Timothy A. Ridens

**** * **** ****** ******* Texas 79423

Cell 512-***-****

E-mail accbga@r.postjobfree.com

****-**** ******* ************** ****** Building Corp.

SL loop 289 Reconstruction

Responsible for the demo and of exiting bridge and

construction of new bridge 1000 ' long in its Place. Also

coordination of subs on the project. Time cards and schedule

for project of multiple crews. Multiple drainage structures.

2011- 2012 Project Superintendent Price Construction

Cottonwood to Dermott Transmission line

Responsible for daily reports, Daily time, and

calling in Dig Test, getting TXDOT permits

Coordinating crews and work being done from Gate

installations & grubbing of R.O.W.

160' wide for the length of the project.

Getting Grubbed R.O.W. brush piled up on the R.O.W

and out of why of towers.

Conducting safety meeting. Also coordinating haul

trucks to move equipment on this

Project which was 74 miles long. Collecting

quantities and getting them turned in for

Payment.

2010-Oct.2011 Project Manager Price Construction

Big Lake Texas, Oil Fields

Responsible the scheduling of equipment and man power to clear

land and grade the location for base for oil rigs to drill new

wells. Making sure mobile crushers are in the right caliche

pit to crush base for location. There are 5 oil rigs that we

are building new locations For. Inputting all of the labor and

equipment hours into Heavy Job system program and E-mailing to

main office. Scheduling repairs for equipment as needed. Also

making sure that billing for locations are correct and signed

for and turned into office in a timely matter.

2009-2010 Project Superintendent/Project Manager, W.W.Webber, LLC

Tom Green County, SL 306 Widening

Responsible for Scheduling and the construction of

the widening of SL 306 and the

Construction of the four Bridges, Two of them

crosses the Concho River. Also making sure it stays on

budget. Coordinating of Sub contractors on the project,

ordering of materials and equipment for the project.

2007- 2008 Project Superintendent/Project Manager, W.W.Webber, LLC

Bexar County, FM 2252 Widening & Loop 1604 Turnaround Bridge

Responsible for Scheduling and the reconstruction of FM 2252

and coordinating of sub contractors. Keeping an eye on the

budget for the project. Also responsible for the construction

of the turnaround bridge at Loop 1604.

2004 - 2007 Structural Superintendent, Granite, Myers, Rados

Garden Grove Freeway, SR22, HOV Project

Responsible for scheduling and supervision of a fast-trac

job, that involved constructing approximately 15,000 lf

of retaining walls, within 6 miles of the project, with

fractured ribbed texture liners. Walls were constructed in

heights that varied from 8 to 30 feet. Construction

supervision responsibilities included construction of three

full replacement bridges, replaced with precast girder

bridges. This work was done with live traffic in two separate

phases. Responsible for Abutments and Columns on the

widening of two other bridges. Handled scheduling and

supervision of construction on Pedestrian Bridge Crossing,

Pump Station, Bridge Barriers, and other structures as

required for completing the project.

2000 - 2004 General Superintendent, Modern Continental

Del Amo Grade Separation and San Diego Light Rail Trolley Line

Responsible for putting up falsework for five different box

girder bridges. Pipe and wood timber falsework. Responsible

for appx. 6000 lf. of retaining walls. Scheduling

subcontractors and concrete pours. Maintain Fast-Trac

schedule using multiple shifts. Calculate formwork and

materials needed. Layout of foundations and piles for

bridgework.

1998 - 1999 Superintendent, Kajima Engineering

I-5 Widening

Responsible for forming abutments, columns and box girder

bridges. Scheduling layout of concrete pours and daily

manpower. Assisted purchasing to ensure proper materials

were ordered and received. Scheduled and supervised multiple

shifts.

1996 - 1998 General Foreman, Kajima Engineering

Badger Bridge Project

Responsible for scheduling removal of existing drawbridge and

replacement of new lift span. Coordinated the building of 2

new cofferdams needed to retrofit old footings of new

drawbridge. Scheduled and supervised multiple shifts and

concrete pours.

1993 - 1995 General Foreman, Brinderson Industrial

Refinery Clean Fuel Projects: Mobil and Ultramar

Responsible for forming four gasoline storage tanks, Coker

basin and Sulfur storage tank. 3 Million gals. Plus in size.

Scheduled manpower and placement of equipment. Coordinated

building of concrete footings and anchor bolts for refinery

processing components.

1990 - 1992 Carpenter Foreman, Hyman-Mortenson

Los Angeles Convention Center

Responsible for forming all concrete stairways. Scheduled

concrete pours. Prepared timesheets and scheduling multiple

shifts as needed.

1988 - 1990 Carpenter Foreman, Brinderson Industrial

Orange County Sanitation District Co-Generation Plant

Responsible for layout, material and manpower calculation for

building of large motor foundations, mechanical equipment

foundations, and pour in place structures including pump

stations and circular concrete water tanks. Weekly timesheets

and scheduling of multiple shifts.

Computer Skills Microsoft Excel and Word

Certifications CPR/1st Aid Certified

Building Inspection Certificate

10 Hour OSHA



Contact this candidate