HANDLING & LIFTING SUPERINTENDENT
Abdul Rahman Rasul @ Sella Durai Suppiah
Block 187 Boon Lay Ave
Address # ** – 64
SINGAPORE 640187
Contact No. : +62-815******** / +62-812-****-**** / +62-812-****-****
Email : actigz@r.postjobfree.com.
actigz@r.postjobfree.com
PERSONAL DETAILS
NRIC No. : S1470730A
Date of birth : 18/5/ 1961 age 54
Nationality : Singapore citizen
Passport : Singapore Passport
Expiry : December 5, 2017
Race : Indian
Religion : Indian Muslim
Driving License : Class 3 & Indonesia class 2 driving licence
National Service : Republic of Singapore Navy
Language spoken : English, Malay, Bahasa Indonesia
: Tamil, Fair Hokkien & fair Arabic
COMPUTER : literate
Skill & Knowledge
CERTIFICATES
2001 Building Construction Safety Supervisor Course- (Minitry of Manpower Singapore)
2001 Oct Rigger Course (Skill Improvement) Singapore
2001 Oct Signalman Course (Skill Improvement) Singapore
2001 Nov Singapore Contractors Association - SC2
Building Construction Safety supervisor - (Tunneling) Course
2001 Dec Lifting Supervisor Safety Course (Minitry of Manpower Singapore)
2002 Jan Standard first Aid /Singapore Red Cross
2004 Oct Confined Space Rescue Course
Singapore Civil Defense Force
2010 Jan Singapore Polytechnic
Apply Workplace Safety and Health Practices Course
MAR 2010-COMPLETED
2/01/ 2010 to 21/04/ 2010
Certificate in Workplace Safety & Health (WSH) Course 30 session-COMPLETED
SINGAPORE POLYTECHNIC
CERTIFICATE OF ATTENDANCE
PERSONNEL & ORGANIZATION DEVELOPMENT (POD)
CONDUCTED 14/4/2010 TO 21/04/2010
“ESS COMMUNICATION AND RELATIONSHIP MANAGEMENT OPERATION” PROGRAMME
SNEF- TRAINING INSTITUTE
(Singapore National Employers Federation)
CERTIFICATE OF ATTENDANCE
ESS – WORKPLACE SAFETY & HEALTH (OPERATION)
CONDUCTED 09/04/2010 TO 12/04/2010.
INDUSTRIALINDO KONSULTRAIN SERVICES
TANJUNG BALAI / KARIMUN.
FIRST AID AND CPR COURSE – LEVEL 2-valid
Advance
Saipem Safety Traning (internal)
1:SAIPEM- SAFETY FOR SUPERVISOR
2:SAFETY DEFENSIVE DRIVING
3: LiHS TRAINING-LEADERSHIP in SAFETY & HEALTH
4: PERMIT TO WORK - Authorized signing permit
5: HSE ROLE & RESPONSIBITY/OPERATION
Education Background
1968/1973 Yio Chu Kang Primary School PSLE
1974 /1978 Secondary 4-St Gabriel Secondary Sch
2010 WorkPlace Literacy / Numeracy.
Advanced literacy & numeracy
level 5 & level 6
SUBJECTED TO QUALIFIED FOR SINGAPORE POLYTECHNIC- WSH SAFETY COURSE
2006-2008 – RECOMMENDED BY SAFETY MANAGER FROM FOSTER WHEELER-
check profile-Linked actigz@r.postjobfree.com
CAREER OBJECTIVES.
A Construction & Engineering in the field of oil & gas and marine sectors,having enough experiences more then 20 years since 1986 Till date )
Experiences at onshore and offshore in multi purposes and various type of jobscope actitivies in rigging and lifting,transportation,marine base logistics and safety management with main companies like Exxonmobil, Foster Wheeler,Saipem Agip,Mcconald Dowell,obayashi(tunnel boring machine),Dubai Metro Rail,Jeddah Islamic Port-Mina Port-NAMMA, Aramco,Iraq,Gorgon brown island
Being working with multi national organization and achieve company Targets : Zero LTI and implementation in safe working operation and safe lifting operation,within all departments as per company requirements and compant standard and safety policy.
I covered a lot of areas in the field of Rigging,Heavy Lifting,Skidding-(loadout of modules nd jackets and offshore working platform,heavy and huge transportation, Scaffolding work and inspection,daily routine for inspection and updating the scaffold tag on weekly basis,
all rigging studies and heavy lift,method of statement, with the engineering team and lifting plan and the type of cranes to be used for the jobscope and for yard facilities ..
Including maintenances of heavy equipments,cranes,prime mover,hyster 3 ton to 44 ton …etc,,maintanences,inspection,loadtest of all equipments and machinerires .
As a yard superintendent for the entire yard of 144 hectres yard developments of yard construction too
Including barges,motor vessel.drilling rigs,working rigs,pipe laying barges,
Prepare mooring and riggers for the alongside of vessels,after clearance,lifting and transportation and logistic,including working with all departments in construction of the yard and enguineering work and the marine base for all 40 Rigs and Drilling vessel and barges materials stored and transport to supply vessel that’s comes to our jetty and yard.
Saipem Indonesia has constructed its own jetty approx. 800 meters long,for 4 to 5 vessels and barges and rigs can alongside..
Saipem yard Indonesia is 6 years old..completed various project – GORGON / ARAMCO/IRAQ TOPSIDE/ICTHYS/BINGDONG.(COMPLETED 3 LOADOUT gorgon,Aramco,iraq.)
Present project are from congo –KAMOBO AND Indonesia –JANGKRIK AND ICTHYS PROJECT
(Start from the current one)
Company : SAIPEM (ENI) FABRICATION & CONSTRUCTION YARD - OIL & GAS
Period : 05/05/2010 (contract end 31/12/2015)
Position : HANDLING & LIFTING SUPERINTENDENT
Job Description : Karimun, Tantung balai-INDONESIA
As a HANDLING & LIFTING SUPERINTENDENT Charge of all safe work operation of 31 operational cranes on site,( 1000 ton tower crane –Garuda Sky / 02 X Super Lift 400 ton Crawler Crane and 2 X 200 ton Liebherr Crane Crane / 07 Grove Cranes -60 ton / 21 small cranes 25 ton to 45 ton,..
6 Manitou Forklift / 06 Hyster forkilift- 3/5 ton & 6 Crawler Cranes-250 ton to 280 ton (Kobelco /IHI)
1000 ton TOWER CRANE – Main Boom Counter weight and counter weight boom- fabricated by saipem.
4 X Hyster 44 ton forklift / React Stacker- 44 ton, 03-Prime Movers - Trailer / 03 Truck Crane & 8 hyster and 4 X tractor 1004 attached with trailer.and many more..heavy equipments.
SPECIALIZED IN JETTY MOVEMENTS & LIFTING AND TRANSPORTATION OF VARIOUS KIND OF PRODUCTS AND MATERIALS AND CONTAINERS INCLUDING FROZEN CONTAINERS – FOOD. HEAVY LIFT & LOADOUT ACTITIVES & PRODUCTION SUPPORT work in saipem & others areas.
Almost 5 years working full time at site as a handling & lifting superintendent all the activities on site,all department jobscope and safe working operational at site.
LIFTING TEAM … I have 2 lifting Supervisor - 11 foremen for erection and lifting and heavylift …
and 9 foremen for scaffolding work- covering fabrication and workshops –
SCAFFOLDING TEAM …in each team consist of 6 scaffolders- making as 1 team…we have about18 teams….steel construction of warehouse and workshop
Approx. 1.5million ton of steel structure and height of 43 meter erection of hall assembly workshop.
approx 27 huge workshop including scaffolding work
Gain a lot of experiences in heavy liftand erection of heavy equipments and erection and installation..e. On rotation do the heavy lift with few riggers and settle the job on barges. .Handling 43 equipment’s of various job scope, barge loading & unloading, containers un-stuffing loading of various kind of pipes and king piles, spun piles etc.
Installation of Overhead Crane approx. 10 to 40 ton each set / Assemble and Steel construction & erection & fabrications and lifting of land drilling machine and piling machine,crane and installation of vibro machine for king pile driving for piling work-shifting and transportation to various site . Preparation for load out and load out actitives..safe lifting operation and safe load out operation.
THIS YARD IS FOR ALL SAIPEM DRILLING VESSEL AND PIPE LYING /PIPE JACKETUP BARGES AND JACKET LEGS AND PLATFORM, FABRICATION,HEAVY LIFT & HEAVY LOAD OUT –SAFE LIFTING OPERATION- onto floating barge or specialize transportation vessel, only for loadout .
Responsibities:
To coordinate and supervision all lifting actitivies and transportation,logistic operation,maintanences actitives,Inspection of lifting equipments and lifting gears,filed and control all documents for lifting gears and certification and inspection of areas to be erection for scaffold work,inspection of scaffold tag,any need of modification on scaffold erection and etc..
All lifting plans and method of statements and done together with the engineering department as per company procedures in the name of safe work procedures and safe working operation and safe lifting operation.
Daily routine,checking of equipments needed repair work,chasing the mechanical deparment to speed up..the maintenaces and repairs.,control of equipments and spare parts ..
ALL JOBSCOPE – DONE IN THE NAME OF REQUEST-USING SAIPEM REQUEST FORM.
VESSEL AND BARGES ARRIVE IN SAIPEM YARD – INSPECTION IS DONE WITH MANAGEMENT AND SAFETY WITH A CHECKLIST .PERMIT TO WORK SYSTEM. (Shipping operation)
ALL SAFE LIFTING OPERATION & LIFTING ACTITIVES IN THE YARD,PRODUCTION,ALL SAIPEM SUPPLY RIGS AND WORRKING RIGS AND VESSELS-COORDINATE TO VESSEL MOVEMENTS AND ARRIVAL AND SERVICES- ALL JOB TO BE DONE WITHIN TIME FRAME BY THE SHIP OWNER
The engineering department working very close with me regarding the lifting plan and lifting study…all lifting plan is also approve by me..all lifting gears records and given to the engineering dept for lifting plan..i will let them know which are the lifting gears to used.then the engineering dept DO the lifting paln for the lifting and scaffold department..
Scaffolding is also into lifting department..
Every jobs in saipem,we do the handling and lifting and instuffing and etc…
Project are gorgon/alwasit project – hasbah & arabiyah – Iraq project foster wheeler
Superintendents on 91/16 working rotation.
Able to lead a team of deverse ideas and creative ideas and outlook toward a pre planned goal.
Able to work under stringent deadlines and time frame.
Food & Accommodation & Transport provided – Hotel - food / car provided
Reason for Leaving : looking forward for better income and better benefits
CHINA CONSTRUCTION (South Pacific) DEVELPOMENT.HIGH RISE BUILDING.
2 TOWER-35 &36 FLOORS.
01 MAN Show-fulltime- WSH SAFETY SUPERVISOR.
Overall in-charge of all safety matters
LIFTING ACTITIVES & GOVERNMENT AGENCIES MOM/NEA/PUB/BCA.25/08/2009-
Scaffolding work and Full erection of metal scaffolding work (major job)
APPROX 70 NOS OF GONDOLA INSTALLED
SAFETY MANAGER Mr. Aurora Nitin- +65 90293704
Exxon Mobil – Client - Singapore & batam
Main Con - Foster wheeler Worley parsons - REFINERY
McCONNELL DOWELL
Singapore pallelled train project
April 2009(Oil & gas Project)
Position: LIFTING SUPERINTENDENT CUM WSH
SAFETY SUPERVISOR
Subcon: Kaefer – painting/blasting/ scaffolding
contractor - Willich insulation- Jakarta. Water- proofing & fire proofing contractor
In charge of all lifting activities in the site all cranes and lorry crane, about 15 lifting supervisors and 68 riggers...
Total work force is about 800 workers...All trades, metal scaffolding. Platform, cranes .spray painting dept., heavy vehicles, working at height and etc._
ALL LIFTING GEARS /CRANES CONTROL ( 700 ton crane to 25 ton mobile cranes- BY SAFETY DEPT.
*In charge of Safety Dept. in Batam Fabrication Yard and All Safety Matter...Selected to be station at Batam
*Plan with Safety Managers
All safety matters and lifting activities,and inspection of crane and lifting gears..
*Job analyst/risk assessment/ JSA –permit to work/safe work practices.
*SHE Training & hazard,commumnication,mass safet tool box,mass manhours celebration preparation &promotion actitives.
SAFETY TOOL BOX MEETING AND MASS TOOL BOX MEETING AND SAFETY ORIENTATION.
*CANTEEN/WORK AREAS/TOOL BOX MEETING/MASS SAFETY *TALKS/MASS HOUSEKEEPING/ FIRE *EMERGENCY DRILL/EXCUVATION DRILL/
*LIAISE WITH RELEVANT AUTHORITES ON REGULATORY COMPLIANCE
PRAPARATION FOR MASS SAFETY TOOL BOX TALKS
GOOD COMMAND AND GOOD IN LEADERSHIP FOR THE SITE IMPROVEMENT.
With creative ideas & good in setting up the entire site.
.
FOSTER WHEELER - REFINERY
LUCITE INETNATIONAL
CELANSES LIVE PLANT
SAKARA AVE.
SAFETY & LIFTING CO-ORDINATOR
IN CHARGE OF ALL SUB CONTRACTORS CRANES AND EQUIPMENTS.
14 LIFTING SUPERVISORS AND 60 RIGGERS : 10 CONTRACTORS
FROM DEC 17 the DEC...31 05 2008...project completed (6 mths)Transfer to exxonmobil project
Safety Manager .Mr. Jagg Singh. +65 8342 9919
Mr. John Harmatch: resident Const Manager
Foster wheeler- LIFTING ACTITIVES IN REFINERIES. AND SAFETY DEPT.
And also confine space entry n gas free for hot work in other activities
All mobile cranes and all crawler cranes from 45 ton to 700 ton.
All safety matters &Housekeeping in charge / fire extinguisher and etc.
DUBAI METRO TRAIN- TUNNELLING
DISMANTLINNG OF TUNNEL BORING MACHINE
DUBAI - JOINT KAMIGUMI - SINGAPORE
Paya Lebar- Circle-line LTA project
BACK FROM kamigumi-Dubai to kamigumi-spore
C823 DISMANTLE WORK ON TBM -2mths Preparation work for dismantling
Kawasaki 12 no’s twin motor EBP-..Diameter 6.0 m.
Approx.: cutter head 42 ton/chamber 99 ton/erector section 3rd: 110ton.Total: 255 ton
Tunnel Boring Machine... commence on 17 Oct 2007
And completion on 30/10/2007.
10/8/2007 TO 30/9/2007
INSTALLATION & DISMANTLE of TUNNEL BORING MACHINE 3mths project:10 METER DIAMETER CUTTER HEAD. 90 ton.
Rigging & Heavy Lifting operation/metal scaffold erection prior to erection work.
Installation of tunnel boring machine. Twin motor. .10 meter..12 no’s twin motor (HITACHI)
Installation of mammoth 400 ton crawler crane
Install and TEST LOAD n ready for inspection and services...
Installation of launching frame cradle. - welding work
Fabrication-work Assist obayashi job scope in launching
TBM frame work /metal scaffolding erection and dismatling and preapartation platform and other actitives. platform. supply of skill workers…dismatling of TBM about 611 ton machine… …Supervision of welders/cutters/riggers/lifting-supv//fitters/ mechanic/electrician
Person in charge ..Mr Yee..Director Singapore number +65 9655 3793 Dubai +97150 875
Organization : TAISEI CORPORATION – TUNNELLING
Project : MRT Circle Line/ LTA -C853
Position : EBP Tunnel Supervisor
Period : 2003 /2007July (BISHAN STATION)
POSTED TO C854 BUKIT BROWN STN..JAN 2007 to JULY 2007
Taisei corporation
LTA project-total 42 months
SLURRY/EPB/TUNNEL & CROSS PASSAGE SUPERVISOR
Job Description
• Assist site Engineer for actual planning on site
• Supervise to prepare the work site by construction of
Substation under by Meiden contractor
Muck pit under by chuan Lim contractor
Grouting plant
Gantry crane foundation for 12.5 ton and 20 ton
And other site facilities
TBM Installation
TBM Dismantle
Supervise by construction of launching shaft /foundation works by using Micro Piling.
In charge tunneling works from the start until completed the bored tunnel from Bishan to Lorong chung using Kawasaki Heavy Industries 6.61 m in diameter two twin TBM
Manage to compute and control TBM additives and grouting –
In charge to compute Muck volume/Pitching/Lips and steps of erector segment ring
In charge to monitor segment erection
In charge of SWC Bracket Installation
Attend weekly meeting for the weekly progress
Compile all daily TBM data and report
In charge of check, changing of cutter head disc, shell bite & cutter bites
Dismantling of TBM
Installation of TBM
Metal scaffolding erection and dismantling prior to Ring Bean Installation …
All work related to civil engineering…in construction of station and tunnel.
Concreting of large volume…1500 cu .meter to 2.800 cu. meter..inside tunnel, pumping procedures..non stopping concreting work for 3 to 4 day and night.. Including finishing and curing .completed concrete system..including of installation of concrete pipes approx 300 to 500 pipes….inside tunnel…approx 1.5 kilometer distance..major working task..heavy flow..approx 250 concrete trunk…completed this project from day 1 to handling over to LTA.
JM SHIPPING PTE LTD- Oversea
TECHICAL LIFTING SUPERINDENDENT
4 months assignment- 02 DEC / 2003 March Doha /Qatar -Middle East
INCHARGE OF ALL CRANES AND GANTRY CRANE IN THE PORT
SUPERVISION OF CRANE OPERATORS/ LIFTING SUPERVISOR / RIGGERS IN LIFTING ACTITIVES..
ALL CRANES INSPECTION N SERVICES ..IN CHARGE OF ALL CRANES..
INSTALLATION OF CRANES AND MODULES N GANTRY CRANES
WEEKLY INSPECTION AND MONTHLY INSPECTION
CRANE MOVEMENTS /CRANE WEEKLY SERVICES REPORT AND SO ON..
ALL SAFETY PROCEDURES AND SETTING UP SAFETY DEPARTMENT AND SO ON_
IMPLEMENT SAFETY LAWS AND ORDERS
HELPING OUT TO RUN A SAFETY DEPARTMENT AND SO ON
OBAYASHI McConnel Dowell JV
Tunneling foreman / Lifting Supervisor - TUNNELLING
( Power Grip Cable Tunnel )
May 2002 /December 2002 Semcorp /Philips Hoffsman JV
Supervisor of All work force and heavy equipment in construction of
underground Tunneling.
TUNNEL WORKING FOREMAN
Job Description : Tunnel working foreman “hand on” experiences;
Manual Excavation, concreting, reinforcement, modification of steelwork, drainage, formwork, hacking, jack picking, grouting for stop water ( from surface to shaft bottom to tunnel ), from installation of TBM ( ROBBIN )
Setting up the TBM, inside the bottom shaft and initial drive and to the main drive.
Installation of segment and taking of pitching and steps and lips and muck skip volume and a lot of working activities in the underground tunneling work.
Mining, installing segment, secondary grouting, TBM lining after coupled running of tunnel./ Drilling of back tunnel and blasting of back tunnel face.
Maintenance work on TBM, cleaning both ports and screw conveyor and belt conveyor sand modification of TBM mucks discharging by belt conveyor..
Rails installation and modification.
Preparation for shaft ground blasting and tunnel blasting.
Drilling of 1.0 meter to 2.4 meters depth ( side wall, ground, tunnel, benches )
Charging of blasting /chemical and connect.
Storage of equipment and materials.
Knowledge on loco motive and other machinery in tunnel work.
Drilling machine, manitou forklift and all equipment materials into tunnel.
Lifting /tunnel boring machine /weight / Approximately 280tons.heavy lifting work by used of 02 crawler crane
Pump of water from tunnel, shaft tunnel boring machine compartment
Installation of packers, ventilation of duct line and wash high pressure jet
Disposal of mud and stone and soil ( Manual)
Installation rock bolt / drilling, testing, and installation of segment rings.
Co-ordination with all departments, mechanical, electrical piping and contractors.
Preparation from the top surface to bottom of the tunnel as a working foreman
Arranged of segment, rails, mud skip, grouting, power supply, lighting, food, etc.
1996 /1997 SOUTH SEA INSPECTION
Traveling often for inspection of oil tools -Oversea work
NDT INSPECTOR / OCTG SUPERVISOR
Job Description
Oil country tubular goods, all oilfield tools and pipes.
Non-destructive testing of oilfield tools and tubular. And all kind /various type of shackles/lifting blocks /chain blocks/
All kind and various sizes of pipelines for services and inspection.
Complete inspection procedures.
1995 /1996 FOSTER WHEELER - REFINERY
DUPONT PROJECT
Celanese plant-Project Supervisor
PROMET PTE LTD (PPL) Oil &Gas
* Supervision of work force in concreting and preparation work prior to casting .
Foundation rack for pipelines/reinforcement n carpenter/formwork work..all general services in the site,,
* Painting n Coating on pipe line/ preparation for repair work prior to coating * Hydro Test for leakage for pipelines
* Installation work assisting with various department.
* All lifting operation in the site
* In charge of all painting n general services
* all job scope is the same as mobil refinery
1993 /1995 LEIGHTON PROMET - REFINERY
MOBIL PROJECT-Oil &Gas
SUPERVISOR Cum Assistant Safety officer
Mr:ALAN FIELD : white industries-Spore
Job Description
Civil work and underground piping.
Manual excavation work on shut down and supervision of workers in casting of pump foundation and construction on sub-station and pump pit and workshops and etc.
Shut down activities such as manual excavation, foundation work, reinforcement, casting, formwork etc. Supervision of all contracting work in the refineries\ and on job site, Follow up with the clients specification and drawing and safety procedures. All permit to work system. Tool box meeting etc.
INCLUDING --- Installation & Erection & Rigging of heavy equipments by use of cranes and lorry cranes
Installation of coating and water proofing and fire proofing
Work closely with the workers,
Training and instruct them to work in a safe working condition.
Work includes,concreting work/ formwork/lifting operation /rigging operation/re-bar work./trenches/erection of structural /flare/erection flange/vessels..various heavy equipments lifting operation..
Very Useful Supervisor and helpful and creative with many ideas in safe work practices / assist all safety matters
Filing reports and daily reports
Lifting gears /crane movements/lorry crane movement.
1991 /1992 OFFSHORE PIPELINE INTERNATIONAL LIMITED
1 year contract BRUNEI SHELL PETROLUEM.
( ex-BROWN & ROOTS )Onboard DLB264
Time keeper/Barge Clerk
Job description
In charge of deploy of offshore crew, arrangement of helicopters, air flights, sending and picking up from airport (Brunei).
Sending and picking up from Anduki (Helicopters Base)
Pre booking of chopper for offshore workers. Safety training booking/hotels/transportation/medical check-up/food/coordinate with offshore/onshore personnel, workers time sheet/salary calculation/OT
Telex machine/computer-daily offshore working activities recorded in computers/telex machines to all oversea officers, communicate with chopper /before/after landing.
All administrative work onboard-safety training/rescue party/excavation drill/arranging of barge..movement, safety assistant to chopper landing, etc.
JULY 1990 /1991 NEW ZEALAND / AUCKLAND / AUSTRALIA-Perth--1 year contract /Oversea
Supervisor : Toys warehouse / Point Chaviler
Job Description
In charge of packing of expensive sun-glasses and postal stamps / delivers arrangements of supplies to collect/ proper packing for glasses for clients and many more general duties in the warehouse and sales department.
IN-CHARGE OF SAFETY MATTERS IN THE TOY WAREHOUSE
1986 /1990 Sembawang Shipyard (PAN MARINE ) JV
SAUDI ARABIA (JEDDAH SHIP REPAIR YARD)
Jeddah Islamic Port
2 years contract - Namma-Pan Marine Pte. Ltd (Singapore)
Extended contract to 1988 to 1991 (Neil Campbell)
RIGGER (1986 – 1988
SAFETY SUPER VISOR – 1988 – 1989
CHIEF SAFETY OFFICER 1989 – 1990 JUNE
Job Description
Overall in charge for safety department / 700 Multi-National Workforce going to outstations at sea & live platforms.
Check Onboard vessel for Gas Free, check various tanks/pump room/double bottom tanks/engine room etc.
. ISSUE Gas free Certificate/bring the vessels along/docking or berthing in shipyard premises. Gas Free Certificate issued to ship and marine department of Jeddah Islamic Port.
Supervision of safety men onboard vessel. Issuing of hot work certificate/safety inspection/checking of work onboard, all safety working procedures on board, check and inspect all safety hazards in all departments, safety training/safety meeting/toolbox, meeting safety reports, site safety walk etc.Overall in charge for safety department / 700 Multi-National Workforce . 45 DAYS FOR JOB TRAINING
Sembawang Shipyard ==_ Safety Supervisor
Roles and Responsibilities
Inspection of workers and train workers in safety working environment in shipyard painting, blasting, docking, undocking, cleaning of ships, tanks chain locker, anchor & chain calibration, all general duties in ship repair business. Preparation for various departments before commence of work /fire fighting and rescue drills and excavation drills.
Inspect all ship in Sembawang Shipyard
Precautions / Gas Free / Safety meeting / Toolbox meeting-checking of fire hazards, safety training-inspection all areas on board vessels, checking/testing before issuing gas free certificate, for hot/cold work, checking with contractor of works ongoing board, welding, cutting, pump room/tank/void tank/decks/engine room etc..
trained in lifting activities.
1985 / 1984 WHTE INDUSTRIES CONSTRUCTION REPAIR YARD ASSISTANT FOREMAN
(Mr. Alan field) _ AUSTRALIA
Supervisor of workers in precast manufacturing work, molding/remolding of panel layout concrete, rebar, reinforcement, supervision of workers on precast panel lifting activities in the yard. Foundation work and concrete links, excavation/pumping and repair all defeated parts and arrangement of trailers to site. Deliveries of concrete panel. Etc.
Rigging / lifting activities in construction industries. Supervisor of construction workers in painting, washing minor repair work on defected area. Plastering rock stone /re-spraying and painting of building, other construction related works in concreting formwork/rebar reinforcement. Work heavy concreting work and earthen treatment work and soil improvement work.
NATIONAL SERVICE – GOVERNMENT MILITARY - ARMY
SEAMAN GUNNER
REPUBLIC OF SINGAPORE NAVY
1979 /1984-Regular 5 years sign on contact
Remuneration
Last drawn Salary : USD 5.500.00 PLUS USD 100.00 plus ferry allowances
( plus yearly bonuses-Car,food,housing)
DEAR SIR;
I HAVE ENOUGH WORKING EXPERIENCE IN MY PROFESSION AS A WORKING
HANDLING & LIFTING SUPERINTENDENT. HANDLING THE BARGES AND WORK ON PRODUCTION OF JACKET/JACKET DECK, WORKING PLATFORM & PHOOTOON AND VARIUOS DECKS ETC..INCLUDING PIPE RACKS ERECTION & INSTALLATION,LIFTING AND ERECTION OF VARIOUS SPOOL PILE ON TOPSIDE INCLUDING AND TRANSFERING OF VARIOUS MODULE AND FABRICATED SPOOL AND BUILDING AND DECKS ..ETC…
INCLUDING HEAVY LIFT AND LOAD OUT & TRANSPORTATION OF VARIOUS MATERIALS INCLUDING HAMMERS,STRINGERS,AND PRODUCTION,FABRICATED MATERIALS AND PROJECTS ITEMS..LIKE SCAFFOLD ERECTION AT PRODUCTION AREA –WORKSHOPS AND VESSELS AND ERECTION AREAS
Transportation of various modules and materials including marine base materials and projects materials and equipment’s –TRANSPORTATION OF ALL KIND OF MATERIALS,KING PILES SPOOL PILES,FABRICATED MATERIALS, LOADOUT,FLIPOVER - using 2 t0 4 t0 6 cranes
MOST OF THE EQUIPMENTS & MATERIALS ARE MORE THEN 2 TONS TO 600 TON EACH.
Intallation and erection of module decks and spool piles and transfer spool pile s to painting cabin..
etc –load out and load in-loading & unloading of various fabricated materials to various department-yard is about 144 hectres
04 May 2010-SAIPEM – TO DATE (31/12/2016-contract end) ALMOST 6 YEARS
CURRENTLY I AM WORKING FOR SAIPEM – ENI INDONESIA
AS A HANDLING & LIFTING SUPERINTENDENT… SAIPEM - ENI INDONESIA-KARIMUN.
AS A LIFTING SUPERINTENDENT & I AM FULL TIME ON SITE BECAUSE OF HEAVY LIFTING AND SERVICING VARIOUS DEPARTMENT AND BARGES AND OTHERS DRILLING BARGE AND PIPE LAYING BARGES,PRODUCTION OF PLATFORM AND JACKETS, erection of any machineries and workshop and fabricated materials etc., The lifting & scaffold department workpower 385 riggers /scaffolders /operators.
(04 superintendent on rotation)
TUNNELLING – I STARTED WORKING AS A GENERAL WORKERS AND FEW YEARS OF EXPERIENCES I WAS PROMOTED TO TUNNEL WORK FOREMEN .AFTER FEW TUNNELLING PROJECT I WAS EMPLOYED AS A TUNNELL SUPERVISOR AND LATER TO CROSS PASSAGE SUPERVISOR- TUNNELLING – TROUBLE SHOOTING IS THE BEST WAY TO DRIVE,WITHOUT ANY PROBLEM …INSTALLATION AND DISMANTLE OF TBM AND TOOL CHANCES … ALL LIFTING ACTITIVES INSIDE AND OUTSIDE SHAFT ..
I AM STATION AT INDONESIA/ KARIMUN TANJUNG BALAI –SAIPEM-ENI KARIMUN FABRICATION YARD.
HAVING ENOUGH EXPERIENCES AND SKILL AND COMPLY WITH ALL SAFETY PROCEDURES AND SAFE WORKING CONDITION AND SAFE WORK LIFTING OPERATION.
I HAVE EXCELLENT WRITTEN AND SPOKEN COMMUNICATION SKILLS IN ENGLISH, TAMIL, MALAY/BAHASA INDONESIA/ AND FAIR IN ARABIC AND FAIR IN HOKKIEN..
I AM VERY MUCH CONFIDENT AND, FRIENDLY PERSON, ABLE TO INTERACT COMFORTABLY WITH ALL LEVEL OF PEOPLE AND TO FUNCTION EFFECTIVIELY IN STRESSFUL SITUATION AND FIRM IN DECISION.
I AM VERY MUCH INTERESTED AND KEEN IN JOINING YOUR ESTEEMED ORGANIZATION. THANK YOU VERY MUCH FOR YOUR KIND ANTICIPATED COOPERATION.
AWAIT FOR YOUR EARLIEST REPLY
YOURS FAITHFULLY.
SELLA