system. I have involved in the Project as Process / Project Engineer and was responsible for Basic Process Engineering activities and Coordinating in Procurement activities. 3. Engineering Services and Procurement Support of Mobile Test 3 # Phase Separator Oil, Gas and Liquid for OMV, Yemen. This was an Engineering and Procurement contract. The scope was mainly includes Design, Procurement and Erection of Pre-Commissioning & Commissioning of Mobile Test 3# Phase Separator. I have involved in the Project as Junior Process / Project Engineer and was responsible for modeling process simulation with typical inlet feed using ProMax software. Run the simulation cases at the specified operating pressures to establish the separator’s capacity, and supporting Senior Engineer in Coordinating Procurement activities.

4. Basic and Detailed Engineering Design Review of a 16" Oil Export Pipeline for OMV,Block S2 Field, Yemen.The project consists of a Export Pump station with metering and launcher at OMV Central Processing Facility (CPF), a 16" diameter, 120 km long, Oil export Pipeline between the OMV CPF and the Safer CPU, a Receiving Facilitiesat the existing Safer Central Processing Unit (CPU). The scope incudes a quantitative Risk Assessment and Carry out a HAZID review of the proposal development, Independent Review of Export Pipeline Detail Design, Development, and Review of Requisitions, Specifications, Data Sheets and Material Reconciliation.

Conceptual, Engineering and Procurement Support Services of the new and up-gradation of the Oil & Gas facilities with TOTAL E&P, (TEPY), Yemen.

Preliminary and Detailed Engineering (Phase # 1& 2) for the installation of Water Injection Facility. The scope of work includes the basic and Detail Engineering of Main Water Injection Pumps, Variable Speed Drivers to run the main water injection pumps, Water Filtration Unit, Booster Pumps, Diesel Generators, and all necessary Safety and Instrumentation along Water Injection Management System.

Basic and Detailed Engineering Design and Procurement support for the new diesel loading/unloading facility. The project consists of a Loading/Unloading Diesel Facilities, Truck diesel Page 5

unloading transfer system to the existing fuel oil tank, Diesel Loading Arms system, Fire Fighting and Fire & Gas Detection system, Open Drain system, Pipe rack to CPU facilities, and all necessary Safety and Control valves and Instrumentation along Loading/Unloading Management System. Project Scope includes Design, Procurement, Erection and Commissioning of the entire facility and recommend the safe location of the facility, the engineering/detail design, fabrication, Preparation for shipment and documentation of engineering package shall be in accordance with General Specification of the TEPY Company. Reported the assessment of all procured equipment, instruments and material in order to confirm suitability for the project and all the operation parameters meet the requirements.

Basic and Detailed Engineering Design and Procurement support for Kharir utility water system. The project consists ofa wellhead facility, Flow lines from Mukalla water wells to Main Manifold, Trunk line form Main Manifold to CCU, Water Utility Manifolds at CPU, BPU & CCU, Filling Lines to Firefighting Water Storage Tanksand all necessary Safety and Control valves and Instrumentation along Utility Water Management System. The project scope includes design, Procurement, Erection and Commissioning of the entire facility as per the TOTAL Standards and requirements. Advice the Company of the quality and quantitiesof each required for the packaged unit and highlight the utilities not available.

FEED and Detailed Design for a Gas Blanketing System for the crude oil, produced water, diesel and slop storage tanks at the Sharyoof CPF (S-CPF), Dove E&P, Yemen. The Scope includes the design of complete tank blanketing system for the Shayroof Tank Farm in order to protect the storage tanks from high corrosion rates. The tanks are pressure relieved to the flare header, and breath via a PVRV from atmosphere. a gas blanket system is to be installed on all storage tanks. 5) Organization : TG Engineering Inc.

Location : Sana’a, Branch office, Yemen.

Position : Process Engineer/Safety Engineer "Trainee" Working Period : Feb, 2011 – Nov 2011

Type of Contract : Part Time "Hourly Rate"

Responsibilities;

Hydraulic Study and Calculation for Gathering Oil & gas flow lines.

Preparation of Process Block Diagrams, UFD’s and P&ID’s drawings, Line List, Fluid List, Utility Scheduleunder the supervision of Senior Engineer.

Procurement support by Technical Bid Evaluation and Vendor data review.

Assist / Development of Process Design Basis Document and Process Description.

Assist / prepared equipment sizing such as test separator, safety and control valves sizing, selection and preparation of datasheets.

Supporting Senior Engineer in performing various process calculations such as firewater hydraulic analysis, firewater and foam demand calculation, piping distribution network pressure drops calculation in various options, deluge system calculation.

Review the existing firefight system and prepare Gap Analysis Report & Discrepancy Table.Sizing and selection of pressure safety and control valves, firewater and jockey Pumps. Performed various equipment specifications such as Deluge, Hydrant Monitor, Subsurface Injection Foam, Water Curtain Nozzle, Foam Branch Pipe, Mobile Foam Unit, Water Foam Monitor and Foam Distribution Package.

Instrument / Technical datasheets preparation for fire flame detectors and fire heat detector, Smoke detector and hydrocarbon gas detector.

CoordinatingProvide Process input required during the Detailed Design, Construction, Commissioning and Start-up phases of the Projects and supporting Senior Engineer in Preparation of weekly reports. The following are the Kay Projects Undertaken:

Basic and Detail Engineering and Procurement Supportof Field Oil Gathering System for OMV, Yemen. The scope includes the Basic and Detail Engineering of field oil gathering network, Well Head Page 6

Facility, Flow Line connection to the Well Heads and Remote Manifold Stations (RMS), Flow Line and Trunk Lines connections to the OMVY Central Processing facility(CPF) and RMS, Well test manifolds and test Separators,Piping and pipeline sizing using ProMax Simulation in accordance with API 14E Standard.

Basic and Detailed Engineering Design and Procurement Support ofCentral Processing Unit (CPU) Fire Fighting Project for TOTAL (TEPY), Yemen. The scope was to review and upgrade of the existing Fire Fighting and Fire & Gas Detection system at CPU, identify the discrepancies between existing firefighting facilitiesand TOTAL General Specifications, and propose the technical solution to upgrade Kharir firefighting means in compliance with TOTAL General Specification. Review F&G system and advise if the number of Fire and Gas detector are enough or more than required. Prior to the detailed engineering TEPY advised to have feasibility study of the various options for the piping material, that is carbon steel above ground or GRP below ground.

Educational Background

Bachelor of Engineering – Five Years in Chemical Process Engineering, University of Hadramout of Science & Technology, 2012 – Yemen. (Major: Condensate Recovery Processing Unit) Professional Program Attended during Graduation Period Operational and Maintenance Training – Four Months on Engineering and Operational Techniques which included Oil Exploration and Production Technology, Wellhead Operation, Well Testing, Early Production Facility, Water & Gas Injection Facility with OMV Exploration and Production Company (01//07/2009–30/10/2009) – Yemen. Operational Training – Two Months for well testing equipment’s, Chock Manifold, HP and LP Separator, Sand Filter, Loading/Unloading Facility, Firefighting Systems and Terminal Loading Facility, Chemical Injection, Heat Exchanger and Water Injection Facility with Callvally Exploration and Production Company (01/02/2010 – 30/03/2010) – Yemen. Process Design using Computer in Oil & Gas Simulations Software with ProMax (9/2012 – 10/2012) –American University of Sharjah, United Arab Emirates.

List of References

1- Mr. Brent Dawydiuk

Company Attended : YemCan Engineering and Construction Company Position : General Manager

Contact Phone : Telephone Canada: +780-***-****

: Telephone Colombia: +57-310-***-****

: Telephone United Arab Emirates: +971-**-***-**** Place : Canada:

Email : adb18l@r.postjobfree.com

2- Mr. Pieter Bornemann

Company Attended : YemCan Engineering and Construction Company Position : Sr. Consultant; Engineering and Project Management Contact Phone : Tel Bus: +31 (0-70-220****

Tel Mob: +31 (0)6 5578404

Place : Holland

Email : adb18l@r.postjobfree.com,

Website : www.bornemannconsultancy.com

3- Mr. MonerAlropassi

Company Attended : OMV Exploration & Production Company. Position : Production Manager

Contact Phone : +967*********