PABLO G. MACIAS

*** ******** *** ************, *** Jersey 08865

908-***-****; email: acgbxe@r.postjobfree.com

MEP Superintendent / Project Manager

Accomplished professional with more then 20+ years of versatile experience at all levels. Demonstrated

success in scheduling, coordinating and overseeing full scale renovations and conversion projects. Maintains

high level of commitment as a team player and can communicate with all levels.

Project Management _ Personnel development _ Mechanical _ Electrical

HVAC _ Architectural functions _ Vendor Relations

PROFESSIONAL EXPERIENCE

HIRANI GROUP ENGINEERING _ 2010 to 2014

MEP Consultant/Superintendent

Working as a part of the onsite Construction Management team (Hazen & Sawyer and

Malcolm Pirnie a JV) on the $230 million Manhattan Pump Station upgrade for New York City

Department of Environmental Protection (NYC DEP)

Coordinate and Inspect all Mechanical, Electrical and Plumbing installations

Generate and monitor the progress of punch lists

Review Submittals, RFIs and Contractor requisitions

Documentation preparation for all equipment/systems, controls functionality,

{Commissioning}

Validation of Equipment that requires to be validated

Prepare close out documents

Review contract drawings, specifications; prepares change order work estimations based on

revised contract drawings

ANG CONTRACTING _ 2008 to 2010

General Superintendent $45 Million Project Value, 225 Sq. ft.225,000

Managed all employees, sub-contractors and vendors for 225,000 square foot building

conversion at JFK Airport from start to finish.

Oversaw pouring of concrete slabs in the winter after the underground was installed.

Scheduled utility coordination with the Port Authority of NY/NJ.

BOYMELGREEN DEVELOPERS _ 2006 to 2008

Lead MEP / Architectural Superintendent, $15O Million Project Value

Oversaw conversion of existing 40 story Chase Bank building into 422 apartments.

Completed all MEP infrastructures.

Coordinated equipment requirements and fire alarm installation.

Scheduled all Con-Ed services for completion

Completed build-out of five penthouse apartments, all operational for 1 st TCO

Reviewed contract drawings, specifications, and monthly contractor requisitions; prepared

change order work estimations based on revised contract drawings.

Prepare close out documents, as equipment was powered, (Testing program was put in place,

documents that require for commissioning.)

Resume

MORGAN CONSTRUCTION ENTERPRISES _ 2002 to 2006

MEP / Architectural Superintendent- Pfizer Corporate Building- $60 Million Project Value

Directed and coordinated project from start to finish.

Superintendent at Pfizer Corporate Building in Midtown Manhattan.

Installed three emergency generators for three buildings along with full renovation of MEP

infrastructure services

Columbia University- $20 Million Project Value

Conducted full infrastructure renovation of MEP services for three floors of 10,000+ sq. feet

laboratory space.

Came in under schedule by 4 months, completing work in only 9 months.

Coordinated all disciplines through entire scope of work.

Completed all architectural and MEP punch list items.

Lavatories require Commissioning and to be Validated

New York Presbyterian Hospital Laboratory for primate research

$60+ Million Project Value, 20,000 SQ, FT

Description: Demolition of existing of existing lavatories HAVC systems and Plumbing and electrical

system all these services were active. Some of these active systems were

In use, relocation of these systems had to be coordinate with building management. Equipment used

fume hoods, wood casework, worktables and cages all different type of animals. Vaccines room holding

area clean room, wash down area, where animals were spray down. Architectural finishes for conference

room, class rooms and professor office Hi end finishes. Role: Lead Super

managed all trades

Duration: There were four phases to this project, as we completed the phases. Existing laboratory

had to start moving.

GIBANE BUILDING COMPANY _ 2001 to 2002

MEP Project Manager

Executed front-end for BMS complete and all architectural and MEP punch list items.

Coordinated full services for laboratory equipment.

Coordinated installation of a three stage Steam Station. It would serve two of three AHU. One of the

three AHU requires clean steam.

Performed tasks that corresponded with active vaccine facility. Clean room, clean steam

Completed fully functional, new domestic water services, chilled water piping, and USP piping.

VRH CONSTRUCTION (VRH/TORCON a JV) _ 1998 to 2001

MEP Superintendent- / Coordinator 2.5 Billion Project Value

Managed and coordinated MEP/HVAC Subcontractors at the American Airlines terminal project

at JFK International airport.

Supervised installation of all Telecom and computer rooms.

Baggage handling system

TAYLOR CONTRACTING of FLORIDA _ 1996 to 1998

MEP /Architectural Superintendent Project Manager

Managed and coordinated all MEP/HVAC and Architectural sub-contractors.

Collaborated with Charlotte Regional Medical Center administrators to facilitate all activities

related to all operating rooms and cafeteria renovation at the hospital.

Assigned tasks and assured timely deliveries of schedules materials.

Assumed responsibility for delinquent projects requiting closure.

Resume

Projects include: Heart of Florida 14 story building, Office building, Residential tasks and a 22-

story condo project in South West Florida.

INDEPENDENT CONTRACTOR _ 1995 to 1996

Owner

Acquired and reviewed bids from MEP/HVAC and architectural trades for a variety of projects

and presented recommendations for clients review.

Provided GC services for these projects.

TISHMAN CONSTRUCTION, INC. _ 1988 to 1995

MEP Superintendent

Coordinated all services with MEP/HVAC sub-contractors for assigned projects.

Reviewed requisitions and submittals, released and tracked materials ensuring timely completion

of projects.

Managed installation of UPS system, computer and Telecom rooms throughout projects.

Projects: JP Morgan, Financial District (Base building. task; 58 story high rise), CITI Corp, 53rd

St (48 story base project), Base building. on 47th & Broadway, Low income housing renovations on

Lenox & 179th St.

Additional Employment Experiences upon Request

EDUCATION & CERTIFICATIONS

Staten Island College, New York AA, Mechanical Drafting

John Jay College _ New York _

• OSHA 10 HOUR CONSTRUCTION SAFETY CERTIFICATION

• OSHA CONSTRUCTION SAFETY CERTIFICATION