Post Job Free

Resume

Sign in

Manager Project

Location:
Okemah, OK, 74859
Posted:
March 30, 2013

Contact this candidate

Resume:

CLIFTON A. DAVIS

*** **** ****

Okemah, Oklahoma 74859

Mobile #1-918-***-****

(Personal)

Mobile #2 - (918) 623-

**** (Home)

WORK EXPERIENCE

March 2013 - (Access Midstream) working through Tulsa Inspection

Senior

Welding Inspector working several gathering lines in P.A.

September 2012 - February 2013 (Praxair) working through Wilcrest

Safety Manager on

a 53 mile Pipeline in Louisiana.

April 2012 - June (Shell) working through Wilcrest/Worley Parsons

OSR (On-Site- Representative) tracking progress on Oil

Wells, pipe line gathering

Systems brought to a common manifold.

March 2012 - (Denbury) working through QCS Inspection Services

Field Construction Manager/Chief Inspector planning work

for Tinsley Extension

checking Inventory of pipe yards

February 2012 - (Enbridge) working through Tulsa Inspection

Resources

Site Inspector working on Pipe Line Dig Up`s to Sleeve

areas of concern in Michigan.

March 2010 through December 2011 - (Denbury Natural Resources)

working through

Wilcrest Field Services Field Construction Manager/Chief

Inspector

I was working directly through the Denbury Plano Office

(Chris Moody, contact

Information below) also working with the Management Group

at the Flowood, Miss. Office.

There are several Project names as listed, The Gluckstadt

24-inch Main-Line project,

13-7 12-inch line, Moles Creek Line lowering it per DOT

requirements, 15-Mile Creek lowering

and overseeing the building of a Box Sag at the Creek

Crossing, DRI-DOCK a new 24-inch line

installed from the well site areas to Tie-in at the

Barksdale to Brandon Main Line beside

Highway 25. Repair some areas in an 8-inch pipe Line this

project was being managed close to

assure this line is done in a timely fashion coordinating

with Operations for as little down time

as possible. My duties were to manage the Contractor

scheduling the project, assuring all

permits are obtained; As-Built Drawings are being

maintained, placing Inspection at the needed

areas assuring all reports, MTR`s and Testing are

maintained and current.

I do maintain all of the needed folders and reports,

organized in binders assuring they are

Complete at the end of each project.

February 2010 through March 2010 - (Spectra Energy) working

through Lonquist

Engineering Field Construction Manager/Chief Inspector.

The Contractor did work

over a Disposal Well, Pulling the tubing and casing,

install some new casing to replace

damaged casing.

December 2009 through January 2010 - Project name (Clarksburg

Compressor Station)

Gas Compressor Station, the ownership of this project

is Exterran

I did work through Alliance Inspection Company working

as a Field Construction

Manager/Chief Inspector

July through October 2009 - Project name (Eunice Reverse Flow)

Gas Compressor Station, the ownership of this project

is Trans Canada/ANR

Field Construction Manager/Chief Inspector working

directly with the Client

To assure the project is completed with the Quality

Assurance and in a timely manner.

October through February 15 2009 - Project name (Des Plaines

Compressor Station)

Gas Compressor Station, the ownership of this project

is Trans Canada/Northern Border

Senior Welding Inspector I was overseeing all of the

fabrication and installation of the

piping off the mainline, Compressor building,

Electrical skid, Mechanical skid and Utility skid.

August 8, 2008 through October - Project name (O'Brian #1- 6

Lateral)

Gas Pipeline Project, The ownership of this project

is Chesapeake Gas.

Chief Inspector I did oversee the Contractor install

about 8 miles of 14-inch pipe from

two wells to a gathering system and a compressor. I

was responsible for all of the

environmental and safety concerns of this project

acting as the EHS officer as well.

July 9, 2008 through July 27, 2008 - Project name (Pine Hollow

Project)

Gas Pipeline Project. The ownership of this project

is the SIMS GROUP.

Chief Inspector I did oversee the Contactor build a

Station Pad with dirt to

Set the compressors and skid units for measuring the

gas as it is transported.

SIMS GROUP had some internal problems and decided to

cancel this project until a latter

Date.

March 2008 through July 9, 2008 - Project Name (REX EAST) Gas

Pipeline Project

The ownership of this project is shared with Kinder

Morgan,

Conoco Phillips and Sempra gas companies.

Assistant Construction Manager over the app.200

miles through Ohio my

responsibilities were to coordinate construction

with the Contractors and the gas

company working through the Ohio area also acting as

the head EHS officer for this

portion of the project.

March 2007 through February 2008 - Project Name (REX WEST) Gas

Pipeline Project

The ownership of this project is shared with Kinder

Morgan,

Conoco Phillips and Sempra gas companies.

Safety Manager for the (7) spreads of this project

my responsibilities

were to insure the Contractors are working under

the guidelines

set forth in the contract. I was responsible for

all incident reporting

with the head quarters of the operations. I did

write all of the

safety manuals and procedures for this project.

June 2006 through March 2007 - Project Name (REX Entrega) Gas

Pipeline Project

Kinder Morgan through Gulf Interstate

Safety Manager on (2) spreads of pipeline from

Wamsutter,

Wyoming to Cheyenne, Colorado. Responsibilities were

to assure

the inspection company is documenting any and all

safety violations

and the contractors are adhering to the safety

policy required by

Kinder Morgan. I do investigate all incident,

accidents recorded and

try to find a resolution to the problem or concern.

August 2005 through June 2006 - Kinder Morgan through Gulf Interstate

Field Construction Manager/Chief Inspector

of (9) new storage tanks (1) water tank and (1)

Vapor recovery tank being built, Ensuring the

quality workmanship

of the tanks, reviewing all the radiograph film and

witnessing

any N.D.E. required. Responsible for as built

drawings, film trazabilty and

all documentation, also watching piping and

instrumentation installation.

February 2005 through August 2005 - Onsite Welding &

Fabrication

QA Manager oversee the shop fabrication and assure

the quality of

workmanship. Interpreting film and writing

procedures as required.

March 2004 through February 2005 - Cherokee Architectural

Field Supervisor and Quality Control Manager

August 2003 through December 14, 2003 - Enbridge through Gulf

Interstate

Chief Inspector: shop fabrication. Ensuring quality

workmanship and

construction of tanks being fabricated and pipeline being

constructed.

March 24, 2002 through August 2003 -Enbridge through Gulf

Interstate

Chief Inspector

Insured the quality of the work and the safety of the men,

Ensuring quality

workmanship and construction of tanks being fabricated and

pipeline being

constructed

January 26, 2002 through March 20, 2002- Forerunner Corp. Lakewood,

Colorado

Chief Inspector for 25 miles pipeline and (1) metering station

December 15, 2001 through January 26, 2002- Epstein & Sons

International-

Chief Inspector of a shop fabricated metering station. I was

also the

EHS officer responsible for the safety and

environmental expectations.

November 4-December 14, 2001-Vector Pipeline (through Gulf Interstate

Field Services)

Welding Inspector reading all radiographs and insuring the

quality of the

welds.

July 2001 -September 26, 2001 - Enbridge Pipeline (through Gulf

Interstate Field Services)

Welding Inspector, Station Inspector and Chief Inspector on pre-

build job.

December 1, 200 thru February 10, 2001 Vector pipeline Company (through

Gulf Interstate Field Services)

Welding Inspector for all work fabricated in the

shop for 3 different metering

stations (Laporte, Wheeler & Crown point)

Insuring the quality of welds, checked

radiographs all N.D.E., a liaison between the

project engineer and the field

Inspection.

January 1, 2000 thru October 31, 2000. Vector Pipeline Company

(through Gulf Interstate Field Services)

Safety Manager. Monitored safety on mainline and meter station

construction activities associated with Spreads SH-1 and SH-2A

on the U.S. portion of Vector's 42-inch gas pipeline system from

Joliet, Illinois to Dawn, Ontario.

March, 1999 - December 31, 1999: Lakehead Pipe Line Company, SEP II

Project (through Gulf Interstate Field Services)

Welding Inspector. Worked on LPL's System Expansion Project II

(SEP II) performing dimensional and visual weld inspections.

Reviewed all X-rays and dimensions in accordance with the job

requirements.

October, 1998 - December, 1998: Lake head Pipe Line Company, Terrace

Expansion Project (through Fluor -Daniel, Inc.)

Welding Inspector. Welding inspection on the firing line and

tie-ins.

May, 1998 - September, 1998: Lakehead Pipe Line Company,

(through Gulf Interstate Field Services)

Chief Inspector Worked at Lakehead's Clearbrook Station near

Clearbrook, Minnesota, on the installation of a new fire

protection system. Performed dimensional and visual weld

inspections. Reviewed all X-rays and dimensions in accordance

with the job requirements.

February, 1998 - May, 1998: Sagebrush - Sapulpa, Oklahoma

Night Lead Man and Fitter. Performed all phases of fabrication,

layout of vessels, and fitting external components, shells,

heads, nozzles, and structural components.

January, 1998 - February, 1998: Matrix - Catoosa, Oklahoma

Shop Supervisor. Shop Supervisor over the vessel department.

checking dimensions and ensured the quality of work performed.

October, 1997 - December, 1997: Zephyr Southwest - Tulsa, Oklahoma

Field Supervisor and Quality Control Manager. Traveled

extensively supervising field crews in different states,

checking and maintaining quality of work performed. Meeting

requirements of each state's standards and specifications.

February, 1991 - October, 1997: Fabwell. - Sapulpa, Oklahoma

Quality Control (shop inspector). Assured the quality of work

by checking layout and fit-up and performing weld inspections,

reading radiograph film and performing all NDE duties.

Fitter / Welder. Performed all phases of fabrication, layout of

vessels, and fitting all external and internal components,

including ladders, platforms, and all structural components.

August, 1990 - February, 1992: Advanced Precision Fabrication

- Tulsa, Oklahoma

Quality Control (shop inspector). Performed dimensional and

visual weld inspections and witnessed hydrostatic function

testing of pressure vessels, vulcanizers, and process gas

boilers. Verified satisfactory performance of non-destructive

testing methods. Reviewed quality verification documentation,

such as MTRs, heat treat charts, NDE reports and performance

test results for conformance to applicable requirements.

EDUCATION

Mounds High School, Diploma -1979

Tulsa Junior College, Certificate - Computer Skills, 1995

Tulsa Junior College, Associate of Science Degree (Pending) - Quality

Control

OSU Okmulgee Tech, Associate of Science Degree (Pending) - Quality

Control

OTHER PROFESSIONAL DATA and TRAINING

CWI classes certification CAWI #09120524

OSHA 500 - Certificate

Environmental- Certificate

CPR and First Aid - Certificate

Respiratory Protection Training - Certificate

Hazwoper Awareness Training - Certificate

Miosha Confined Space Training - Certificate

Capital X-Ray - ASNT Level II, Radiography, Film Interpretation and

Evaluation

John Edwards Services - ASNT Level II, Magnetic Particle,

Interpretation and Evaluation

John Edwards Services - ASNT Level II, Liquid Penetrate,

Interpretation and Evaluation

Advanced Inspections - ASNT Level II, Ultrasonic Testing

Tulsa Community College-B31-1, B31-2, Section 8, Section 9 and API

1104

Please feel free to call any of my references to inquire about my work

References;

Chris Moody

Denbury Natural Resources

Office 972-673=2171

Cell 713-***-****

Marty Hudson

Cell 904-***-****

P. Joe Reid

Reid Construction

Cell 601-***-****

Donald Case

Denbury Natural Resources

610-***-****

Joshua Riese

Chesapeake Energy

CeII 616-***-****



Contact this candidate