Post Applied –General Manager –Civil &MEP services
I am truly a single point total solution provider for project
M.V Natarajan (Alias: Suri. M. V)
General Manager – High Rise building -MEP Services
Sion Mumbai (E) Maharashtra India -400022
Mobile no-989-***-****, 900-***-****, Email: acry4i@r.postjobfree.com, acry4i@r.postjobfree.com
Career Objectives:
Highly motivated and experienced manager with strong leadership skills and to utilize my skill set as a senior manager in a reputed organization and use my extensive experience to bring in positive results from the project’s and become a valuable company asset.
Career Summary:
25 yrs.’ experience from engineer to MEP General Manager working on different projects from a technical institute in India to a company in the UAE. I have extensive experience in managing Mechanical and Electrical projects from inception to completion. Worked on projects in various disciplines for the past years with reputable companies with experience in MEP system with, HVAC, Electrical, plumbing, firefighting, FA.PA system ELV system. Well acquainted with Government Authority of India & U.A.E towards document and material approval from DEWA / ADDC/BEST power & water, ADSSC for drainage, Civil defence for Fire alarm & fire fighting and LPG, Municipality for project completion certificate and Etisalat for telephone & services network, HVAC: Chiller Installed up to 2000 ton VRF, FCU AHU, Fresh Air, Exhaust System, Toilet Extract system, Stair case pressured system, lift room pressure system, cooling tower, Heat recovery. Designing issue:- 1. Cross check size of pipe /duct, 2. Cross check air & water balancing, 3. Extreme condition maximum load & high ambient temperature peak load – equipment to be selected. Note-High rise building – chiller were used in common area. VRF are used in the Apartment with water cooled one by cooling tower system – 55% power will saved. ELECTRICAL: HV- Incoming, L.V Distribution, P & D transformer, Bus bar – Trunking, maximum demand control, back up powers UPS, Generator sets with acoustic lighting external /internal,Earthing/ lightning protection, laisioning approval, commissioning & asset management – Note-calculation of sizing, bus bar, earthing, cabling, lighting protection, illumination, D.G set, battery & battery charging, co-ordination layout drawing for power control with schematic, design & engineering of LV/HV Electrical distribution system. Interfacing management with other services building services. FIRE FIGHTING: Fire plant room & fire Equipment’s, fire alarm and sprinkler & hydrant system & fire escape system. GARBAGE CHUTE: transporting garbage, store location & disposal - safety/hygienic to be considered. ELV SYSTEM: MATV, CCTV, P.A, fire alarm, system, structural cabling system – design and preparation layout data, voice, network barrier, AMF panel, lighting systems, security systems, water pump, firefighting panel & pumps, HVAC system are to be inter connected through BMS.
PHE: Fountain, Reflection pool, Swimming pool & Filtration Plant -Water and waste water - R.O. plants, Desalination plants, Sewage Treatment plants & ETP, Hot water system ( boiler/ solar,/heat recovery coil system), water pump – designed & Installation with booster pump system & gravity system with water hammering, OHT, UGT & flow system & installation with PRV, loft tank, bath tub, sinks, shower, hot & cold mixer, Drainage air vent, nanny trap ), Storm Water, Rain Harvesting, landscape systems, High rise building – plumbing shaft method of installation,noise proof, access for free maintenance, toilet & bath room & balcony area- water proofing. VERTICAL TRANSPORT SYSTEM: - elevators, conveyors and carousels, elevators, E.O.T crane, EQUIPMENT; kitchen, weighing machines, special types of doors etc. boilers, laundry system, vehicle scanner, boom barrier
CONSTRUCTION INDUSTRIES EQUIPMENT’S : tower crane batching plant trucks, vibrator, jcb, road roller, temporary power supply for construction ( D.G SETS), car,concrete pumps, mixers, jack hammer etc., maintenance & servicing, TOOL ROOM INDUSTRIES – Injection moldings, compression moldings, sheet metal, press shop-1000 ton press hydraulic, pneumatic & CNC control press Godrej,tool room machinery, quality control equipment’s, sparking machine, wire cutter, welding machine forge, heat treatment, gas welding, D.G set up to 1000kVA, air compressor up to 3000 TC, Pellet truck, battery driven high reach truck, dock level, shearing machine, CNC tool room machines – electrical, mechanical, electronic – maintenance & service, repair.
Professional Summary:
Close to 25 years of Experience in MEP Planning, Coordination, Designing, Execution and commissioning & with comprehensive knowledge in International codes and standards like NFPA, International Building Code, UPC, ASHRE and NBC with adequate knowledge in ECBC norms Exposure in handling and executing projects in various verticals covering Commercial buildings, Hotels, Facilities and Residential complexes in multi-cultural environment
Personal Profile:
I am an Engineering professional with 25 year’s experience in contract management, POMEC and Engineering mainly gained from working within the construction industries in the UAE and India. My areas include practical and administration experience in MEP Engineering / FM / POMEC / Hotel Industries / Industrial Engineering / Building Services on projects such as High Rise buildings, high profile residential and commercial developments.
Professional skill:
Leadership skill
Coaching skills.
Process analysis skills.
Strategy development.
Proprietary methodologies
Co-ordination is the unification, integration, synchronization of the effort of group members so as to provide unit of action in the pursuit of common goal, planning, organizing, staffing, directing, controlling.
Outstanding troubleshooting and Diagnostic skills.
Prove ability to lead people and get results through others.
Ability to manage multiple tasks and priorities.
Proficient with, AutoCAD, CMMS and MS Project Primavera.,TPM, EMS, BaaN,ERP
Project management.
Project coordination
Execution & Billing
planning ( schedule & planning )
Quality/ASHRAE -62.1
Sub-contractor management
Engineering & procurement
Client management
Tender & Budget
Managing the consultant
Client co-ordination
Build project from concept to commissioning
Commercial
Rate Finalization
Monitoring
Time Management
Technical issue
Erection & commissioning
Design
Business development
Contract management
Risk management
Comprehensive building solution included design & engineering
Communication skills
Cost management
Laisioning
Educational Qualification:
Associated Degree- N.T.T.F Electrical maintenance Engineering
N.T.T.F Technical Training institute – India - Web site –WWW.nttftrg.com, Phone - 009***********
Integrated Facilities management -certificated in Haden International India ltd
CUMMINS Engine – Trained as service engineer from Ajax Bangalore India
Significant Highlights/Trainings and memberships:
Approved by ADDC as MEP Manager.
Active Member of American Society of Mechanical Engineers (ASME) Undergoing Seminars
IT/ Software Skills:
MS Office 2007, MS Project 2007,AutoCAD, primavera, Fidelio
Personal Information:
Date of Birth- 21st July 1969
Nationality-Indian
Marital Status-Married
Driving License-Valid India
Language Know-English, Tamil,Telugu,Malayalam, Hindi, Kannada, & Marathi
Main Responsibilities:
Demonstrate & use of Expert know how the entire MEP part of construction projects in all its aspects such as : design, function, installations, Functionality & coordination with other facility provider /project manager as per clients wishes .
Coordinate the MEP design and execution between architecture /structure /design office and contractors/subcontractors
Provide the planning input for the MEP works and Monitor Planning vs. Progress on site
Document project progress and/or delays through letters which can be used as contractual aids during disputes. Lead and control the document flows
Able to review resource reports like (manpower histograms, plant and machinery schedule) and ascertain adequacy of resources deployed for timely completion of the project
To review and certify the monthly invoicing of the contractors/subcontractors.
Audit the performance of MEP subcontractors.
Implement/follow proper QA/QC procedures by maintaining and following Project QA/QC Manual.
Lead technical coordination meetings with subcontractors and project staff.
To provide technical input for offer requests and the awarding of MEP subcontractors to the contracts, procurement department.
Be adaptive in and aware of International and Local Building Codes of all MEP Systems
Have hands on experience on the procurement, installation and testing & commissioning of all MEP Systems
Lead and mentor a team of Mechanical and Electrical Managers on Site
Oversee and enforce the implementation of HSE by MEP Contractors
Able to perform all post tender activities of construction until the handing over and completion of the defects liability period of the project
To ensure compliance of construction activity to best industry standards, international codes, planned timelines, allotted budget, company strategy and goals.
Strong knowledge of scheduling/planning and tracking of progress
Strong interpersonal skills
Strong verbal and writing skills, with regards to contractual communication
Knowledge of risk assessment and contingency planning
Awareness/ Exposure on various Construction/System methodologies
Ability to manage multiple project site
Problem solving skills
People management skills
Major Project India & U.A.E- Total 25years Experience
Presently working
Miran international hotel – Project General Manager – 5th June 2015 ( Tashkent Uzbekistan ) Russia www.miran hotel.com…
India Experience –(North India ) MUMBAI
Omkar Realtors & Developer Pvt ltd – South Mumbai- India - General Manager – MEP SERVICES- Handling 9 projects - Report to EPC Head. Mr John Guest - India Project - 1 Year 8 Month – Dec 12th 2013 Till 31st July 2015
Client: Omkar Realtors & Developer pvt. ltd
Architecture – Foster +Partner
Consultant : Buro Happold
Main Contractor : L& T
ESPA – SPA Design
DHA- Lighting Design
LDA -Land Scape Design
HBA- Hirsch Bedher Associates – Hospitality Interior Design
Barkley – Pet Care design
MEP Contractor : Not Finalised
Commencement Date : August 2006
Area – 10 Million SQ FT
Height – 300 metres tower-A – 78 floor, Tower-B -77 Floor, Tower-C -63 Floor
Web Site- Http://Omkar1973.Com
MEP Team Members :- 19 person+ secretary =Total 20 no’s
Site team -6 supervisor, 1- MEP co-ordinator, 3 -MEP manager’s, 1 Assistant MEP manager, 1-Site electrician.
Office team – Design team -1-HVAC, 1-Electrical & ELV, 1- Plumbing & Fire Fighting, 3-MEP Draft man, 1-tendering & budget, 1- procurement & work order=20 people.
MEP Design to freezed for Worli project it took me Around 1 year & 7 Months:
HVAC – Apartments VRV Were Used And Saved 50 % - Instead Of Chiller Water System Units
Electrical Bus Bar We Used ALU & Cu Connector Saved Around 50%,
Plumbing As Per Design- Pressure Pump Converted Into Gravity System
Firefighting As Per CFO Norms
Substation Location With Best HV Supply Common Area, Lv Supply To Flats – Completed It Saved Around – 13 %
STP 680 KLD is used for Cooling Tower Purposes It Will Cool the VRV out Door Unit.
Boiler,
Heat Exchanger,
Safety & Security System- Design freezed
Facilities Management – Services Design freezed
Swimming Pool, Foundation, Water Curtain, Design Freezed
Lightning Arrestor Freezed
Shaft Plumbing Raiser Mock Up Completed –Consultant Approved Material Were Changed - We Saved Around 26 %
Electrical Raiser Cable / Wire –In Shaft/ Apartment Freezed –In Material Saved Around 32 %
Apartment Consultant Design – 2 Electrical DB. We Changed Into 1 Electrical DB- Saved Around -6 %
Lift – 66 Were Freezed ( Landing location as per traffic, Safety & Guest Comfort -Designed Were Freezed With Schindler )
Garbage Chute Fire Safety / Hygienic Purposes Washing with Chemical Dosing– Shifting Material & Location and Storing the Dry & Wet Garbage and Segregating the Waste & Transporting them.
Final Design Worli Tower Only 2 Staircases For Tower-A – Construction Were Completed Up To 47 Floors. At The Time Of Approval CFO Required 4 Staircases. (Staircase Pressurised System Were Re-Designed Work Completed)
Mechanical floor – plumbing water supply ring circuit it was in the apartment – shifted to mechanical floor
For Tower A, Tender Were Floated In The Market-B3 TO P-13 Level.
Lobby Design Freezed - MEP Contractor Were Appointed Work Under Progress,
Apartment –Mock design freezed – work under progress
Rehab building
Apart from this I was handling 8 rehab buildings, constructions were on going in that- MEP design & installation done for a 4 projects & handed over properties.
Rehab building
Worli Maha Lakshmi – 7 tower
Kaprideo – 3 tower handed over
Praghati – 3 towers were handed over
Memon Chawl – 1 building were handed over
All building were handed over with O.C
Sale building
Memon chawl- Up to 27 floor completed, handed over with OC to the properties.
Vayu( projects -design were completed, tender closed/ appointed contractor work under progress)
Veda – 1 tower up to 27 floor completed, handed over with OC to the properties.
Ganeshwadi ( projects -design were completed tender closed/ appointed contractor work under progress)
Kurla jai kalayan (projects -design were completed tender closed/ appointed contractor work under progress)
U.A.E Experience:- 9 Years-
Project-1
Al-Futtaim Carillion LLC
JV- Hastie International LTD
Project – Abu Dhabi
Project Name – Cleveland Clinic
Designation – Deputy Project Manager
Area – 17,18,19 floor
Main contractor – Samsung C & T company join venture partner six constructions.
Developer- Mubadala - joint venture- MEP –AECOM Patient tower
Architecture –HDR Inc. USA
Past 2 years ETA hasn’t been able to get approval from Consultant/ Cleveland team. MEP work carried with proper MEP co-ordination with all services within 15 days and got approval from consultant & Mubadala – (Al-Futtaim Carillion LLC MEP engineering team) - for patient room, guest room, corridor & stair case. We finished project -3 floors in 7 months with commissioning and handed over the client to MUBADALA, 1600 technician’s, 15 supervisors, 3 engineers, 1 deputy project manager & project manager.
Project value – 68,656,000/-AED
Project-2
Down town Dubai development plot no -55-56-57
29 Boulevard offers a stylish residential address in Downtown Dubai.
Designed by Frank Williams & Partners Architects,
Civil contractor – Al-Futtaim Carillion LLC
MEP Contractor – Hastie International ltd LLC
Client: Emaar properties PJSC
Client’s engineer: Bruce Henderson Naseer Saeed Partnership (BHNSP)
Contract name: Burj Dubai Developments.
Designation – Mep Construction Manager
Project handed over -23rd November 2010
Project cost -44,400,000 AED
The loft project involves the construction of 3 high rise residential buildings, two of 42 floors and one of 38 floors. These are connected by a podium/basement structure of 9 floors. This structure has three basement levels of car parking, a ground floor containing retails units, a further level of parking, and four floors of apartments.
The overall floor area is measurement 155000 metre square and the total number of apartments is 670. Other amenities included canteen, wash rooms, squash courts, lounges, business center, children’s play areas, mini theatre, library, games rooms, gym and steam room.
The building envelopes is a mix of precast concrete panels and curtain wall at lower level stone cladding will be provided . The internal finishes are generally to a high specification and building services are normally found in similar residential developments.
District Cooling- HVAC, Water hammer were used. Hot & cold water – PPR Issued, drainage- HDPE pipe, kitchen extract duct connected to portable kitchen smoke extract
(Work As Mep Construction Manager in Hastie international LLC - Joint venture -with al-Futtaim Carillion LLC- building service manager. Hastie company closed due to crisis in Dubai 2011 and was promoted as deputy Project Manager for Cleveland clinic)
Khalidiya Palace Rayhaan by Rotana Hotel & Residences – complete project handled and handed over to Rotana client
Project-3
Client : Pvt. Dept. of H.E. Sheikh Mohammed Bin Khalid Al Nahyan
Project Manager: M/s E.C. Harris International Limited
Consultant: M/s Khatib & Alami Consolidated Engineering Co.
Designation- MEP Project Co-ordinator
Main Contractor: M/s Nurol General Contracting LLC
MEP Contractor: M/s Emirates Technical Associates (ETA), Abu Dhabi
Started Date: August 2006
Completion Date: September 2010
The project involves construction of 4 high rise towers in 4 Blocks: Block A will house the Khalidiya Palace Rotana Hotel comprising a ground floor, a mezzanine level, a technical floor and 18 additional floors offering 400 single bedroom units and 43 suites. Block B and C will each house a residential tower comprising a ground floor, a mezzanine floor and 19 additional floors offering 10 flats on each floor of which 5 flats will be duplexes. Block D will house a residential tower comprising a ground floor, a mezzanine floor and 19 additional floors offering 8 flats on each floor. Amenities in the project include: squash courts, 2 tennis courts, a spa, a gym, swimming pools and a children’s play area. Facilities in the project include: 24 hours safety and security, 36 office spaces, 2 well branded shops, business facilities as well as an underground car parking area of 30,000 square meters. Cost 210,000,000 US$,
ETA- M&E has provided Mechanical & Electrical services for the entire complex including leisure facilities such as white sanded beach, swimming pools, state of the art fitness centre and spa and extensive water sport activities, along with all-day restaurants and ballroom
Chillers Bay
Chilled Water Pumps
Air Conditioning Work
6,500 TR Air Cooled Screw Chillers
41 Nos. FAHUs/AHUs
2177 Nos. Fan Coil Units
43 Nos. Chilled Water Pumps
40 KM Chilled Water Piping
125,000 Sq. Mtrs. of Ducting
Fire-rated ducts for sensitive areas
77 Nos. Exhaust Fans
17000 Nos. BMS Points
Stair case pressure system
Parking ventilation system
Fire door –entry safety – theft issue
Fire damper
Electrical & ELV System
22 Nos 11 kV/400 V Dry Type Transformer
3000 Meters of Bus bar Installations
4 Nos. standby Generator (15,364 kw)
3 Kilometres of HV Cables
5 Nos. 11 kV Switchgear
19 Nos. MDB
149 Nos. SMDB and 1080 Nos. DB
11 Kilometres of XLPE Cables
42000 Nos. Switches & Sockets
4500 Nos. Fire Detecting Device
1165 Nos. Voice Evacuation Point
49,000 Nos Light Fittings
48 Nos. Central Battery Panel
46 Nos. Lighting Control Panel
11 Nos. Fire Alarm Panel
Solar light
LV ROOM
HV ROOM
Parking -occupancy sensor
Plumbing & Fire Fighting System
48 Kilometre Water Supply Pipes
25 Kilometre Hot Water Supply Pipes
31 kilometres Fire Fighting Pipes
1117 Nos. Water Heaters
25 Sets Water Pumps
3 Nos. Fire Pumps
7000 Nos. Sprinklers
Specialised Equipment’s
3 Nos. Steam Boilers
6 Nos. Clarifiers
2 Nos Water Filtration System
2 Nos. Water Softener System
Swimming Pool & Water Fountain
System
Room, carpets
Interior/balcony grill
Marble
Wall paper
Furniture
Door lock
Staff room
Hk room
Pomec department
Camera
Laundry chute
Corridor music system
Tv/telephone system/ epbax, Xerox,internet wi-fi, balcony drainage system,
Basement drainage system
Centralized LPG System
Gymnasium
Spa & equipment’s
Fountain
Kitchen equipment’s
Laundry
Restaurant
Night club/ lighting /music system
Pet care
Ro plant
Stp plant
Parking system
Safety & security system
Lighting-internal/ external
Music system
Store room
Canteen
Fire wall/fire ceilent
Mechanical floor – 3nos
Garbage room
Bar equipment’s
Mood light
Fedilo hotel soft ware
Revolving door
Lifts
Cold rooms
Project-4
Main Contractor – Target
Consultant – Ramboll
Mep Contractor – Sensaire Service - 2 Towers ( HVAC & PLUMBLING )included Site Co-Ordination
Project Handed Over
Designation- FM – Mep Services
Ramee royal hotels is a four star deluxe property. The hotel offers 102 elegantly furnished rooms (96 standard and executive rooms and 6 suites) new unfinished hotel was renovated as a 4 star hotel- Dubai- B1+B2+G+4+R
I had joined as MEP maintenance manager for Ramee group of hotels.
Apart from this I use to handle 8 hotels on POMEC issue.
*Regent Palace Hotel, *Regal Hotel, *Ramee international,*Ramee Royal, *Ramee Guest line- 2 ( quality inn ), *Ramee Guest line-3,( Binsalone plaza), *Ramee Apartment, *Ramee guest line apartment-1, *Ramee Beach Resort, *Ramee Cruises-1 & 2 *Mr.Clean laundry, *Ramee PIZZA,* 2 & 3 Ramee guest line hotel( old hotel )was purchased from Ramee project management – renovation was carried out & it was handed over to hotel management
Haifa technical service –Dubai
Worked as –Facilities manager- CIVIL & MEP SERVICES
Construction & MEP company
Project detail given below
WWW.haifagroup.com
Consultant M/S. Eng. Adnan Saffarini
Main Contractor M/S. Al Nuaimi Group
Mep Contractor M/S. Haifa Technical Services
Building: G + M Office, Warehouse And G + 3 Parking Building (8lvl) For Emirates Arabian Adventure Operation Center At D.I.P.
RAK MALL, Shopping Center( G + 1st + 2nd ) on Plot No. 13303 in Al Quirm Area, Ras Al Khaimah
CLIENT M/S.Emirates Airlines
CONSULTANT M/S.Design Concepts
MAIN CONTRACTOR M/S.High Star Contracting
MEP CONTRACTOR M/S.Haifa Technical Services LLC.
Building- 2B+G+M+8+TYP BUILDING AIRPORT ROAD-DEIRA
Client Mr. Dhai Khalfan Dhahi Bin Tamim
Consultant Eng.Adnan Saffarini
Main Contractor Buset Contracting & Gen. Transport Co.
Work Electro Mechanical Services
Scope of Work: Air-conditioning: Supply & Installation of ducted split of 560 nominal tones capacity. Supply and installation of ventilation system, Copper pipes with insulation & finish. G.I. Duct work incl. supports & Hangers.
Electrical:: Load Connected 2 x 1000 KVA Transformers Total connected 1572.57 kW .Main LV Panels supplies 701.67 kW & 870.9 kW.
Plumbing: Drainage & Water supply line with water tank 2 Nos of 7000 gallons. Drainage & Water supply line with water tank 2 Nos of 7150 gallons and Fire Fighting.
Building 2B+G+M+8+GYM COMM BUILDING (GARHOUD)
Client Mr. Rashid Bin Thani Bin Khalaf Aal Thani
Consultant M/S. Eng. Adnan Saffarini
Main Contractor Ginco Contracting Est
Work Air-Conditioning
Scope Of Work: Air-Conditioning: Supply & Installation Of Ducted Split Of 390 Nom. Tones Capacity. Copper Pipes With Insulation & Finish. G.I. Duct Work Incl. Supports & Hangers.
Building B+G+13 Res.Building Tower (Internet City)
Client Mr.Tayyab Mohammad Ibrahim
Consultant Al Ajmi
Main Contractor Al Badr Contracting Co. Llc
Work M E P
Scope of Work: Air-conditioning: Supply & Installation of ducted split of 700 nominal tones capacity. Copper pipes with insulation & finish. G.I. Duct work incl. supports & Hangers.
Electrical: Load Connected 2 x 1500 KVA Transformers Total connected 2679 kW .Main LV Panels supplies 1301 kW & 1376 kW
Plumbing: Drainage & Water supply line with water tank 2 Nos of 7000 gallons
Building 2B+G+8 BUILDING (AL BARSHA)
CLIENT MR. ZAID BIN MESFER BIN ZAID AL WAAAYAN
CONSULTANT H A D I
MAIN CONTRACTOR GOLDLINE CONTRACTING LLC
WORK AIR-CONDITIONING
Scope Of Work: Air-Conditioning: Supply & Installation Of Ducted Split Of 318 Nominal Tones Capacity. Copper Pipes With Insulation & Finish. G.I. Duct Work Incl. Supports & Hangers.
As Construction Facilities managers I have to wear many hats-duties calculating cost estimates, budgets and schedules; selecting appropriate construction methods for
the job and budget; explaining contracts and technical information to employees; supervising construction personnel and activities onsite; developing work-around for
Delays and other problems; and hiring and training workers and subcontractors, as well as making sure the project meets all building and safety codes. Also spend a
Good deal of time interacting with clients and other building professionals, especially in the early phases of a project. In addition to the time spent in the initial
negotiations for the project, they have to give clients regular progress updates and submit budget reports & collaborating with architects, engineers, inspectors and
Other building specialists. Supporting and assisting the Exec General Manager (EGM) for the Civil Construction Sector, including:
Provide information to management for the purpose of decision making
Prepare FM presentations on construction project
Arrange staff events on behalf of FM, including but not limited to: Leadership Meetings, Wider Leadership Meetings and Full Team Briefings
Arrange field visibility opportunities for FM
Assist the FM with his corporate connection and flow of information
Assist FM to meet CEO requirements and requests
HR administration of FM direct reports, including but not limited to meeting preparation and records for 1:1s, Performance reviews and on track discussions
Reporting writing and compilation, including but not limited to SMT monthly report and Board reports
To manage the action registers with accurate and up-to-date information
To assist in the writing of business plan/strategy documents as required
To maintain the Civil Construction risk register
To work with the FM to undertake project based work as required
To assist the FM as required with monthly reporting requirements including compilation
Maintain management processes, systems and folders on behalf of FM
Assist the FM to ensure we meet internal and audit criteria
Actively identify systems and process within the Civil Construction Division that conflict or do not align to Corporate requirements
Ensure all FM internal communication reflects Haifa /sensaire services values and strategic goals of growth, innovation/efficiency and excellence
To work with other Civil Construction support functions (namely human resources and health and safety) to raise levels of internal communication and staff engagement
Working with the HR Manager, take the temperature of internal communication from time to time to gauge satisfaction levels and maintain the high-level Staff Engagement Plan
Draft and distribute key FM communication tools, such as FM Newsletter, HSQE Newsletter, and text messages on a regular basis
Take an overview of Civil Construction stakeholder communications to ensure they are concise, consistent and relevant.
Lead the Communication team ensuring quality output and high levels of internal customer satisfaction (two direct reports)
Motivate and manage the team to ensure high levels of team engagement
Generate staff development plans, provide regular performance feedback and conduct appraisals.
Conduct recruitment activity as required
Assist with staff events which aim to raise the level of satisfaction and engagement within the division
Review new contracts for communications requirements and opportunities.
Ensure clients’ expectations are understood and met or exceeded by the Project Managers
India Experience-15 Years (South India)
Royal Orchid Central Park Hotel Bangalore India – joined as Assistant Chief engineer promoted to Chief Engineer- Aug 15th 2005
Hilton Group -Golden Palm Hotel & Resort & Spa -Bangalore Assistant Chief Engineer March 5th 2003
Haden International Group India Ltd – IFM system - Maintenance Engineer- Ford Car Company/Vinoram April 4TH 2001
M-far construction –Hotel Le-Meridian Project Plant Engineer Cochin- Kerala –India- Bangalore July 19TH 1999
Data links-Maintenance Engineer -ELV system – (Palm Grove, Ashoka, Bala Residency, St Mark, Museum Inn) June 18th 1996
N.T.T.F Production Centre India – Bangalore – (Industrial engineering) Technician -2, Supervisor,Engineer May 2ND 1988
Present Salary - Rs 46 Lakhs P.A. +Yearly flight ticket +free accommodation
References
Mr. .John Guest – EPC HEAD – Omkar Realtors & Developer Pvt ltd- mobile no 077********
Mr M.K. Rama Krishnan – Project head – mobile 098******** acry4i@r.postjobfree.com