Post Job Free
Sign in

Project Manager

Location:
La Fortuna, Provincia de Alajuela, Costa Rica
Salary:
120,000
Posted:
November 02, 2017

Contact this candidate

Resume:

JOHN MELLON

*** ******* *****, *** ********, Florida 32159 USA

Mobile: + (1-845-***-**** Email: ac23a3@r.postjobfree.com

PROJECT MANAGER/SUPERINTENDENT

(Mechanical/Construction)

Accomplished management professional offering extensive experience in project management, sub-contractor management, emergency welding repairs, managing boiler outages, testing, and risk assessment in the mechanical and construction sectors. Expertise in managing projects from inception to completion while maintaining high quality standards as well as adherence to budget requirements. Track record of attaining desired results as per planned construction/project guidelines as well as quality assurance and manpower requirements while regularly reporting status to clients and stakeholders. Unique problem-solving and communications skills along with ability to perform efficiently in diverse environments.

CORE COMPETENCIES

• Risk Management • Strategic Planning and Implementation • Project Planning and Execution • Design Development •

Developing Mitigation Plans • Budget and Quality Management • Schedule Adherence • Contract Management • Preparing

Staging and On-Site Safety Plans • Organizational and Problem-Solving Skills • Mechanical Aptitude • Construction Management • Health, Safety, and Environment Policy • Quality Standards Implementation •

KEY SKILLS

•Leadership and Vision Leading project team through entire project life cycle while ensuring timely completion of project deliverables. Developing overall plan for managing, executing, and controlling project scope, schedules, costs, quality, risks, procurement functions, resource requirements, and communications with internal and external stakeholders.

•Strategic Project Planning Working with project controls and key team members to develop fully-integrated, logical, and optimal project schedule; ascertaining design, scoping, and investment budgets for project as a whole. Controlling services provided and monitoring project progress with respect to delivery timelines and expected profitability.

•Human Resources Management Aligning resources from multiple functions such as engineering, services, sales, product development, finance, and supply chain as well as third parties while ensuring productive working relations; coordinating team members to provide seamless and cost-effective solutions to customers. Skilled in determining manpower requirements, communicating established operational plans as well as scheduling and reviewing work accomplished for attaining accuracy in desired outcomes.

•Client and Operations Management Proficient in executing work with professionalism and safety while meeting client specifications as well as budget and time constraints. An eye for detail in examining work progress, equipment requirements, and site activities to ensure adherence with safety policies and specifications.

Interpersonal and Communication Skills Excellent communicator with fluency in English. Skilled in interacting effectively with people of diverse nationalities; comfortable working in multicultural settings. Demonstrated ability to communicate and build relationships easily with people at all levels of seniority,

CAREER HISTORY

Superintendent AP COM POWER Centralia, WA 2017

TFA-ALSTOM-Bahia Blanca, Argentina 2017

Craft Superintendent – AP COM POWER- West Olive, MI

2016

TFA-ALSTOM-Bahia Blanca, Argentina

Mechanical Superintendent I Skanska 2014

Supervised construction of 2 HRSGs in Newark, NJ. 3/14-5/15

• Handled planning, rigging, welding and testing of all piping on both units.

2015

Project Coordinator I Worley/Parsons

2013

•Addressed outage requirements involving main steam header modification, valve replacement, instrumentation replacement and radiant shield replacement on 2 HRSGs at the Arizona Public Service plant Redhawk units 1 and 2.

•Coordinated welding, x-ray, heat and stress operations while tracking progress on the remaining subs for ensuring smooth completion.

Owner I JDKR Mechanical Inc. 2005 - 2012 Handled role of sub-contractor and project manager for Shirin Construction, New York City (NYC).

1

John Mellon I Mobile: + (1-845-***-**** Email: ac23a3@r.postjobfree.com

•Involved in all outage bids/proposals and scheduling activities as well as directly overseeing all outages.

Handled all R stamp paperwork and procedures,

Directly in-charge for all su b-contractors, material requisition, tooling, welding, manpower, x-rays, and all types of testing.

•Met utility outage coordinators every morning for updating on progress reports including Con Edison in NYC.

•Led 4 major outages at 14th Street Power Plant in NYC, as well as emergency welding repairs on Heat Recovery Steam Generator (HRSG) units 10/20 and conventional units 60/70.

•Managed all boilers, condensers, tanks, and streamlines for Shirin Construction, NYC. Oversaw outages for Astoria Energy and Con Ed System.

Superintendent I Consolidated Edison, Inc. (Con Edison/Con Ed), New York City 2003 - 2005

•Worked on bid proposals of boiler outages at unit 60 (Con Ed, 14th Street Plant) while executing replacement of wall panels, burners, and over-fired air ducts including ordering of tools and material as well as hiring manpower and sub-contractors.

•Led entire team of 20 people and supervised over 400 men for start-up of units 10 and 20 as well as HRSG at 14th Street,

NYC.

•In-charge of entire project; dealt with manpower planning, testing, and arranging material and equipment supplies.

General Foreman and Superintendent I Skanska 2002 - 2003

•Accountable for erection, testing, and completion of 3 peaking units for the Power Authority of the State of New York

(PASNY) from start to completion and testing,

In-charge for hiring personnel and tooling for constructing units as well as turning them over to PASNY.

•Tasked with scheduling crane operations, facilitating material deliveries, arranging manpower, and conducting x-rays and repairs.

Various Projects 2001

Babcock and Wilcox (B&W) Construction

Repaired steam drum at Unit 20 in Astoria Station.

Orion Power Unit

•Responsible for plugging drum and SH value for bringing unit operations on line; reworked on previously decommissioned and ragged hole. Also preheated area and welded it out to 1.5".

General Foreman, ABB

•Acted as in-charge of 2 shifts on a boiler implosion.

•Replaced buck-stays as well as rear walls and repaired burners while completing R-stamp requirements.

EARLY CAREER

Superintendent/General Foreman (Various Projects) 1991-1998

Deltak/B&W/Foster Wheeler/Frank Lill/ABB

Superintendent (Combustion Engineering) 1989- 1990

Aguire Station Unit 1/Guayanyo Station, Puerto Rico

General Foreman (Oil-to-Coal Conversions) 1986- 1988

Central Hudson Units 3 and 4/Danskammer, NYC

Journeyman 1974- 1985

Several fossil and nuclear plants/new installations and outage work

Apprentice 1970- 1973

EDUCATIONAL QUALIFICATIONS

International Boilermakers for Trade School

PERSONAL INFORMATION

Date of Birth: 30th Jul, 1950 Nationality: American

Marital Status: Married Driver's License: American Driver's License

References available on request

2

John Mellon I Mobile: + (1-845-***-**** Email: ac23a3@r.postjobfree.com



Contact this candidate