MOHD FIKRI OSMAN
**/**** ** ******* *******, Balok
Kuantan,Pahang,
Malaysia
Experience Level: Almost 8 Years’ experience in Oil and Gas Retrofits construction, testing, pre-commissioning and commissioning. Especially in line up prior to system Start-Up, line setup, preparation for testing activities. Knowledge about inspection and acceptance of materials and equipment such as piping and mechanical for the project involve. Name : Mohd Fikri Bin Osman
Address : 10/1126 Kg Chengal Lempong, Balok Kuantan,Pahang Mailing Address : Blok E2-4, Kuaters Perguruan Bercham, Hala Tasek Timur 26, 31400 Ipoh Perak
I/C No : 880***-**-****
Age : 28 Years
Date Of Birth : 03 May 1988
Place Of Birth : Hospital Tengku Ampuan Afzan
Nationality : Malaysian
Emile : acteuf@r.postjobfree.com
Contact no : +601********
Status : Married
Gender : Male
Religion : Islam
Language : Mother Language & English
Health : Excellent
Hobby : Badminton
License : B2 & D
Willing To Travel/Relocate : Yes
Possess own transport : Yes
CURRICULUM VITAE
EMERGENCY CALL
Name : Nur Elia binti Abdullah Suhaimi
Relationship : Wife
Address : Block E2-4,Kuaters Perguruan Bercham, Hala Tasek Timur 26, 31400 Ipoh,Perak
Phone Number : +601********
Having a stable and challenging career that used personal capability and creativity where I can enhance my skill and knowledge to work in a company with good working environment in order to improve the company with good and myself. Also willing face new challengers in fulfilling the company vision and expanding my carrier.
Personality:
Able to hard work independently or in team. Able to learn fast. Outgoing to pleasant. 1995 – 2000 : Sk Slim River ( Upsr)
2007 – 2005 : Smk Beserah (Pmr/Spm)
2007 – 2008 : Institute Technology Perwaja
-Instrumentation Industrial & Control Level 2
SHORT COURSE CERTIFICATION
2008 : University Malaysia Pahang (Cenfed)
- Safety And Health Officer Course
2009 : Institute Nuclear Malaysia (Mint)
- Radiography Testing Level 1 And 2
- Radiography Interpretation Level 2
CAREER OBJECTIVE
EDUCATION
2012 : Institut Kemahiran Mara Jasin
- Magnetic Partical Inspection (Cswip/Twi)
2013 : Niosh Kemaman
- Ogsp Level 2
2014 : Institut Kemahiran Mara Jasin
- Dye Penetrant Testing (Cswip/Twi)
2015 : ADTEC Kemaman
-Visual Welding Inspection CSWIP 3.0
Competency
Certificate Of Loss Prevention System (Lps), Conducted By Exxonmobil Exploration & Production Malaysia Incorporated.
Basic Offshore Safety Emergency Training (Boset).
Regular Crew For Exxon Mobil Platform (Non Short Service Workers – Ssw)
Green Card Training (Construction Industry Development Board- CIDB NO 042407).
Offshore Safety Passport Petronas Carigali (valid 28/01/2017) Hydratight Cid Card No : 2015/0056/SG (valid 11 June 2016 – Grade 2)
Hand Torque Flange
Hydraulic Torque Flange
Bolt Tensioning
Informate Advantage
Qa/Qc Joint Inspection & Tagging
Process Engineering Drawing
Process And Instrument Diagram
Technical Foundations
May 2015 until January 2016
Company : Hydratight Pte Ltd
83 Joo Koon Circle, #01-03 Singapore 629109
Position : Joint Integrity Inspector (Flange Management) Project : Chevron / Bechtel - Wheatstone ISBL LNG Project (Lumut) Work Experience
Company Background:
Hydratight is the only company in the world accreted to ASME PCC-1-2013 standards for bolted flange joint assembly.
Scope of work
Inspection of flange related spool fabrication, erection, flange assembly and tightening in accordance with project procedures and specifications.
Keep statistic of flange defect or flange assurance for non-compliance cases
Check and provide torque/tensioning value for all flanges including non-standard flanges.
Line walk down and update flange punch list broken joint, loose fit-up and complete joint.
Tagging joint and work flow control direction.
Progress reporting and closed ITR ( inspection test report) and NCR by system
Inspection after machining on site
Inspection of Joint, fault finding and identification of remedial work.
Inspection as recommended by the specification with ASME PCC1 – Guidelines for Pressure Boundary Bolted Flange Joint Assembly
Inspection as recommended by the specification with ASME B16.5, ASME B16.47, ASME B16.2, ASME B16.21, ASME B31.3, ASME PCC2, etc.
Inspection as recommended by the specification with piping material such as ASTM A105, A182,A193, A194,A320, etc.
Mei 2013 – April 2015
Company : Shapadu Energy And Engineering Sdn Bhd (SEEN) Department : System Completion
06th Floor, Campbell Complex, JalanTunku Abdul Rahman Kuala Lumpur, Malaysia
Position : Mechanical & Piping Technician
Project : Tapis Alpha Eor Brownfield Exxonmobil Malaysia Inc Company Background
Shapadu Energy and Engineering Malaysia Sdn Bhd is the Main Contractor for ExxonMobil Exploration and Production Malaysia Incorporated (EMEPMI) involved in major engineering, commissioning and construction project onshore and offshore Platform.
The Project scope selected is based on EMEPMI existing platform architectural and layout configuration. Thus, it will optimize the overall development cost with improved project schedule.
SEEN has undertaken Telok Gas Development Project, Guntong - E host tie- in modification crude transfer, HP flare and drainage facilities between satellite platforms, Tapis Alpha Enhance Oil Recovery TEOR project to improve gas lift and WAG for existing and new well heads and fabrication of new facilities, upgrading. Tapis B,C, and P existing facilities. Scope Of Work
Develop Turnover Commissioning Package (TCP) and Mechanical Completion Package
(MCP) for Tapis A project, Tapis C & Guntong E Telok project.
To check all installation are based on P&ID and ISO drawing for piping, electrical and instrumentation drawings, If any adjustment or modification will be recorded in P&ID or ISO.
(Compile red Line mark-up).
Doing Line walk every day to close any check sheet.
Working with Inspection test record ‘A’ check sheet for construction & ‘B’ check sheet for commissioning stage
Prepare the test limit or system limit for any testing conduct.
Working with Pegasus to ensure it is tally with construction work pack and job card progress planning.
To ensure that the construction test is completely finish before handing over the system to the system completion
Responsible to the system completion lead for all communication meeting between client and construction.
Responsible to coordinate all Mechanical Completion stage and interact with QA/QC for commissioning stage.
Working with static & dynamic commissioning
To arrange MC walk-down with construction team before proceed to System completion.
To rectified all construction punch list must be closed before proceed to testing.
To develop new punch list (if any) when doing the walk-down.
Ensure all required certificate are prepared, signed by appropriate supervisors/manager and distributed as stipulated in the project coordination procedure.
Involve in check sheet finalization meeting with client.
Involve with commissioning meeting with client. Prepare all the required documentation for handing over procedure as per client requirement, (MC certificate, static Commissioning certificate, Ready for start-up certificate, Turn over certificate, vendor data, compiling check sheet, punch list etc.).
Participate with client and construction team for Tapis-A Platform Pre-start-up Safety Review
(PSSR)
Controlling valid/expired Recorder Chart Single Pen and Double Pen for Hydro test and Leak Test.
Monitoring expired and order equipment with Material Issued Request (MIR) or Construction Equipment Request (CER) with Material Coordinator (matco).
Preparation Hydro Test Activity medium testing with fresh water according Exxonmobil specification
Preparation Leak Test Activity medium testing with nitrogen (n2) or fresh water according ExxonMobil specification
Ensure flange rating and pressure using confirmation with Test Package Hydro-test/ Leak Test from Qc or engineer
Knowledge Activity Flushing After Hydro-test and Leak Test using wire mesh according specification for Finding any contamination and prepare any report finding with QC
Ensure Test Package accept with QC before Testing
Apply permit pressurization Hydro-test or Leak test with permit runner
Ensure That No High Pressure Testing Occur in the work canter
Ensure Personal conducting the test stand behind a barrier during pressurization
Mark off the area as a dangerous site and ensure individuals associated with the testing activities are in the area
Notify station personal of area to be avoided due to potential risk during pressure testing
Checking Valve condition, position, flow same with Isometric Drawing and specification
Monitoring Bolting Activity with Sub Contractor and reporting activity with engineer according ExxonMobil Specification
Monitoring Preservation Activity ensure all track bolt nut with greaser, ensure valve wheel function and smooth to open and closed, controlling any part with painting for contamination from corrosion attacking.
Ensure little nitrogen save in piping/launcher/receiver/separator before start-up activity with according specification
Prepared Request Final Inspection (RFI) to Permitted acceptance with specification
Ensuring all documentation are updated, maintained and under control
Assist Commissioning Engineer to prepare mechanical completion documentation to be hand over.
Joints walk down activities for completion sub-system or system before hand over to operation Onshore
Assistant with engineer to be setup commissioning procedure for final document FD5 handover.
Collect any have document datasheet, vendor data, NCR, TQ, STQ from Construction Engineer, document controller, Qc for platform Guntong Teluk, Guntong Tapis. Bravo Pam and Charlie.
To be closed Check sheet by system.
To be killing punch list mechanical part.
Working with inspection test record (ITR) A check sheet construction test record, B check sheet (commissioning) perform required testing in prior to complete system, closed related check sheet base on EM Pegasus database along with managing discipline commissioning engineer in pursue for handover by sub-system.
December 2012 - Mac 2013
Company : Environmental Science Malaysia
Position : Technician (Freelancer)
Scope of Work
Technician Site For Monitoring Testing Ambient Air Quality, Groundwater, Sea Water, Characteristic Study, Environmental Impact Assessment (EIA), Site Noise And Wind Speed Monitoring.
Client Site :
Fpg Oleochemicals, Kemaman Bitumen Company, Fpso,Tioxide, Environ, Asia Baru,Polyplastics, Ecosystem Pengerang, Ahn Norlan United, Lynas, Azrb Resources, Petronas Petlin, Mtbe, Basf Petronas, Ranhill Worley, Tnb Remaco, Bp Chemical, Bredero Shaw. October - December 2012
Company : OilGon Solutions Sdn Bhd, Ampang, Selangor Position : Technician Operation
Project : Pre-com Pipeline 18’x 32km from Temana to Bcot (water waste treatment) Bintulu Crude Oil Terminal
February 2010 - February 2012
Company : Testex (M) Sdn. Bhd/ Intestmal Group Company Position : Multi Dicipline Inspector
Project : Petronas Penapisan Melaka (PSR 2 Revamp) Scope of Work
Technician Rt to x-ray pipe by new technology used by SAFERAD
Interpretation film after expose Rt.
Reported qc sub-con Pfce, Dialog, Foster wheeler and etc company
Radiography Testing No Register Aelb : 4470 (Lembaga Perlesenan Tenaga Atom Malaysia)
September Until December 2009
Company : Juraxis Sdn. Bhd, Kerteh, Terengganu
Position : Semi Skill E&I
Project : Cable installation in Petronas MTBE Kuantan, Pahang Jun until October 2009
Company : Wehaya Regelung Sdn. Bhd, Shah Alam, Selangor Position : Assistant Instrument Technician
Scope of Work
Learn how to use Instrumentation equipment, like hart communicator, instrument air.
Responsible for clearing post project punch items. Maintenance and repair of all electrical systems and equipment whilst complying with safety standards and practices.
Perform breakdown repairs whenever required and undertake steps to improve plant and filed
Installation tubing for transmitter, control valve and etc.
Involved with construction and installation of instrument.
Prepared and setup the control valve to calibrated.
Remove any tubing request by client and install back tubing as per hook-up drawing
Assist vendor to do calibration and troubleshooting
Overhaul displacer switch, control valve and any instrument.
Gland cable for termination power panel switch earthing box
Responsible for leak-test of impulse and air line witness by client, functional test and sequence test for motorize operate control valve, solenoid valve and shut off valve
To ensure all hook-up and installation instrument follow the approve drawing.
Prepared all drawing and document to submitted to client.
Witness Leak-test, Functional Test all instrument device by contractor
Arrange and liaise with client to do the inspection. January until April 2009
Company : Jurunature Sdn Bhd, Pasir Gudang
Position : Assistant blasting/painting
Project : B11K-A Topside (SHELL) – MMHE
Scope of Work
Helper painter to spray installation jacket, apply permit before perform to working. Painted used be passive firewall protection jacket platform.
Computer Skill : Win, Win Xp, Win Vista, Win7
Computer Literate : Microsoft Word, Excel, Power Point and Microsoft Outlook 1. Kevin Jures, Wheatstone Joint Integrity Project Manager, Bechtel Wheatstone LNG, ISbL Module Yard Kencana, Lumut, Perak, Malaysia.
2. Steven Teo, Field Service Engineer, Hydratight (Singapore) 3. Shahril bin Hassan, Project Manager Shapadu Energy and Engineering Sdn Bhd. 4. Yusran bin Yusoff, Site Project Manager Shapadu Energy and Engineering Sdn Bhd. 5. Mior Badli Shah bin Karuzaman Mechanical Completion Lead / Commissioning Engineer 6. Mohd Nizam bin Crin, Senior Advisor Commissioning, EMEPMI 7. Russel Spell, Consult EMEPMI.
Expected SalaryPer Day : 200usd (Worldwide)
: Negotiable (Malaysian Only)
Date For Employment : Available Any Time
DECLARATION
I declare that all information herein is true and correct to the best of my knowledge. I understand that my misrepresentation or omission of facts will be sufficient cause for cancellation of consideration for employment or dismissal from the company’s service if I have been employed, I also authorized any investigation of the information provided here in for purpose of verification. I would like to thank you for your kind attention to this curriculum vitae. Your Sincerely: Date:
COMPUTER KNOWLEDGE
REFERENCE
EXPECTED SALARY
MOHD FIKRI BIN OSMAN
10/1126 Kampung Chengal Lempong,
26100 Kuantan,
Pahang Darul Makmur.
Tel: +601********
Dear Sir/Madam,
I have great pleasure in submitting for the above mentioned post which is advertised in dated. Here with attached my resume providing details of my qualifications & experiences. I am truly interested in the career opportunity offered in your company believe that my leadership, decision making, initiative and my ability to learn quickly, I will be able to contribute positively towards your organization's success. I look forward to being the opportunity of a personal interview at your Convenience
Thank You,
(MOHD FIKRI BIN OSMAN)
Letter of Recommendation and Recognition
jjf