D esignation – Erection & commissioning engineer (site

e ngineer)

SiteEngineer

Objective

To enhance my working capacities, professional skills, business Efficiencies and to

serve my organization in best possible way with sheer determination and

commitment

B. Tech in Electrical Engineering along with the knowledge of several hardware tools

and programming languages, I possess an ability to analyze complex engineering

p roblems, evaluate and recommend alternatives and communicate recommendations

effectively seeking a full-time position.

P rofessional Summation

P resently working in Jaypee Nigrie Super Thermal

Power Plant 2x660 MW from jan 2013 to till .

Presently looking Boiller-1, DM Plant, ESP,Intake & Raw water. All Erection

& Commissioning of this area.

Background in the principles and practices of Electrical Generation.Excellent

supervisory experience, including setting goals and objectives, planning and

organization & operation.

In-depth knowledge of Power Generation & Electrical Power Distribution (LV/MV

T YPE) & (HT/LT TYPE)

Detailed knowledge of CHP, Cable Routing & Scheduling along with the knowledge of

ESP, BOILER & SWITCHYARD OF 400kv

Earthings & Lighting Layout Installation of Cable Trays on pipe racks, inside substations

and on conveyors

Focused on work quality and excellence in client service

Experienced in Electrical Engineering Service Areas respectively – CONSTRUCTION &

T ESTING

Elaborated Work Experience with Key Accountabilities

1 year 11month of experience in Electrical Engineering (Thermal Power

P lant)at I deas Engineers P rivate Limited, Aurangabad.

P roject: 2X300MW Thermal Power Plant (Coal Handling Plant)

Job Site: GMR E MCO LTD., CHP

Project Activities: T ransformers & Panels

Erection, Testing & Commissioned of 4nos of LTMCC(415) & 1nos HT(6.6kv) panel As

per scheme & relay logic of LT & HT panel

Commissioned Mobile Crusher, travelling t rippler, Wagon t rippler& S/R with all

p rotection

Commissioned conveyor for coal feeding with MD, belt scale, PCS & BCS

Erected & commissioned 1 No’s of 2 MVA Dry Type Cast Resin, Vector Group: Dyn11,

Voltage Ratio (HV/LV): 6600V/433V Transformer according to TCE standards in Stacker

Reclaimer& testing of transformer

Erected & commissioned 4 No’s of 2.5 MVA & 1.25 MVA Transformer oil type & done

testing of the transformer’s

Erection as well as commissioning of 66/33 KV switchyard

Installation Transformers, Switchgears, Control Panels, VFD,PLC, HT, PDB, MLDB,

WDB, ACDB, DCDB,VBMS,HOIST PANEL, MD and MCC panel

Installation of 4no’s bus duct for transformer to LTMCC panel

H igh & low voltage cable laying

Responsibilities

Overall responsibility for site work, installation

Installation of temporary construction power and lighting network in consultation with

t he operation group

Installation of Cable Trays inside conveyors, substations, Station Control Room (SCR)

Providing primary and secondary supports to the routes of cable tray

Laying of cables for HV, LV power distribution

Laying of control cable

Meggering of bus duct, LT & HT panel, cable, panel bus bar and continuity test

Installation and making operational different lighting fixtures on building, platform &

concourse Level & also under craft level

Inside substation, control room and office lightening with false ceiling

Sizing / Selection of Power Cables, Control Cables, Breakers, Fuse Unit, CT/VT, Cable

L adder / Trays, Cable Trench, Cable Glands, MCT Frame & Modules, to name a few

Conducting site visit and collecting information required for t ie-in projects with existing

facility and expansion

Installation of cable t rays & conduits

HV & LV Cable laying & also glancing along with termination for it

Installation, testing & commissioning of area light

Maintained effective working relationships with field crews, contractor, outside agencies,

t he public and city staff members

Responsible for on-site work, including construction administration and electrical

engineering consultation and performed quality assurance and control

Installation of ELCB, MCCB, LA, CT, PT, PLATE, PIPE & EARTHING and man power

management

Attending meeting with Clients & Consultants about the technical problems and solve

t hem

Reviewing drawings and necessary co-ordination

Preparation of Technical submittal schedule, Submission and follow-up for approval

Check other discipline drawings, review vendor documents, to name a few

Attending meetings with contractor and providing design clarifications during

construction of projects and provide the technical support for all project execution

Preparing sketches and coordinating with draughtsman to decide cable routing, Location

of push button, lighting, finalizing substation equipment layout and finalizing electrical

d rawing with consultants and planning for meter panel, HT/LT and PCC panel drawings

a long with the electrical consultants

Academic Details and Technical Proficiency

B. Tech in Elect rical Engineering from Rajashtan Technical University,

J aipur Engineering College (JEC KUKAS, JA IP UR)

Done D iploma I n EEE F rom Govt Of Sikkim,CCCT Chisopani, South Sikkim.

P rograming languages: C, C++, Java, DSA & DB MS

Ha rdware Languages: M icroprocessor 8085, Embedded Systems,

M icrocontroller 8051, PLC

Ha rdware: Assembly, I nstallation & M aintenance of PC, Power Supply, SMPS,

N etworking, maintenance of electronic equipment

Software Packages: MS Office (MS- Word, Excel & PowerPoint), P roteus &

M AT LAB; Platforms: Windows Vista/XP/2000/2003/2008/Windows 7

Personal

D ossier

Date of Bi rth: 18th November, 1990

Fathe r’s Name: Gau ri Shanker Singh.

Sex: M ale

Languages P roficiency: English, H i ndi & Nepali

Nationality: I ndian

Ma r i tal Status: Singl

P assport no - K 0634529.

D eclaration

I h ere b y d ecl a r e t h a t t h e i n fo r m a t ion p r ov i d ed by m e i s t r ue t o t h e b est

of m y k n ow l ed ge.

( Abhishek Kumar Singh )



Contact this candidate