Resume:

**** ******** 972-***-****

Road. Samtrevino*@gmail

Groveland NY .com

14462

Samuel S Trevino

Objective Cost and schedule management positions, where

analytical ability, problem solving skills and the

ability to gain the respect and cooperation of

others can successfully promote increased project

control and gross margin.

Summary of Extensive experience in Cost, Scheduling and

Qualifications Estimating with demonstrated skills in analysis,

problem resolution and establishing productive work

relationships both nationally and internationally.

Experience includes:

Implementing and controlling cost, schedules and

estimating on a wide range of projects.

Strong background in governmental and commercial

reporting requirements, including earn value.

Through knowledge of all aspects of

telecommunications, manufacturing, environmental,

petroleum, pipelines, aerospace, mining/metals,

Professional transportation, chain supply and construction

Experience projects.

Expert in Primavera software, both P3 and P6

October 2011 to Present P6 Trainer, Claims

Consultant SY Visions

Planning/Scheduling, Claims Consultant, Primavera

Trainer

Professional Provide planning and scheduling support/development

Experience to various construction and oil companies.

Developed claims support to constructions companies

resulting in additional 10 million plus in revenue.

July 2010 to October 2011 British Petroleum Basra

Iraq

Senior Drilling Manager/ Regional Primavera

coordinator

Responsible for coordination of 14 work over rigs,

unexploded ordnance clearance, site prep, equipment

movement and crew deployment. Issued daily progress

reports on each rig. Trained local staff in P6.

Issued daily report on progress to senior

management in London. I worked on rotational bases

4 weeks in Basra and then 4 weeks off back in the

USA.

November 2008-July 2010 Granite

Construction Lewisville TX

Project Controls Manager

Responsible for all Major project 250m + on the

east coast. Trained local staff in P6 and project

controls concepts. Provided claims support on 6

major project, generating an addition 300m in

revenue. Review all subcontractor and vendor change

requests for cost and schedule impact.

Advise management of risks that may affect project

profit, cost, schedule and client relations.

Created construction schedule for Key water bridge

Key West FL, provided cost and estimating support

for scope creek. Provide schedule support to

environmental team, interface with customer on

environmental issues.

July 2007-November 2008 CH2M HILL

Professional Bellevue, WA

Experience Senior Project Controls Engineer

Responsible for the development of scope, schedule,

budget and estimate to complete data for Civil

Projects.

Review all subcontractor and vendor change requests

for cost and schedule impact.

Advise management of risks that may affect project

profit, cost, schedule and client relations.

Development and maintenance of periodic status

reports to keep management informed on project

progress.

Professional November 2004-July 2007 Boeing Everett,

Experience WA

Program Manager / Scheduler

Contractor developed and maintain detail schedules

for Systems Integration, Lab, Production first

Operational Date (PFOD), Certification, Interface

control Document (ICD) and Verification &

Validation

Provided scheduling and earn value analysis

Professional March 2004-November 2004 PVA Iraq

Experience Project Controls Supervisor

Recruited to provide projects controls support

utilizing Primavera P3e software to manage $150M

contract for communications infrastructure

restoration in Iraq.

Developed schedule, cost and resource loaded for 5

new switch buildings.

Professional 2003-2004 GE Transportation Rail Blue Springs, MO

Experience Project Controls Manager

Provide project controls support for all Transit

and Short Line rail projects nationally and

international (27 current projects).

Developed project controls procedures and trained

staff of 15 in Baseline, WBS, OBS, Ram, P3 desktop,

resource loading, earned value (Schedule/Cost),

statusing, change control, schedule of values,

documentation, estimating and monthly progress

reports (Crystal Report Writer).

Integrated project control policies with program

management and engineering policies.

Developed Subcontractors tracking and reporting

Procedures.

Professional 1999-2003 Lucent Technologies Redmond, WA

Experience Project Controls Manager

Created and trained Project Controls Organizations

in 4 Asia Pacific Countries.

Using P3 developed WBS, OBS, activity codes, cost

accounts and formatted the P3 data into Crystal

weekly summary schedules and cost reports.

Developed and controlled the estimating, cost and

schedules on 5 GSM projects and two CDMA projects.

Developed Estimates, Cost, Schedule and Trend

Procedures.

1995-1999 Bechtel Telecom Asia Pacific/China

Senior Project Controls Engineer

Developed and controlled the project estimating,

cost and schedule on a various projects. Using

Crystal Report Writer designed and integrated the

project reporting systems for performance tracking.

Worked closely with all disciplines to evaluate the

project progress.

Worked closely with project managers to establish

and implement proper reporting requirements to keep

the projects profitable.

Developed and implemented projects cost and

schedules for Engineering, Procurement and

Construction.

Using P3 compiled and reported resource usage, cost

and schedule status on groups of projects to

senior management for evaluation.

1992-1995 Bechtel Civil Seoul, Korea

Project Coordinator

Developed and managed estimates, schedules,

forecast, funding plans and contractual documents.

Responsible for estimating, design and construction

schedule development for $6.8 billion Korean High

Speed Rail Transportation System.

Estimated project cost for under ground

substations.

Coordinated all commutations between management and

contractors.

Using Crystal Report Writer established and

implemented proper reporting requirements to the

Korean Ministry of Transportation.

Responsible for all office automation, maintenance

and training.

Trained local engineers in P3 Korean version,

activity codes, baselines, budget cost accounts,

constraints, critical path, calendars, leveling,

updating, labor units, lag time, finish and start

dates, Gantt charts and Pert charts, cost and

resource reports.

1991-1992 Bechtel Civil Taipei, Taiwan

Senior Project Controls Engineer

Developed and controlled estimating, project

construction and equipment schedules, for Light

Rail System.

Reviewed and approved all project estimates.

Identified analyzed and found solutions for problem

areas that needed special concern.

Responsible for cash flow Vs appropriations fiscal

analyses and formal progress reports in Crystal

Report Writer including cost reporting with

expenditures and forecast.

1990-1991 Bechtel Civil San Francisco CA

Senior Project Controls Engineer

Staff position in estimating and planning

department.

Developed estimates for Manila, Philippines Light

Rail system

Developed estimates for Bart expansion.

Lead engineering planner for various PG&E projects.

Developed the project code of accounts, tracked

equipment and material status and cost.

Imported customer MS Project schedules into P3

Provided weekly Crystal Report Writer summary

schedules and cost reports to project managers.

Developed cost and resource loaded schedule for

Lipira in NJ USA environmental number one 1 super

cleanup site. Constructed water treatment plant,

reported weekly status to the Army Core of

engineers.

Education 1980-1982 Clayton University Clayton, MO

B.S., Business Management

Computer Access, PowerPoint, Excel, Lotus, dBase, Primavera

Proficiency (P3 and P3E versions), Microsoft Word, Openplan,

Quiknet, Artemis, MicroPlanner Expert, Microsoft

Project, Crystal Report Writer.



Contact this candidate