Matt Richer
METROPOLIS, IL. 62960 619-***-****
EXPERIENCE SUMMARY
OVER 31 YEARS CONSTRUCTION EXPERIENCE, INCLUDING NUMEROUS PRIVATE,
COMMERCIAL, AND PUBLIC WORKS PROJECTS RANGING UP TO $2.9 BILLION IN VALUE.
THESE PROJECTS INCLUDED BUT WERE NOT LIMITED TO "LAND LOCKED" TO "OVER
WATER WORK.". THESE PROJECTS INCLUDED CONSTRUCTION OF NUMEROUS MARINE
STRUCTURES, CITY PARKS AND MUNICIPAL UTILITY INFRASTRUCTURE. I HAVE MANAGED
UP TO 100+ CRAFT PERSONAL AND 5 CONSTRUCTION SUBCONTRACTORS ON A SINGLE
PROJECT.. I HAVE OVERSEEN THE SELECTION AND PERFORMANCE OF TRADE
CONTRACTORS AND CRAFT TO COMPLETE SPECIFIC COMPONENTS OF THE PROJECTS
INCLUDING LABORERS, CARPENTERS, PILE DRIVERS, CEMENT MASONS, TEAMSTERS,
OPERATING ENGINEERS AND IRON WORKERS. I DETERMINED LABOR REQUIREMENTS AND
HAVE BEEN RESPONSIBLE FOR ENSURING THAT ALL WORK ON ASSIGNED PROJECTS WAS
COMPLETED ON SCHEDULE, SAFELY AND TO THE LEVEL OF QUALITY EXPECTED. I BRING
EXPERIENCE WORKING IN CONJUNCTION WITH A NUMBER OF CITIES, COUNTIES, PUBLIC
WORKS DIVISIONS, PORT DISTRICTS, AND LARGE COMPANIES, ACQUIRING VARIOUS
ACCOLADES AND AWARDS OVER THE YEARS. (E.G., AGC, ROICC).
training: Ess Cross-training, hazwoper, 30 hr. osha, first aid, cpr,
l.c.m., QA/QC, SSHO, STS
PREVIOUS EXPERIENCE
MARINE SUPERINTENDENT, OLMSTED LOCKS AND DAM, OLMSTED, ILLINOIS (URS)
This project is to construct a new Tainter / wicket gate dam on an active
river using "In the Wet" construction methods.
General Marine supervision of all "in water" activities. These supervision
responsibilities included overseeing underwater pile driving, subaquatic
subgrade preparation, foundation stone placement, pre-grouted "pillow mat"
fabrication and deployment under water, all day shift tug boat (7) support
coordination and all over water safety monitoring and supply procurement.
Construction Manager, Metairie, La. (Tetra Tech-INCA)
Develop construction plans and schedule for the "Maintenance Dewatering
Structure" that is to be utilized ant the Montgomery Point Lock and Dam for
the USACE (Little Rock District).
Perform "on-site" construction supervision for the installation of a new D-
I water system for Lockheed/Martin at the Stennis Space Center.
Project Superintendent, Project Development, New Orleans, La.
U.S.A.C.E.(Tetra Tech, EC, Inc.)
Perform project constructability analysis, assets in project schedule and
technical approach development, support estimating team in developing cost
matrix.
Project Superintendent, Sediment Remediation (P.C.B.) and dredging. Alcoa
Vanexco Plant, Vancouver, Wa. (Tetra Tech, EC, Inc.)
Performed environmental dredging and shore line remediation, removal of
contaminated soils and fills and reconstruction of shore line levees and
slopes, place dredge spoils in 'on site' landfill and transport
contaminated spoils to suitable " off site " land fills, construct shore
line protection ( rip-rap ).
This work was performed on the Columbia River during the winter months
with snow events and freezing conditions. The project was performed at an
accelerated schedule due to the migration period of the native salmon.
Precautions were taken in the handling of all dredge spoils and mitigation
removal material due to the unknown levels and types of contaminates to be
encountered. The project had 0 loss time or recordable incidents.
Project Superintendent, Quay Wall and Fendering Replacement, NAVSTA, 32nd
Street Naval Station, San Diego, Ca. (Marathon Construction Corp.)
Performed demolition and reconstruction of structural foundations (above
and below water), installation of structural concrete "sheet pile caps",
driving new concrete, plastic and steel "H" beam piles, underwater dredging
and grading, floating dock installation and cementitious back fill.
This project was located in an active portion of a naval base and was
performed with both derrick cranes and land based cranes and heavy
equipment with naval equipment and personal in close proximity. A majority
of the work to be preformed was at an elevation that was generally
underwater at mid or high tide. Work schedules were adjusted (nights and
weekends) to accommodate these elements.
The procedures and materials used in this project, in most cases had never
been tried or tested. Many "firsts" were encountered during the duration of
the project. The project had 0 loss time or recordable incidents.
Project Superintendent, Mooring Facilities for the U.S.S. Midway, San
Diego, Ca. (Marathon Construction Corp.)
This project was designed to accommodate the aircraft carrier Midway that
was to be used as a public maritime museum. The pier that the ship was to
be moored to was found to be not structurally suitable for this
application.
The project consisted of the construction of mooring "dolphins" and
upgraded current pier facilities to accommodate the anchorage of the
aircraft carrier. The "dolphins" (2) consisted of a total of 95 pre-
stressed (20" hex.) concrete pilings, both plumb and battered, with lengths
ranging from 87' to 98'. The dolphin caps were poured in place. All
construction activities (fewer deliveries) were conducted from derrick
equipment.
This was a "High Profile" project and was constantly monitored by both the
public and the media. The project had 0 loss time or recordable incidents.
Project Superintendent, Reconstruction of Piers 1 & 5, NAVSTA, 32nd Street
Naval Station, San Diego, Ca. (Marathon Construction Corp.)
The Driving factors for this project were to stop the degradation of the
existing piers due to the environment (salt) and to up grade the capacity
of the piers to accommodate larger ships.
This project consisted of demolition and reconstruction of structural
foundations and pile caps, placement of new structural pier deck, removal
and installation of all electrical (substations, conduit and service
panels), and mechanical services ( steam, oily waste, sewer, rain run off,
compressed air and potable water).
This project was located in an active portion of a naval base and was
performed with both derrick cranes and land based cranes and heavy
equipment with naval equipment and personal in close proximity. Work
schedules were adjusted (nights and weekends) to accommodate these
elements.
Project Superintendent, 10th Ave. Marine Terminal, San Diego Unified Port
Dist. (Marathon Construction Corp.)
The Driving factors for this project were to stop the degradation of the
existing "cyclopean wall" and to facilitate the dredge depth capabilities
of the marine terminal. The project was designed and engineered to minimize
the use of divers in the near "black out" conditions that existed at the
elevations the work was to be performed. Communication between divers and
support (crane operators, riggers, concrete pump operators and tenders) was
paramount.
The project consisted of demolition and reconstruction of structural
foundations (above and below water), underwater dredging and grading,
placement of new steel sheet piles, installation of "underwater erosion
measures," driving new plastic piles, and construction of new oily waste
sumps. This work was performed with both derrick cranes and land based
cranes and heavy equipment.
The procedures and materials used in this project, in most cases had never
been tried or tested. Many "firsts" were encountered during the duration of
the project.
Project Superintendent, Emergency Seismic Stabilization Measures, "The
Child Development Center", NAVSTA, Submarine Base, San Diego (Marathon
Construction Corp.)
The Driving factor for this project was to stop the migration of the earth
beneath an existing structure that was built on a hill side. The site was
on a known seismic fault location and all access to the wall being
constructed was on a two to one slope. The stabilization needed to be
complete as quickly as possible so that the multi-million dollar structure
was not lost to soil movement.
The project consisted of hillside "pinning" and "solder pile", construction
of a structural gunnite retaining wall, installation play ground, removal
and reinstallation of hardscape and landscape components, site grading, and
new drainage (piping, ditches and structures). The project had 0 loss time
incidents
Project Superintendent, Automated Welding and Fabrication Facilities,
NASSCO, San Diego, Ca. (Marathon Construction Corp.)
The facilities we constructed were designed to automate the fabrication and
construction of large sections of naval and commercial ships. This project
was located in a very active portion of a commercial ship building and
repair facility. This shipyard operated 24/7 so coordination with the plant
entities was crucial.
The project consisted of demolition and reconstruction of structural
foundations, site grading, removal and installation of all electrical and
communication services (substations, conduit and service panels) and
mechanical services (steam, CO 2, argon, natural gas, oily waste, sewer,
rain run off, compressed air and potable water), and installation of
automated welding machines and devises. The project had 0 loss time
incidents.
Project Superintendent, Marina Floating Dock Systems, San Diego and
Oceanside, Ca. (Marathon Construction Corp.)
The projects consisted of removal and replacement of old dock components,
removal and installation of all electrical (substations, conduit and
service panels), underwater dredging and grading, "rip-rap" installation,
and driving of dock guide piles.
These projects were located in public marinas where private yachts and
pleasure craft were moored. The possibility for damage to private property
was high. The media and the public traffic were always present. All
construction activities (less deliveries) were conducted from derrick
equipment.
Project Superintendent, Hollandia Park, San Marcos, Ca. (Heffler Company,
Inc.)
The project was to construct a 37 acre public park for the City of San
Marcos, Ca. The design criteria consisted of 27 acres of vegetated area,
including three baseball fields and a soccer field, that were to be
irrigated by an on site, 170 gpm well. 150,000+ cubic yards of earth were
excavated and relocated on site in order to achieve finish elevations. The
site was to be a "balanced site", however 52,000+ cubic yards of imported
material was needed to be brought in to accomplish this task. The site
consisted of primarily granite, thus requiring a large amount of
"blasting". The blasting was closely monitored due to an 18" high pressure
natural gas transmission line dissecting the site.
The project consisted of site grading and irrigation with both potable and
well waters. Project included A.D.A. ramps, sidewalks, trails, Ball Fields
(soccer & baseball) installation including back stops, bleachers, fencing,
Skate Board park, comfort stations, concession stands, climbing wall, horse
shoe pits and storm drain ditches, structures, and piping. The project had
0 loss time incidents.
Project Superintendent, Balboa Ave. Street Scape (Heffler Company, Inc.)
The Driving factor for this project was "Neighborhood Revitalization" and
to correct street run off drainage issues. This was a "High Profile"
project and was constantly monitored by both the public and the media.
The impact to both foot and vehicle traffic were great. Access to stores
and residences had to be maintained during all phases of construction and
minimal detouring of vehicular traffic was mandatory.
The project consisted of site grading, irrigation, landscaping, A.D.A.
ramps and sidewalks, and traffic control. The project had 0 loss time
incidents.
Project Superintendent, University Ave. Street Scape (Heffler Company,
Inc.)
The Driving factor for this project was "Neighborhood Revitalization" and
to correct street run off drainage issues. This was a "High Profile"
project and was constantly monitored by both the public and the media.
The impact to both foot and vehicle traffic were great. Access to stores
and residences had to be maintained during all phases of construction and
minimal detouring of vehicular traffic was mandatory.
The project consisted of site grading, irrigation, landscaping, A.D.A.
ramps and sidewalks, and traffic control. The project had 0 loss time
incidents.
Professional and personal references will be provided upon request.