FORM TECH * – CURRICULUM VITAE - NATIONAL Col. K L Monga, Page 1 of 6

Construction Supervision of Uttarakhand State Roads Project 1. Present Position TEAM LEADER

2. Name of Firm: M/s Euroestudios S.L.-M/s Theme Engineering Services Pvt. Ltd. (JV). (Consultant) 3. Name of Expert: Col. Krishan Lal Monga

4. Date of Birth: 17th May 1946 Citizenship: Indian 5. Education: • Graduate B.E Civil Engineering

• MBA Material Management from Pune University 1985 6. Membership in Professional

Associations:

Member, Indian Roads Congress.

Member, Indian Society of Arbitrators

Member, Indian Building Congress

Associate Member, Aeronautical Society of India

7. Other Trainings: Two months CAD course for Design of Roads, Aug. to Sept., 2006 Six months training with snow Avalanche Study Establishment (SASE) for study of landslides in Jammu and Kashmir, 1992 (Hill Area)

One year Course in Quality Control / Quality Assurances, Pune, Nov. 1984 Three months training in laying of ready-made truck mounted tracks in deserts under operation command of the Western Army, 1982-83

8. Countries of Work

Experience:

India, UAE, Turkey, Yemen

9. Languages: Language Speaking Reading Writing

English Excellent Excellent Excellent

Hindi Excellent Excellent Excellent

10. Employment Record

From 1 May 2014 To Till date From 1989 T0 1992

Employer M/s Euroestudios S.L.-M/s Theme Engineering Services Pvt. Ltd. (JV). (Consultant)

Employer DRDO

Positions Held Team Leader Position Held Dy. Director of works From Nov 2010 To April,2014 From 1989 T0 1992

Employer URS Scott Wilson Pvt Ltd. (Consultant) Employer DRDO Positions Held Team Leader Position Held Dy. Director of works From Jan 2010 To Nov 2010 From 1968 To 1989

Employer SMEC International Pty (Consultant) Employer Corps of Engineers / MES Positions Held Team Leader Position Held

Superintending Engineer / Executive

Engineer / Asst Executive Engineer

From Aug 2008 To Jan 2010

Employer Artefact Project Ltd (Consultant)

Positions Held Team Leader

From Feb 2008 To Aug 2008

Employer Sheladia International USA, (Consultant)

Positions Held Team Leader

From April 2006 To Feb 2008

Employer ICT Ltd, (Consultant)

Positions Held Team Leader

From Nov 2003 To April 2006

Employer Roughton International jv with CED ltd (Consultant) Positions Held Resident Engineer

From Feb 1999 To Nov 2003

Employer Lea Associates South Asia (Consultant)

Positions Held Sr. Consultant (Highways) Team Leader, From Feb 1993 To Jan 1999

Employer Al-Rawaj Con.Services Dubai (Consultant)

FORM TECH 6 – CURRICULUM VITAE - NATIONAL Col. K L Monga, Page 2 of 6 Construction Supervision of Uttarakhand State Roads Project Positions Held Resident Engineer

11. Detailed Tasks

Assigned:

• Shall be overall

responsible for

the project Inter

alia including:

• Mobilisation

• Preparation of

Quality

Assurance Plan

• Review of data

and documents

• Reconnaissance

• Site Inspection

• Start-up Meeting

/Issue of

Commencement

Report

12. Work Undertaken that Best Illustrates Capability to Handle the Tasks Assigned Name of assignment Or Construction Supervision of civil works for Lalsot- Karsuli Section (85 Km.) Project Of NH 11B in the state of Rajasthan under Phase 1 NHIIP, Funded by World bank, on FIDIC Condition Contract Year May 2014 To Till Date

Location Rajasthan

Client MORT&H

Main Project Features Project Length: 85 Km. Including six Major/Minor Bridges/ROB/RUB Project Cost 243 Crores

Position Held Team Leader

Activities Performed Responsible for lead the team as Team Leader in Day To day Quality Control & Supervision of Road Project, Project Management, Contract Administration, checking the accuracy of all controlled surveys, Investigations, Construction Program, safety plans, Interpretation of provisions in the contract documents and technical specification was the prime responsibilities. Modification and issuing of detailed drawings to the contractor, preparation of variation statements, reviewing of monthly progress review meetings and co-ordination. Total Quality Control for entire project, Reviewing of Contractor’s QA & QC Plan, Quality Monitoring.

• Shall be overall

responsible for

the project Inter

alia including:

• Mobilisation

• Preparation of

Quality

Assurance Plan

• Review of data

and documents

• Reconnaissance

• Site Inspection

• Start-up Meeting

/Issue of

Commencement

Report

• Preparation of

Construction

Manual

• Setting out /

Cheek setting

out

• Review of

Contractor’s

Work Programm

• Review of

Contactor’s

Construction

Name of

assignment or

Project:

Construction Supervision of civil works for Bihar State Highways Project(South Bihar)-ICB Package-2 of 2008-9, Funded by ADB, FIDIC Condition Contract Year: Nov 2010 to April,2014

Location: Bihar

Client: BSRDC

Main Project

Features:

Project Length: 377km, Project Cost 839 Crore,

Position held: Team Leader

Activities performed: Responsible for lead the team as Team Leader in Day To day Quality Control & Supervision of Road Project, Project Management, Contract Administration, checking the accuracy of all controlled surveys, Investigations, Construction Program, safety plans, Interpretation of provisions in the contract documents and technical specification was the prime responsibilities. Modification and issuing of detailed drawings to the contractor, preparation of variation statements, reviewing of monthly progress review meetings and co-ordination. Total Quality Control for entire project, Reviewing of Contractor’s QA & QC Plan, Quality Monitoring.

Name of

assignment or

Project:

Construction supervision of 1st year roads of Orissa state road project, Funded by World bank, on FIDIC Condition Contract

Year: Jan 2010 to Nov 2010

Location: Orissa

Client: PWD ORISSA

Main Project

Features:

Project Length: 450Km, Project Cost: 710 Crore

Position held: Team Leader

FORM TECH 6 – CURRICULUM VITAE - NATIONAL Col. K L Monga, Page 3 of 6 Construction Supervision of Uttarakhand State Roads Project Mothodologies

• Review of

Contactor’s key

Superintendent

Personnel

• Evolve and

Established

Quality

Assurance

System

• Verification/Certi

fication of

Complete Works

• Supervision /

Verification of

Acceptance

tests

• Verification of

As-built

drawings

• Examination of

Measurements

• Progress

Monitoring

• Maintenance

works during

construction

period

• Assists in

arbitration

• Defect Works

• Documentation /

submission of

reports

• Guiding /

Supervising the

work of Key

Personnel &

Support

Documents

Activities performed: Responsible for lead the team as Team Leader in Day To day Quality Control & Supervision of Road Project, Project Management, Contract Administration, checking the accuracy of all controlled surveys, Investigations, Construction Program, safety plans, Interpretation of provisions in the contract documents and technical specification was the prime responsibilities. Modification and issuing of detailed drawings to the contractor, preparation of variation statements, reviewing of monthly progress review meetings and co-ordination. Total Quality Control for entire project, Reviewing of Contractor’s QA & QC Plan, Quality Monitoring

Name of

assignment or

Project:

Construction supervision and contract administration for Construction of 4-Lane Kota Bypass on NH-76 KM of 4 lane rigid pavement at Kota on East-West Corridor in the state of Rajasthan Package no CS (RJ-4), Funded by ADB, FIDIC Condition Contract

Year: Aug 2008 to Jan 2010

Location: Rajasthan

Client: NHAI

Main Project

Features

Project Length: 76Km, Project Cost: 386 Crore,

Position held: Team Leader

Activities performed: Responsible for lead the team as Team Leader in Day To day Quality Control & Supervision of Road Project, Project Management, Contract Administration, checking the accuracy of all controlled surveys, Investigations, Construction Program, safety plans, Interpretation of provisions in the contract documents and technical specification was the prime responsibilities. Modification and issuing of detailed drawings to the contractor, preparation of variation statements, reviewing of monthly progress review meetings and co-ordination. Total Quality Control for entire project, Reviewing of Contractor’s QA & QC Plan, Quality Monitoring

Name of

assignment or

Project:

Supervision of operation, Maintenance and upgradation of of 387 KM of 4 Lane Road Pulekhumeri-Mazare-Sharif-Balk and International Stretegic link from Naibabad to Uzbekistan border- supervision and contract Management, Funded by ADB

Year: Feb 2008 to Aug 2008

Location: Abghanistan

Client: Min of Civil Works Govt of Afghanistan

Main Project

Features

Funded By ADB on FIDIC Conditionsof contract,

Position held: Team Leader

Activities performed: Responsible for lead the team as Team Leader in Day To day Quality Control & Supervision of Road Project, Project Management, Contract Administration, checking the accuracy of all controlled surveys, Investigations, Construction Program, safety plans, Interpretation of provisions in the contract documents and technical specification was the prime responsibilities. Modification and issuing of detailed drawings to the contractor, preparation of variation statements, reviewing of monthly progress review meetings and co-ordination. Total Quality Control for entire project, Reviewing of Contractor’s QA & QC Plan, Quality Monitoring,.

Name of

assignment or

Project:

Independent Consultancy Service for Rehabilitation and Upgradation to four lane of Jhansi – Lalitpur Section from km 0+000 to km 49+700 of NH-25/26 in the State of Uttar Pradesh (Independent Consultancy Services Package No. NS1/IC/UP-2). Year: April 2006 to Feb 2008

Location: Uttar Pradesh

Client: NHAI

Main Project

Features

Project Length: 49.70Km, Project Cost: 655 Crore

Position held: Team Leader

Activities performed: Responsible for Project Management, Contract Administration, checking the accuracy of all controlled surveys, Investigations, also responsible for reviewing the Geometric and Crust design, setting construction standards for roads alignment. I have been continuously interacting with the Client. My duties and responsibilities include ensuring adherence to design standards ensuring quality construction of the project. For this purpose I had constantly interacted with number of other experts both on roads and bridge sides. I had been involved all types of road maintenance i.e. emergency, routine, periodic maintenance. During tenure I was responsible for road property FORM TECH 6 – CURRICULUM VITAE - NATIONAL Col. K L Monga, Page 4 of 6 Construction Supervision of Uttarakhand State Roads Project management, safety management and Toll fee collection. I have good exposure in junction improvement providing crash barrier and construction of Truck and Bus Lay byes.

Name of

assignment or

Project:

Construction Supervision of 4 laning of Dharwad to Belgam Section of NH-4 from km 433 to km 495 (length 62 km) in the rolling terrain of Karnataka State, FIDIC Condition Contract

Year: Nov 2003 to April 2006

Location: Karnataka

Client: NHAI

Main Project

Features

Project Length: 62Km, Project Cost: 540 Crore

Position held: Resident Engineer

Activities performed: Was responsible for review of detailed project reports and contract documents, check contractors’ setting out of the works, review of contractors’ work method and work program, develop Quality Assurance System, contract administration, review the contractors’ Quality management and assist in developing their Quality Assurance System, inspection of works during execution, materials and enforcing quality and safety, review and monitor contractors’ resources management, evolve Computer Aided Progress Monitoring System, monitor physical and financial progress of work, ensure implementation of Environmental Mitigation Plan, issue Interim Payment Certificates, evaluation of Contractors’ Claims, settlement of disputes and recommend issue of variation orders, verify ‘As-Built Drawings’. Name of

assignment or

Project:

• Consultancy Services for Quality Assurance, Contract management, Independent Checking and Technical Audit of Rehabilitation and Maintenance of Road Works in the State of Mizoram (length 225 km, 2lane SH), Funded by World Bank, FIDIC Condition Contract

• Supervision Consultancy Service of four laning and strengthening of the existing two lane sections from km 317.000 to km 65.000 (length 77 km) of NH- 2 in the states of UP and Bihar (GTRIP-5) (Construction Package –IV – A), World Bank funded. FIDIC Condition Contract

• Supervision Consultancy Services for Maintenance and Rehabilitation work of 4 laning NH-8 from km 162/500 to km 248/000 and km 273/500 to km 366/200 in the state of Rajasthan

• Construction Supervision of Ahmedabad – Mehsana Toll Road Project (length 50.6 km, 4 lanes) in the state of Gujarat,

• Construction Supervision of 4 laning of Vadodara – Halol State Highway No. 87 (length 32 km) on BOT basis in the state of Gujarat, FIDIC Condition Contract

Year: Feb 1999 to Nov 2003

Location: India

Client: NHAI, PWD

Main Project

Features

Funded by World Bank, FIDIC Condition Contract,

Position held: Team leader / Resident Engineer

Activities performed: Responsibilities included proof checking of the detailed engineering design and drawings, overall supervision of the physical progress of work using modern Project Management Techniques viz CPM and PERT to ensure execution of the project with in the time schedule avoiding time and cost overruns, review and approve contractor’s Work Programme and methodology, check the contractor’s setting out and quality assurance of work, assure the quality of laboratory testing of materials and check contractor’s laboratory, plant and machinery required for timely completion of the work. Also monitored contractor’s operations and ensured that the mixed material brought to the site met with specifications requirements. Other responsibilities included verification and certification of contractor’s interim payments and documentation of all measurements and testing reports, examine claims of contractor for unforeseen items of work or additional items of work which might have been assigned by the client and recommend variation, unit rate analysis, fixing the price of variation. Was also responsible for preparation of progress and other reports as and when required as per contract agreement and liaison with the client.

FORM TECH 6 – CURRICULUM VITAE - NATIONAL Col. K L Monga, Page 5 of 6 Construction Supervision of Uttarakhand State Roads Project Name of

assignment or

Project

Planning and execution of network of roads at Mahajan Range in Bikaner Sector of Rajasthan including 83 km of roads (2 lane), funded by Govt. of India Year: 1989 to 1992

Location: Rajasthan

Client: Govt of India Min of Def

Main Project

Features

The project involved road works in desert terrain besides other technical and research facilities

Position held: Dy. Director of Work

Activities performed: Responsible for overall project management including planning, scheduling, detailed engineering design and construction supervision, rehabilitation / re-construction of pavement (flexible and rigid) interpretation of specifications as per the contract documents, quality assurance, soil and material testing and investigations at laboratory as well as on site, contract management and administration, verification of contractor’s bills, preparation of progress reports and other necessary reports. Works was carried out as per IRC Specifications and Standards and MORT&H Specifications for Road and Bridge works

Name of

assignment or

Project:

• Project Preparation including design and construction supervision of Express Highway from Dubai in UAE to Muscat in Oman (length 170 km, 6 lanes)( Jan 1998 to Jan 1999)

• Construction Supervision of strengthening and widening from 2 lane to 6 lane of the 140 km road from Dubai to Abu-Dhabi in UAE. (Jan 1997 to Jan 1998)

• Design and Construction Supervision of strengthening and widening of Road from IZMIT to DUZCE section of Main Europe Route (length 70 km, 6 lanes) in Turkey (Jan 94 to Dec 96).

• Rehabilitation and re-construction of the roads / bridges from Sanah to Aden

(length 120 km, 4 lenes) in Yemen (93-94)

Year: Feb 1993 to Jan 1999

Location: UAE, Turkey, Yemen

Client: Govt of UAE, Govt of Turkey, Govt of Yemen Main Project

Features

International Bank Funded

Position held: Resident Engineer

Activities performed: Responsible for overall project management including planning, scheduling, detailed engineering design and construction supervision, rehabilitation / re-construction of pavement (flexible and rigid) interpretation of specifications as per the contract documents, quality assurance, soil and material testing and investigations at laboratory as well as on site, contract management and administration, verification of contractor’s bills, preparation of progress reports and other necessary reports. Works was carried out as per IRC Specifications and Standards and MORT&H Specifications for Road and Bridge works.

Name of

assignment or

Project:

• Construction Supervision and Repair and Rehabilitation of Road from Tezpur to Bomdila (length 170Km, Hilly Roads) in Arunachal Pra.

• Construction Supervision of 2 lane road from Akhigo to Maluri (length 37 km Hilly road) in Nagaland.

• Construction supervision of road from Phutzero to Tadubi (length 44 km, 2 lane asphaltic road) in Nagaland, Hilly Roads)

• Construction Supervision of Avantipur Airport. which included airfield pavement construction (Rigid 4 km – 60 m wide including shoulders.

• Construction Supervision and Repair and rehabilitation of 2-lane Pathankot – Srinagar National Highway (NH-1A) (length 300 km), in the states of Punjab and Jammu & Kashmir (Hilly Roads)

Year: 1968 to 1989

Location: Indian,

Client: MES

Position held: Superintending Engineer (equivalent to Team Leader) / Executive Engineer (equivalent to RE) / Asst Executive Engineer (equivalent to ARE) Activities performed: Responsible for overall project management and supervision of construction works including review and approval of detailed designs and drawings, approval of materials FORM TECH 6 – CURRICULUM VITAE - NATIONAL Col. K L Monga, Page 6 of 6 Construction Supervision of Uttarakhand State Roads Project and materials sources, pavement designs and specifications, monitor both financial and physical progress of works in terms of cost and time overruns, adherence to strict quality controls as per the specifications in contract agreement, verification of contractor’s bills and preparation of monthly progress reports. 13. Certification:

I, the undersigned, certify to the best of my knowledge and belief that

(i) This CV correctly describes my qualifications and my experience;

(ii) I am not employed by the Executing / Implementing Agency;

(iii) In the absence of medical incapacity, I will undertake this assignment for the duration and in terms of the inputs specified for me in the Personnel Schedule in Form TECH-7 provided team mobilization takes place within the validity of this proposal or any agreed extension thereof;

(iv) I am committed to undertake the assignment within the validity of Proposal;

(v) I am not part of the team who wrote the terms of reference for this consulting services assignment;

(vi) I am not sanctioned (ineligible for engagement) by ADB. I understand that any willful misstatement described herein may lead to disqualification or dismissal, if engaged. K.L.MONGA

Date: 23/02/2015

[Signature of expert or authorized representative of the firm Day/Month/Year Full name of authorized representative:



Contact this candidate