Address: ***** ** *** *****
Miami, Florida *****
Phone 305-***-**** (cell)
E-mail: acekz9@r.postjobfree.com
Educational Background
M.Sc., Environmental Engineering; Florida International University, 2001
M.Sc., Construction Management; Florida International University, 1995
B.Sc., Construction Management; Florida International University, 1994
Certification:
State Licensed General Contractor
OSHA Trained
Experience Summary
My current position is that of Construction Project Manager/Flood Plain
Construction Officer with Miami-Dade County Public Works and Waste
Management (PWWM) Department. Prior to this assignment, I worked with EGSC
Engineering Consultants and Brown and Caldwell (B&C). B&C is the former
County Bond Engineer for whom I worked for more than 11years, in
progressively more responsible assignments. Over the past 30 years I have
developed expertise in project management, construction methodology, and
have coordinated and planned the construction of new public facilities
working closely with consultants, architects and engineers. My
responsibilities also involved the compiling of monthly status reports,
interpreting regulatory codes, drawings and specifications, the
solicitation of bids from prime contractors, conducting pre-bid
conferences, executing NTPs and issuing field directives and change orders
to contractors. I have processed and made recommendation for payment on
contractor payment requisitions, prepared, issued and tracked RFIs. In my
role as project manager, I have provided supervision of construction
projects of various dollar values, as well as provided supervision of
engineering staff on Water, Wastewater, Airport, School and Solid Waste
projects in the United States and the Caribbean. Other responsibilities
included, value engineering/analysis, claims management, construction
scheduling and constructability reviews.
MIAMI-DADE COUNTY PUBLIC WORKS & WASTE MANAGEMENT (PWWM) Department
Flood Plain Construction Official - August 2013 to date
Working with hydraulic modelers to record and evaluate flood data used in
conjunction with NPDES related capital project. The data is also uploaded
to the FEMA database, and is used by that department to update flood maps
for use in Miami-Dade County. I am responsible for using ArcGIS Maps to
establish flood zone designations for individual properties throughout the
County, and compiling letters for residents, banks and insurance companies
for flood insurance purposes.
Olinda Park Remediation and Closure - (Project cost $2 million) April 2012
to August 2013
Construction Manager: Remediation, clean up and closure of an old County
monofill and converting the cleaned up area into a state of the art
community park. The work involves the implementation of engineering and
work practice controls to minimize exposure to contaminants. During soil
moving operation fugitive emissions were monitored on site, and control
stations were set up along the projects periphery to gauge the migration of
particulate material off-site. A storm water collection system with
attendant drainage structures, landscaping and a sprinkler system were also
installed.
Brown and Caldwell's Bond Engineer Services, Miami-Dade County Department
of Solid Waste Management ($138 million) March 1997 to September 2008
Project Manager/Client Service Manager: Provided construction
oversight during the expansion and retrofit of the Air Quality Control
System at the Miami-Dade County Resources Recovery Facility in the mid-
1990s. This retrofitted plant is a 3,000-tons-per-day Waste to Energy
Facility for which the Capital Expansion Projects were designed to achieve
conformance with EPA Maximum Achievable Control Technology emission
standards in 2001. A few of the projects of note include:
Demolition of two (2) 150 feet tall stacks and the construction of two
new ones each 32 feet in diameter (concrete) and 250 feet tall with wall
12 inches thick
The installation of four (4) Induced Draft (ID) fans
Demolition of four (4) electrostatic precipitators and the installation
of four (4) Air Quality Control bag-houses
Installation of spray dryers, fly ash and bottom ash conveyors, fluid
drive motors
Construction of a computer center, a building that also houses the motor
control centers (MCCs) for all the mechanical equipment
Construction of a concrete clarifier, a well water treatment system, two
lime silos (each 120 feet tall) and two carbon silos (each 80 feet
tall), compressor rooms, a four storey high cooling tower refurbishment
and the installation of air quality control system appurtenances
The expansion of the Trash tipping floor and the installation of new
Trash processing equipment (destoners, trommels, conveyors, concrete
bunkers, cranes and new building, etc.)
The construction of a new cell (monofill) and the closure of two (2)
other monofills at the Facility, as well as the closure of a 170 acre
landfill in North Miami (Munisport). At Munisport the groundwater was
impacted by ammonia, and because of concerns as to how the ammonia would
have impacted a Mangrove preserve adjacent to the site, a two-step
biochemical reaction process was employed to convert the ammonia a
nitrate and then to nitrogen gas.
Client Service Manager (CSM)/Supervising Engineer (Other Administrative
Duties):
In my role as CSM, staff and I conducted countywide inspections of all
Solid Waste facilities, provided technical evaluations, financial
assessments and construction management and inspection of Capital Expansion
Projects (Retrofit and Additional Improvements) at the Miami-Dade County
Resources Recovery Facility. Other responsibilities included the
supervising of the compilation of the Department's countywide systems
reports, annual inspection reports (Waste to Energy Facility), landfill
capacity analysis reports, and landfill closure, long-term care cost
estimates and the Comprehensive Landfill Closure Plans for two landfills.
My responsibilities also found me working with County Task Managers
assigned to individual Work Orders to ensure that good quality work
products were delivered to the Department on time and within budget.
STORMWATER AND WASTEWATER PROJECTS
EGSC Engineering Consultant: Miami-Dade County, Florida September 2009 to
June 2011
City of Sweetwater Stormwater Improvement Project, Phases II A and IV. -
Expansion of the existing stormwater infra structure ($5.7 and $4.0
million, respectively)
Project Manager: Responsible for preconstruction and construction
administration. The construction assignment included the inspection of
work carried out by the contractor, compiling daily reports and monthly
project status reports, processing progress payments, RFIs, RFPs and
liaising with the design engineer (Craig A. Smith and Associates), public
utility vendors and the city's Maintenance and Capital Projects Divisions.
Included on these improvement phases were the construction of four (4)
undergrounnd pump stations, the installation of pipes sized from fifteen
inches (15") to eighty four inches (84") in diameter, various types of
concrete inlet structures, manholes, a new head wall at the SFWMD's C-4
Canal, electrical appurtenances and asphalt restoration and overlay of the
streets impacted within the project's footprint. Four (4) new generators
were provided as standby power, one for each pump station. The constructed
improvement is comprised of a force main and a gravity system.
City of North Port Wastewater Treatment Plant Upgrade - 2008 Expansion of
the 3.7 MGD Facility to a 7.0 MGD ($23 million)
Senior Project Manager: Provided construction administration as the
projects's resident engineer. The assignment included the inspection of
work carried out by the contractor, processing progress payment, RFIs, RFPs
and liasing with the design engineer (Brown and Caldwell) and the city's
Utilities Division. Included in this expansion was new yard piping, the
costruction of a new clarifier, new headworks, anoxic basins, effluent
fliters, chlorine contact tank, a reuse tank, the refurbishment of existing
facilities and installation of new equipment.
BND Consulting Engineers; Miami-Dade County, Florida April 1994 to
March 1997
Phase II Expansion, North District Wastewater Treatment Plant, Miami-Dade
Water and Sewer Department (WASD), Florida ($65 million)
Construction Manager: Responsible for project management and contract
administration (updating schedules, tracking and processing RFIs, RFPs,
monthly progress payments, as-build drawings, change orders, and work
directives). I was in charge the inspection team, coordinating and
supervising the contractors, sub-contractors and suppliers. Detail of work
on this project included:
Contract No. S-486, WASD, Florida
Supervised the construction of a moving screen facility, deep injection
well pump station, meter vault, junction box, pump stations, electrical
duct-banks, lift stations, new roadway and the installation a of 96 inches
diameter pipeline and appurtenances. The installation of seven vertical
turbine pumps; HVAC, four RTUs, MCCs, pump drives, hydrostatic accumulator,
surge tanks, and general instrumentation. Construction of the moving
screen facility, deep injection well pump station, meter vault, junction
box and pump stations included:
Excavating to formation elevation within cofferdams, pumping tremie
concrete to anchor the foundations associated with various structures
mentioned above, pumping water from the top of the tremie, drilling and
installing anchors for the reinforced concrete foundation that supports
these structures, check and verify that reinforcement are sized, cut,
spliced and spaced correctly in columns and walls, that formwork is
properly designed and firmly installed, that concrete is vibrated
adequately during pour and that location is clean prior to pour. Checked
rebar distribution and spacing in the walls as well as the stability of
formwork during the concrete pour. The approval of the pour methodology was
also in my jurisdiction.
Contract No. S-428 A and B, WASD, Florida
Supervised the construction of a 160 feet diameter primary clarifier
(concrete), clarifier dome and all interior mechanical equipment; concrete
enclosure for an odor control facility; Oxygenation Trains, flow-meter
chamber, roadway, french drains and the laying of 72 inches diameter pipes
and appurtenances. Construction of the clarifier, odor control building,
Oxygenation Trains and the flow-meter building included:
Excavating to formation elevation within cofferdams, pumping tremie
concrete (850 C.Yds.) to anchor the foundations associated with the
clarifier mentioned above, pumping water from the top of the tremie,
drilling and installing anchors in the tremie for the reinforced concrete
foundation that supports these structures, check and verify that
reinforcement are sized, cut, spliced and spaced correctly, that concrete
is vibrated adequately during pour and that location is clean prior to
pour. Checked rebar distribution in columns and spacing in the walls as
well as the stability of formwork prior to and during the concrete pour.
Here as well I approved the concrete pour methodology.
Contract No. S-428 C, WASD, Florida
Supervised the construction of two (2) 160 feet diameter secondary
clarifiers (concrete) and domes, two return sludge (RS) pump stations, one
return flow sludge distribution chamber, new roadway and the laying of
pipes and appurtenances up to 96 inches in diameter. Construction of the
clarifier, return sludge pump stations and the return flow sludge
distribution chamber included:
Excavating to formation elevation within cofferdams, pumping tremie
concrete (850 C.Yds.) to anchor the foundations associated with the
clarifier, pumping water from the top of the tremie, drilling and
installing anchors for the reinforced concrete foundation (4 feet thick)
that support the clarifier, checked and verify that reinforcement are
sized, cut, spliced and spaced correctly, that concrete is vibrated
adequately during pour and that location is clean prior to concrete pour in
all the structures Check rebar distribution and spacing in the walls as
well as the stability of the formwork during the concrete pour. I also
approved the concrete pour methodology.
Also included in this contract was the installation of RS pumps,
mechanical equipment, variable frequency drive pumps, motor control
centers, duct-banks and general instrumentation.
Contract No. S-501, WASD, Florida
Responsible for the supervision of the construction of a new two story wing
for the maintenance building, and a new fuel dispensing station plus the
removal and disposal of the existing underground storage tanks.
Details of the maintenance building construction included:
The excavation for a strip foundation and column footings per the design
drawings, the placing of formwork and reinforcement along the foundation's
periphery, the column footings, grading of the floor area to formation
elevation, pouring concrete foundation, performing slump tests on concrete
and establishing surveying datum for the general contractor. The
perimeter wall of this two-story structure is of concrete masonry units
(both levels) with rebar at 16 inches on center, a slab on grade and
concrete floor on the upper floor.
Contract No. S-614, WASD, Florida
Also supervised the drilling for and installation of four (4) deep
injection wells, each to a depth of 3,000 feet to complement the deep
injection well pumping station, and the construction of buildings to house
instrumentation and appurtenances for the deep injection wells.
WATER PROJECTS
Curator-Hill Water Supply: National Water Commission (NWC) Jamaica
WI ($2.5 million)
January 1979 to August 1989
Resident Engineer: Provided daily supervision of site-inspectors,
contractors and their teams. Compiled daily, weekly, and monthly project
status reports for three contracts, liaise with consultants and effectively
manage the construction of a half million gallon reinforcement concrete
reservoir, four miles of 6" and 4" diameter ductile iron pipes, and a
20,000 gallons elevated steel tank.
Eastern St. Thomas Water Supply: NWC Jamaica WI ($12 million)
Resident Engineer: Responsible for daily supervision of three contracts,
site-inspectors, project administration, and liaison with consultants.
Compiled as-built drawings, checked elevations and test facilities during
the construction of a 100,000 gallons steel-tank; inspected the
construction of three miles of 12 inches diameter pump main, 8 inches and 6
inches diameter pipeline and a pump station at spring source. The project
was taken to commissioning stage.
NWC Jamaica WI ($ multi-million)
Senior Engineer: Commissioning and general maintenance of constructed
facilities on the Greater Mandeville Water Supply Project, a project
financed by the Inter-American Development Bank (IADB) and World Bank.
Responsibilities included the supervising of Site Inspectors during the
construction of numerous small water supply projects.
Greater Mandeville Water Supply: NWC Jamaica WI
Project Engineer: Site-Engineer engaged in the supervision of the
construction of transmission pipelines and storage facilities. Supervised
the construction of six (6) half million gallons reinforced concrete
reservoirs, the laying and testing of 4.5 miles of 20 inches and 18 inches
ductile iron pipes for a pump main with a maximum head of 1,150 feet, the
construction of two vertical turbine deep-well pump stations; each with
vertical electrical prime movers and 4.16KV power supply, 500 HP and 600 HP
motors, automatically charged compressed air surge tanks, instrumentation,
and remote control telemetric system. Provided back-up supervision for the
construction of two other reinforced concrete reservoirs each 25 and 1.0
million-gallon capacity respectively.
EARTHWORK PROJECTS
Florida Site Development, Pompano Beach, Florida January 1990 to January
1991
Project Estimator: Responsible for quantity "take-off". Quantities were
used in bidding on new projects.
Other Assignments/Projects
City of North Bay Village, Miami-Dade County, Florida January 1991 to
April 1994
Assistant Public Works Director: Responsible for repair and maintenance
of the city's: sprinkler systems, water supply system, main sewer plant,
three sewer sub-stations, an in-house gas and diesel dispenser and general
maintenance of various physical facilities belonging to the city.
Miami-Dade County Aviation Department, Miami International Airport, Florida
2003 (February through May)
Supervised the closeout of a construction contract involved with the
installation of a 12 feet by 8 feet box culvert on the North-side Utilities
Project.
Awards:
National Deans List 1992-1994
Who's Who among American students 1992-1993
Recchi American/MIA Association Joint Venture Scholarship
Honorary Member Phi Kappa Phi
Honorary Member Golden Key Honor Society